HomeMy WebLinkAboutI - 07 County Review & Recommendations - CP Read Realty LLC1 Cortland County Planning Department ROBERT CORPORA 60 Central Ave • Cortland, New York 13045-2838 County Administrator Telephone: (607) 753-5043 email: administrator@cortland-co.org General Municipal Law (GML) 239 Report ______________________________________________________________________________________ TO: Cortland County Planning Board November 10, 2022 FROM: Cortland County Planning Department RE: GML #86.13-01-32.000– Site Plan Review & Aquifer Protection Special Permit _______________________________________________________________________________________ Applicant: CP Read Realty, LLC 3975 NYS Route 281 Cortland, NY 13045 Owner: CP Read Realty, LLC 3975 NYS Route 281 Cortland, NY 13045 ______________________________________________________________________________________ SYNOPSIS - Site Plan Review & Aquifer Protection Special Permit review for the purpose of constructing a 6,000 square foot retail store and associated parking on an existing partially developed site. The property is described as 3975 NYS Route 281 (Tax ID 86.13-01-32.000) within the Town of Cortlandville. It is zoned B-2 (Highway Commercial Business), is within the Aquifer Protection District, and is within the Wellhead Protection Area District (Zone 1a) in accordance with the Code of the Town of Cortlandville, hereafter the Code. The site plan review and aquifer protection special permit review is being referred to the Cortland County Planning Board because the property is located within 500 ft. of NYS Route 281, NYS Route 222, & Kinney Gulf Road (County Route 111). ______________________________________________________________________________________ ANALYSIS - The applicant is requesting a site plan review & aquifer protection special permit so they may construct a 6,000 square foot retail store and associated parking on an existing partially developed site. Retail stores are permitted in B-2 (Highway Commercial Business) districts subject to site plan review. Since the applicant is proposing to build a retail store, they have applied for a site plan review. §178-46 (B) requires any development, other than residential, within the Aquifer Protection District exceeding $150,000 in development cost to obtain an aquifer protection special permit. As this development exceeds $150,000 in development cost, the applicant has also applied for an Aquifer Protection Special Permit. The county planning board has previously reviewed two GML referrals on this property. The first, in September 1996, was a conditional permit and special permit to construct a 14,000 square foot addition onto an existing 6,400 square foot building. The county planning board recommended approval of the application with three contingencies. The addition was never built and the referenced 6,400 square foot building is now the Meldrim’s paint center store currently on the property. The second application, in November 1998, was for a site plan review, aquifer protection district special permit, and subdivision to construct a 12,738 square foot drug store with drive-thru facilities. The county planning board recommended approval of the application with six contingencies. The proposal subdivided off and constructed what is now the Rite Aid Pharmacy next door. 2 §178-2.3 D of the Code outlines prohibited uses and activities in Wellhead Protection Area District Zone 1a. The proposed retail store does not involve any of said prohibited uses and activities, therefore it complies with §178-2.3 D of the Code. §178-2.4 (A) (1) requires parcels in Wellhead Protection Area District Zone 1a to provide at least 50% greenspace. The site plan shows that the proposed retail store will decrease the parcel’s greenspace to about 42%, however §178-2.4 (A) (4) of the Code allows parcels having areas of three acres or less to provide a minimum of 20% greenspace. As the parcel is 1.77+/- acres, the proposed retail store complies with this section. §178-45 of the Code lists the restrictions and requirements for uses and activities in the aquifer protection district. §178-45 (B) (2) requires bulk storage of toxic substances or hazardous materials be subject to compliance with Article XVIII of the Sanitary Code of the Cortland County Health District. The proposed retail store will be a paint store. Certain paints can be considered toxic or hazardous. It has been determined that the store will not store paint in bulk, therefore §178-45 (B) (2) does not apply. It should be noted that §178-45 (B) (1) & (2) both refer to now-unrelated articles of the Sanitary Code of the Cortland County Health District. The Cortland County Health Department no longer regulates the bulk storage of petroleum, toxic substances, or hazardous materials. That is now regulated by the NYS Department of Environmental Conservation (DEC). It is therefore recommended that the Town consider revising §178-45 (B) (1) & (2) of the Code to refer to NYS Department of Environmental Conservation (DEC) regulations instead of Cortland County Health regulations. The proposed retail store otherwise complies with this section. §178-71 of the Code outlines the information required for applications for site plan review. Most of the required information is present in the submission, however the location of fire/emergency zones, the location and design of outdoor lighting facilities, and a general landscaping plan / planting schedule are missing. It is therefore recommended that the applicant provide an updated site plan to the Town including a lighting plan, general landscaping plan, and, if necessary, the locations of emergency zones / fire hydrants. §178-72 A of the Code outlines general considerations the planning board should contemplate for site plan reviews. These general considerations include the site compatibility of lighting, the adequacy of landscaping constituting a visual and/or noise buffer, and the adequacy of protecting neighboring properties against noise / glare / unsightliness. These considerations are especially important when there are neighboring residential properties, such as those to the north of this proposal. It is therefore recommended that the Town review the updated site plan to ensure adequate protection of neighboring properties, especially those which are residential, against noise, glare, or unsightliness. Further general considerations in this section include the adequacy of emergency zones / fire hydrants and the adequacy of structures / roadways / landscaping in areas susceptible to flooding / erosion. It is recommended that the updated site plan be reviewed and approved by the Town of Cortlandville Fire Department. §178-90 of the Code requires the applicant to prepare a stormwater pollution prevention plan (SWPPP) before initiating any land clearing, land grading, earth moving, paving, property subdivisions, or construction or development activities, where such activities otherwise require a special or conditional permit, or site plan review. As the applicant has not provided a SWPPP, it is recommended that the applicant prepare a storm water pollution prevention plan (SWPPP) in compliance with the Town of Cortlandville stormwater ordinance (Article XVI of the 1985 Zoning Law of the Town of Cortlandville, Cortland County, New York) and provide it to the Town for review and approval. 3 The Coordinated Review Committee (CRC) reviewed this proposal and addressed the following issues: 1. Kathy McGrath, NYSESCCP Water Quality Specialist at the Cortland County Soil & Water Conservation District, had multiple comments: a. This property is in Cortlandville Wellhead Protection Zone 1A, the drinking water zone with the shortest travel time to a public water supply well and therefore with the greatest consequences if a contamination incident were to occur. Dry Creek has the potential to contribute flow to groundwater, which would represent a direct contaminant conduit to groundwater. Management of all chemicals during construction, such as petroleum products, will be critical to avoid potential for release into the creek or onto the ground. b. All construction activities should avoid discharge of any materials including sediment or nutrients into Dry Creek. Basic erosion and sediment control practices should be employed during construction to ensure that sediment does not reach the creek or adjacent properties, including [Route 281]. Discharge of contaminants into the creek channel, even when not flowing, will ultimately be carried downstream to the West branch Tioughnioga River. c. There is considerable Zone AE [100-year] floodplain on the property associated with Dry Creek. It appears that both proposed stormwater basins are at least partially in the Zone AE area. This is not recommended because flood storage and treatment area may not be available if already flooded from a second source, and, floodwaters can damage or contaminate stormwater management facilities. d. The Dry Creek channel is on or immediately adjacent to the property. Construction should not damage the riparian corridor, destabilize the river banks, or result in release of contaminants including sediment to the creek channel. Mature trees are present along the creek frontage. This vegetation provides critical bank stabilization and should not be damaged or removed. e. The entire property is classified as Prime Farmland. f. Revegetation and landscaping details were not provided. We recommend the use of New York native non-cultivar species for any landscaping other than lawn grass. These species are much more effective at supporting ecological values such as pollinators and songbirds than are non-native species and cultivars of native species. 2. Mike Ryan, P.E., Director of Environmental Health at the Cortland County Health Department, commented that Environmental Health’s only concerns are related to the possible well contamination referenced by Kathy McGrath above. He would like to reiterate those concerns. 3. Julie Melançon, CPESC, Environmental Program Specialist II at the NYS Department of Environmental Conservation, had multiple comments: a. Since the proposed disturbance is less than 1 acre, coverage under the GP-0-20-001 (Construction Stormwater General Permit) is not required. If the scope changes and disturbance is greater than one acre, there are addition items that would need to be addressed: i. A NOI and Full SWPPP would need to be developed before disturbance 4 goes over the acre. ii.GP-0-20-001 does not allow for placement of post-construction stormwater controls in the FEMA 100-year floodplain. iii.A letter of No Effect would be required from SHPO. iv.Please note that GP-0-20-001 does not go into effect until all UPA Permits are obtained for the site. b.It does not appear that disturbance of Dry Creek is proposed, however if the plans change, Dry Creek is classified C(T) in this location. i.Any disturbance to the bed or banks of the creek would require an Article 15 Protection of Waters Permit. Banks is defined as the land area immediately adjacent to and which slopes toward the bed of a watercourse and which is necessary to maintain the integrity of a watercourse. A bank will not be considered to extend more than 50 feet horizontally from the mean high water line, with the following exception: Where a generally uniform slope of 45 degrees (100%) or greater adjoins the bed of the watercourse, the bank is extended to the crest of the slope or the first definable break in slope, either a natural or constructed (i.e., road or railroad grade) feature, lying generally parallel to the watercourse. ii.The Applicant would also need to verify that a federal permit is not required with Army Corps. If a federal permit is required, DEC may need to issue an Individual Water Quality Certification if the work does not meet the blanket water quality cert. Finally, the proposed site plan review & aquifer protection special permit is considered an unlisted action under SEQR. The applicant has therefore completed Part I of the Short Environmental Assessment Form. Parts II & III should then be completed by the Town to determine if there may be any significant adverse environmental impacts as a result of the proposed subdivision. ______________________________________________________________________________________ RECOMMENDATION - The staff recommends approval of this application for site plan review & aquifer protection special permit to construct a 6,000 square foot retail store and associated parking on an existing partially developed site only if the following contingencies are satisfied: 1.that the Town consider revising §178-45 (B) (1) & (2) of the Code of the Town of Cortlandville to refer to NYS Department of Environmental Conservation (DEC) regulations instead of Cortland County Health regulations. 2.that the applicant provide an updated site plan to the Town including a lighting plan, general landscaping plan, and, if necessary, the locations of emergency zones / fire hydrants. 3.that the Town review the updated site plan to ensure adequate protection of neighboring properties, especially those which are residential, against noise, glare, or unsightliness. 4.that the updated site plan be reviewed and approved by the Town of Co1ilandville Fire Department. 5.that the applicant prepare a storm water pollution prevention plan (SWPPP) in compliance with the Town of Cortlandville storm water ordinance (Article XVI of the 1985 Zoning Law of the Town of Cortlandville, Cortland County, New York) and provide it to the Town for review and approval. 6.that all construction activities avoid discharge of any materials or contaminants including sediment, nutrients, and petroleum products into Dry Creek. 7.that the mature trees present along the creek frontage be preserved to the greatest extent practicable to ensure bank stabilization. 8.that the updated site plan including a general landscaping plan use native New York and non-cultivar plant species to the greatest extent practicable. 9.compliance with SEQR requirements. Alex M. Schultz Planner 5 R ert Corpora County Administrator