HomeMy WebLinkAboutPB Packet 12-17-24 - MWII SEQR - PDZ Recom1 DEPARTMENT OF PLANNING 215 N. Tioga St 14850 607.273.1747 www.town.ithaca.ny.us TO: Planning Board Members FROM: Christine Balestra, Senior Planner DATE: December 10, 2024 RE: Cornell University Maplewood Phase II Project – SEQR Determination & Recommendation to Town Board Regarding Proposed Planned Development Zone Enclosed please find the following additional materials associated with the Maplewood Phase II development project: 1. Draft SEQR resolution 2. Revised draft Full Environmental Assessment Form (FEAF) Parts 1-3 3. Draft resolution to the Town Board recommending rezoning from MR/HDR to PDZ 4. Revised draft Maplewood Phase II rezoning PDZ language 5. Revised applicant narrative and drawings, dated 11-15-24 6. Additional revised applicant narrative and drawings, dated 12-9-24 7. Two sheets depicting bicycle storage that were presented to the board on 10-15-24 SEQR The Planning Board, as the Lead Agency in the environmental review of the Maplewood Phase II project, began a discussion of potential environmental impacts at their meeting on September 17, 2024. The Board reviewed a FEAF Part 1 at that meeting (submitted by the applicant) along with draft FEAF Parts 2 and 3 (prepared by Planning staff). Staff highlighted sections of the draft FEAF Part 3 to indicate where more information or additional discussion was needed. The Planning Board provided feedback to staff and the applicant at the 9-17-24 meeting. All questions and highlighted sections from the previous draft FEAF have since been resolved. The attached revised draft FEAF Parts 1-3 contains new red-lined sections to indicate the changes that have been made between the 9-17-24 version and the current version. Site Plan Revisions Some plan sheets that were submitted and previously reviewed by the Planning Board have been revised, based on applicant discussions with the Town’s Code Enforcement and Engineering Departments. The landscaping, site layout, and grading/drainage plans, along with the SWPPP, and the FEAF have been revised to reflect mostly minor revisions to the site layout (e.g., buildings have been shifted a few feet to accommodate Fire Code requirements). The only significant revision is the widening of the proposed walkway between the main parking lots/thoroughfares. The walkway, as previously presented, was not wide enough to comply with NYS Fire Code provisions. Rather than 2 seek a NYS variance, the applicants decided to widen the walkway to comply with code. Based on the modifications, the number of parking spaces has been reduced to 155 (from 161), and there are minor changes to the fire access plans. However, there are no changes to the project that would preclude the Planning Board from making an environmental determination. Rezoning/PDZ Request The Board reviewed the draft rezoning (PDZ) language for the project at their meeting on October 15, 2024. This document has also been revised since the last meeting. The attached version contains revisions that reflect the Board’s comments from 10-15-24 Planning Board meeting; Attorney for the Town comments; and applicant responses to the Board’s suggestions from the 10-15-24 meeting. The Board/Attorney comments are red-lined; and the applicant responses are blue-lined (this is highlighted in the header of the document). The purpose of the December 17th meeting is for the Planning Board to: 1. Consider making a SEQR determination for the Maplewood Phase II project, and 2. Consider recommending the rezoning language to the Town Board. As discussed at the October 15th Planning Board meeting, the Planning Board will hold a public hearing before making their recommendation (per Town Code, §270-181(F)). Please note there is no public hearing on SEQR; rather it is on the recommendation to the Town Board regarding the rezoning request. Please feel free to contact me if you have questions regarding this proposal by phone at (607) 273- 1721, extension 121, or by email at cbalestra@townithacany.gov. Cc: Michele Palmer, Senior Associate, Whitham Planning & Design, PLLC Leslie Schill, University Planner & Director of Campus Planning, Cornell University Jeremy Thomas, Senior Director of Real Estate, Cornell University Scott Whitham, Principal, Whitham Planning & Design, PLLC PROPOSED RESOLUTION: SEQR Maplewood Phase II Project Maple Avenue, Town of Ithaca Tax Parcel No.’s 63.-2-5, 63.-2-6, 63.-2-7.1, and 63.-2-7.3 Town of Ithaca Planning Board December 17, 2024 WHEREAS: 1. This is consideration of a Determination of Environmental Significance for the Maplewood Phase II Project on Maple Avenue, located between the Maplewood Graduate Student Apartment complex and the East Lawn Cemetery. The project, which requires a rezoning from Multiple Residence and High-Density Residential Zones to a Planned Development Zone (PDZ), involves consolidating four parcels and constructing six (6) five-story apartment buildings, containing 615 units/800 beds in studio, one bedroom, and two-bedroom unit configurations. The project will also include integrated amenity/service spaces, parking areas, trails and pedestrian facilities, open spaces, stormwater facilities, and other site improvements. Cornell University, Owner/Applicant; Michele Palmer, Whitham Planning, Design, Landscape Architecture, PLLC, Agent, 2. The proposed project, which requires Site Plan approval and Special Permit by the Town of Ithaca Planning Board and a rezoning to a Planned Development Zone (PDZ) by the Town of Ithaca Town Board, is a Type I action pursuant to the State Environmental Quality Review Act, 6 NYCRR Parts 617.4 (b)(3) and (b)(5)(iii), respectively, as well as Town of Ithaca Environmental Quality Review Code section 148-5B(2) as the project as proposed involves a zoning change and the construction of 250 or more residential units (30 or more per Town Code) that will be connected to existing community or public water and sewage systems, 3. The Planning Board, at its meeting on August 6, 2024, proposed to establish itself as Lead Agency to coordinate the environmental review of the project, and on August 7, 2024, notified potential Involved and Interested agencies of its intent to serve as Lead Agency, 4. The Planning Board, at its meeting on September 17, 2024, established itself as Lead Agency to coordinate the environmental review of the project, after having received no objections from other involved agencies, 5. The Planning Board, at its meeting on December 17, 2024, has reviewed application materials, studies, and a narrative plan set dated 07-19-2024, titled “Maplewood Phase II Preliminary Site Plan Submission,” submitted by Whitham Planning Design Landscape Architecture, PLLC; supplemental materials and drawings dated 08-26-2024, submitted by Whitham Planning Design Landscape Architecture, PLLC; revised materials and drawings, dated 11-15-24, submitted by Whitham Planning Design Landscape Architecture, PLLC; additional materials and drawings, dated 12-9-24, submitted by Whitham Planning Design Landscape Architecture, PLLC; revised draft PDZ rezoning language labeled for 12-17-24 PB meeting; a completed Full Environmental Assessment Form (FEAF) Part 1, prepared by the applicant; and a completed FEAF Parts 2 and 3 prepared by Town Planning staff, and 6. The Town Planning staff has recommended a negative determination of environmental significance with respect to the proposed project; NOW, THEREFORE, BE IT RESOLVED: That the Town of Ithaca Planning Board hereby makes a negative determination of environmental significance in accordance with Article 8 of the Environmental Conservation Law and 6 NYCRR Part 617 New York State Environmental Quality Review for the Maplewood Phase II development project, based on the information in the FEAF Part 1 and for the reasons set forth in the FEAF Parts 2 and 3, and, therefore, a Draft Environmental Impact Statement will not be required. Name of Applicant/Sponsor: Ryan Souls |Sr.Director,Development,Greystar Telephone:843-579-9400 E-Mail:ryan.souls@greystar.com Address:465 Meeting St.Ste 500 City/PO:Zip Code:State:Charleston SC 29403 Project Contact (if not same as sponsor;give name and title/role ): Michele Palmer,Senior Associate,Whitham Planning Design Landscape Architecture Telephone:607-280-6916 E-Mail:palmer@whithamdesign.com Address: 404 N Cayuga City/PO: Ithaca State:Zip Code: 14850NY Property Owner (if not same as sponsor ): Jeremy Thomas,Senior Director of Real Estate,Cornell University Telephone:607-266-7869 E-Mail:jt675@cornell.edu Address: 15 Thornwoood Drive City/PO:Zip Code:State:14850IthacaNY Page 1 of 13 Full Environmental Assessment Form Part 1 - Project and Setting Instructions for Completing Part 1 Part 1 is to be completed by the applicant or project sponsor. Responses become part of the application for approval or funding, are subject to public review, and may be subject to further verification. Complete Part 1 based on information currently available. If additional research or investigation would be needed to fully respond to any item, please answer as thoroughly as possible based on current information; indicate whether missing information does not exist , or is not reasonably available to the sponsor; and, when possible, generally describe work or studies which would be necessary to update or fully develop that information. Applicants/sponsors must complete all items in Sections A & B. In Sections C, D & E, most items contain an initial question that must be answered either “Yes” or “No ”. If the answer to the initial question is “Yes”, complete the sub-questions that follow. If the answer to the initial question is “No”, proceed to the next question. Section F allows the project sponsor to identify and attach any additional information. Section G requires the name and signature of the applicant or project sponsor to verify that the information contained in Part lis accurate and complete . A. Project and Applicant/Sponsor Information. Name of Action or Project: Maplewood Phase II Project Location (describe, and attach a general location map ): 301 Maple Ave, Ithaca, NY, 14850 Brief Description of Proposed Action (include purpose or need): The project is a stand alone expansion of the Maplewood student housing community and is oriented toward Cornell graduate and professional students, similar to the residents of the adjacent community. The site is approximately 9 acres and six five-story residential buildings are proposed that will house approximately 615 units with 800 beds, primarily studios and one-bedroom apartments with a small percentage of two-bedroom. A one-story community center to serve residents will also be constructed. Approximately 155+/- parking spaces are proposed. Greystar, the operator of Maplewood Phase I, is positioned to blend Maplewood Phase I and Maplewood Phase II to create a larger Maplewood neighborhood which will share some services, including street connections, water service, and outdoor amenity space. Revised for 12-17-24 PB mtg 7/7/2024 (for all noted) NYS DEC - lead agency concurrence 7/7/2024 Tompkins County Planning Department- GML 239, lead agency concurrence Possible acceptance of utility extensions 2014 Town Comprehensive Plan Future Land Use Map Special Permit However, the East Ithaca Recreation Trail serves the project site. Project is technically considered new, with its own review process and new PDZ language. 27* *(Indicated in application) 9.71 9.27 57 Water Improvement Area Sewer Improvement Area * *Town sewer mains exist, but will be reconstructed to better serve project. -to centerline of Maple Ave 5.82 9.14 55 2.80 1.64 2.92 5.12 0.49 4.10 2.32 (1.15) 1.18 (2.35) Project site includes MW2 + MW1 = 9.71 acres 20 Michele A Palmer 7/19/2024 Senior Associate Whitham Planning Design Landscape Arcihtecture DRAFTPage 1 of 10 Full Environmental Assessment Form Part 2 - Identification of Potential Project Impacts Part 2 is to be completed by the lead agency. Part 2 is designed to help the lead agency inventory all potential resources that could be affected by a proposed project or action. We recognize that the lead agency=s reviewer(s) will not necessarily be environmental professionals. So, the questions are designed to walk a reviewer through the assessment process by providing a series of questions that can be answered using the information found in Part 1. To further assist the lead agency in completing Part 2, the form identifies the most relevant questions in Part 1 that will provide the information needed to answer the Part 2 question. When Part 2 is completed, the lead agency will have identified the relevant environmental areas that may be impacted by the proposed activity. If the lead agency is a state agency and the action is in any Coastal Area, complete the Coastal Assessment Form before proceeding with this assessment. Tips for completing Part 2: •Review all of the information provided in Part 1. •Review any application, maps, supporting materials and the Full EAF Workbook. •Answer each of the 18 questions in Part 2. •If you answer “Yes” to a numbered question, please complete all the questions that follow in that section. •If you answer “No” to a numbered question, move on to the next numbered question. •Check appropriate column to indicate the anticipated size of the impact. •Proposed projects that would exceed a numeric threshold contained in a question should result in the reviewing agency checking the box “Moderate to large impact may occur.” •The reviewer is not expected to be an expert in environmental analysis. •If you are not sure or undecided about the size of an impact, it may help to review the sub-questions for the general question and consult the workbook. •When answering a question consider all components of the proposed activity, that is, the Awhole action@. •Consider the possibility for long-term and cumulative impacts as well as direct impacts. •Answer the question in a reasonable manner considering the scale and context of the project. 1.Impact on Land Proposed action may involve construction on, or physical alteration of,† NO † YES the land surface of the proposed site. (See Part 1. D.1) If “Yes”, answer questions a - j. If “No”, move on to Section 2. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may involve construction on land where depth to water table is less than 3 feet.E2d 9 9 b. The proposed action may involve construction on slopes of 15% or greater.E2f 9 9 c. The proposed action may involve construction on land where bedrock is exposed, or generally within 5 feet of existing ground surface. E2a 9 9 d. The proposed action may involve the excavation and removal of more than 1,000 tons of natural material. D2a 9 9 e. The proposed action may involve construction that continues for more than one year or in multiple phases. D1e 9 9 f. The proposed action may result in increased erosion, whether from physical disturbance or vegetation removal (including from treatment by herbicides). D2e, D2q 9 9 g. The proposed action is, or may be, located within a Coastal Erosion hazard area.B1i 9 9 h. Other impacts: _______________________________________________________ ___________________________________________________________________ 9 9 Agency Use Only [If applicable] Project : Date : FEAF 2019 PLEASE SEE PART 3 FOR ANY ITEM CHECKED "YES"- Unchecked boxes are "No Impact" Maplewood II Residential Development 4 4 4DRAFTDecember 17, 2024 Revised for 12/17/24 PB mtg DRAFTPage 2 of 10 2.Impact on Geological Features The proposed action may result in the modification or destruction of, or inhibit access to, any unique or unusual land forms on the site (e.g., cliffs, dunes, † NO † YES minerals, fossils, caves). (See Part 1. E.2.g) If “Yes”, answer questions a - c. If “No”, move on to Section 3. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. Identify the specific land form(s) attached: ________________________________ ___________________________________________________________________ E2g 9 9 b.The proposed action may affect or is adjacent to a geological feature listed as a registered National Natural Landmark. Specific feature: _____________________________________________________ E3c 9 9 c.Other impacts: ______________________________________________________ ___________________________________________________________________ 9 9 3.Impacts on Surface Water The proposed action may affect one or more wetlands or other surface water † NO † YES bodies (e.g., streams, rivers, ponds or lakes). (See Part 1. D.2, E.2.h) If “Yes”, answer questions a - l. If “No”, move on to Section 4. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may create a new water body.D2b, D1h 9 9 b. The proposed action may result in an increase or decrease of over 10% or more than a 10 acre increase or decrease in the surface area of any body of water. D2b 9 9 c. The proposed action may involve dredging more than 100 cubic yards of material from a wetland or water body. D2a 9 9 d. The proposed action may involve construction within or adjoining a freshwater or tidal wetland, or in the bed or banks of any other water body. E2h 9 9 e. The proposed action may create turbidity in a waterbody, either from upland erosion, runoff or by disturbing bottom sediments. D2a, D2h 9 9 f.The proposed action may include construction of one or more intake(s) for withdrawal of water from surface water. D2c 9 9 g.The proposed action may include construction of one or more outfall(s) for discharge of wastewater to surface water(s). D2d 9 9 h.The proposed action may cause soil erosion, or otherwise create a source of stormwater discharge that may lead to siltation or other degradation of receiving water bodies. D2e 9 9 i. The proposed action may affect the water quality of any water bodies within or downstream of the site of the proposed action. E2h 9 9 j. The proposed action may involve the application of pesticides or herbicides in or around any water body. D2q, E2h 9 9 k.The proposed action may require the construction of new, or expansion of existing, wastewater treatment facilities. D1a, D2d 9 4 4 DRAFT DRAFTPage 3 of 10 l. Other impacts: _______________________________________________________ ___________________________________________________________________ 9 9 4.Impact on groundwater The proposed action may result in new or additional use of ground water, or † NO † YES may have the potential to introduce contaminants to ground water or an aquifer. (See Part 1. D.2.a, D.2.c, D.2.d, D.2.p, D.2.q, D.2.t) If “Yes”, answer questions a - h. If “No”, move on to Section 5. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may require new water supply wells, or create additional demand on supplies from existing water supply wells. D2c 9 9 b. Water supply demand from the proposed action may exceed safe and sustainable withdrawal capacity rate of the local supply or aquifer. Cite Source: ________________________________________________________ D2c 9 9 c. The proposed action may allow or result in residential uses in areas without water and sewer services. D1a, D2c 9 9 d. The proposed action may include or require wastewater discharged to groundwater.D2d, E2l 9 9 e. The proposed action may result in the construction of water supply wells in locations where groundwater is, or is suspected to be, contaminated. D2c, E1f, E1g, E1h 9 9 f. The proposed action may require the bulk storage of petroleum or chemical products over ground water or an aquifer. D2p, E2l 9 9 g. The proposed action may involve the commercial application of pesticides within 100 feet of potable drinking water or irrigation sources. E2h, D2q, E2l, D2c 9 9 h. Other impacts: ______________________________________________________ __________________________________________________________________ 9 9 5.Impact on Flooding The proposed action may result in development on lands subject to flooding.† NO † YES (See Part 1. E.2) If “Yes”, answer questions a - g. If “No”, move on to Section 6. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may result in development in a designated floodway.E2i 9 9 b. The proposed action may result in development within a 100 year floodplain.E2j 9 9 c. The proposed action may result in development within a 500 year floodplain.E2k 9 9 d. The proposed action may result in, or require, modification of existing drainage patterns. D2b, D2e 9 9 e. The proposed action may change flood water flows that contribute to flooding.D2b, E2i, E2j, E2k 9 9 f.If there is a dam located on the site of the proposed action, is the dam in need of repair, or upgrade? E1e 9 9 4 4 4 DRAFTPage 4 of 10 g. Other impacts: ______________________________________________________ ___________________________________________________________________ 9 9 6.Impacts on Air † NO † YES The proposed action may include a state regulated air emission source. (See Part 1. D.2.f., D.2.h, D.2.g) If “Yes”, answer questions a - f. If “No”, move on to Section 7. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. If the proposed action requires federal or state air emission permits, the action may also emit one or more greenhouse gases at or above the following levels: i. More than 1000 tons/year of carbon dioxide (CO2) ii.More than 3.5 tons/year of nitrous oxide (N2O) iii. More than 1000 tons/year of carbon equivalent of perfluorocarbons (PFCs) iv. More than .045 tons/year of sulfur hexafluoride (SF6) v. More than 1000 tons/year of carbon dioxide equivalent of hydrochloroflourocarbons (HFCs) emissions vi. 43 tons/year or more of methane D2g D2g D2g D2g D2g D2h 9 9 9 9 9 9 9 9 9 9 9 9 b. The proposed action may generate 10 tons/year or more of any one designated hazardous air pollutant, or 25 tons/year or more of any combination of such hazardous air pollutants. D2g 9 9 c. The proposed action may require a state air registration, or may produce an emissions rate of total contaminants that may exceed 5 lbs. per hour, or may include a heat source capable of producing more than 10 million BTU=s per hour. D2f, D2g 9 9 d.The proposed action may reach 50% of any of the thresholds in “a” through “c”, above. D2g 9 9 e. The proposed action may result in the combustion or thermal treatment of more than 1 ton of refuse per hour. D2s 9 9 f. Other impacts: ______________________________________________________ __________________________________________________________________ 9 9 7.Impact on Plants and Animals The proposed action may result in a loss of flora or fauna. (See Part 1. E.2. m.-q.)† NO † YES If “Yes”, answer questions a - j. If “No”, move on to Section 8. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a.The proposed action may cause reduction in population or loss of individuals of any threatened or endangered species, as listed by New York State or the Federal government, that use the site, or are found on, over, or near the site. E2o 9 9 b. The proposed action may result in a reduction or degradation of any habitat used by any rare, threatened or endangered species, as listed by New York State or the federal government. E2o 9 9 c. The proposed action may cause reduction in population, or loss of individuals, of any species of special concern or conservation need, as listed by New York State or the Federal government, that use the site, or are found on, over, or near the site. E2p 9 9 d. The proposed action may result in a reduction or degradation of any habitat used by any species of special concern and conservation need, as listed by New York State or the Federal government. E2p 9 9 4 DRAFT DRAFTPage 5 of 10 e. The proposed action may diminish the capacity of a registered National Natural Landmark to support the biological community it was established to protect. E3c 9 9 f. The proposed action may result in the removal of, or ground disturbance in, any portion of a designated significant natural community. Source: ____________________________________________________________ E2n 9 9 g.The proposed action may substantially interfere with nesting/breeding, foraging, or over-wintering habitat for the predominant species that occupy or use the project site.E2m 9 9 h. The proposed action requires the conversion of more than 10 acres of forest, grassland or any other regionally or locally important habitat. Habitat type & information source: ______________________________________ __________________________________________________________________ E1b 9 9 i.Proposed action (commercial, industrial or recreational projects, only) involves use of herbicides or pesticides. D2q 9 9 j. Other impacts: ______________________________________________________ __________________________________________________________________ 9 9 8.Impact on Agricultural Resources The proposed action may impact agricultural resources. (See Part 1. E.3.a. and b.)† NO † YES If “Yes”, answer questions a - h. If “No”, move on to Section 9. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may impact soil classified within soil group 1 through 4 of the NYS Land Classification System. E2c, E3b 9 9 b.The proposed action may sever, cross or otherwise limit access to agricultural land (includes cropland, hayfields, pasture, vineyard, orchard, etc). E1a, Elb 9 9 c. The proposed action may result in the excavation or compaction of the soil profile of active agricultural land. E3b 9 9 d.The proposed action may irreversibly convert agricultural land to non-agricultural uses, either more than 2.5 acres if located in an Agricultural District, or more than 10 acres if not within an Agricultural District. E1b, E3a 9 9 e. The proposed action may disrupt or prevent installation of an agricultural land management system. El a, E1b 9 9 f. The proposed action may result, directly or indirectly, in increased development potential or pressure on farmland. C2c, C3, D2c, D2d 9 9 g.The proposed project is not consistent with the adopted municipal Farmland Protection Plan. C2c 9 9 h. Other impacts: ________________________________________________________9 9 4 4 Please See Part 3 DRAFT DRAFTPage 6 of 10 9. Impact on Aesthetic Resources The land use of the proposed action are obviously different from, or are in † NO † YES sharp contrast to, current land use patterns between the proposed project and a scenic or aesthetic resource. (Part 1. E.1.a, E.1.b, E.3.h.) If “Yes”, answer questions a - g. If “No”, go to Section 10. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. Proposed action may be visible from any officially designated federal, state, or local scenic or aesthetic resource. E3h 9 9 b.The proposed action may result in the obstruction, elimination or significant screening of one or more officially designated scenic views. E3h, C2b 9 9 c. The proposed action may be visible from publicly accessible vantage points: i. Seasonally (e.g., screened by summer foliage, but visible during other seasons) ii. Year round E3h 9 9 9 9 d. The situation or activity in which viewers are engaged while viewing the proposed action is: i. Routine travel by residents, including travel to and from work ii. Recreational or tourism based activities E3h E2q, E1c 9 9 9 9 e. The proposed action may cause a diminishment of the public enjoyment and appreciation of the designated aesthetic resource. E3h 9 9 f. There are similar projects visible within the following distance of the proposed project: 0-1/2 mile ½ -3 mile 3-5 mile 5+ mile D1a, E1a, D1f, D1g 9 9 g.Other impacts: ______________________________________________________ __________________________________________________________________ 9 9 10. Impact on Historic and Archeological Resources The proposed action may occur in or adjacent to a historic or archaeological † NO † YES resource. (Part 1. E.3.e, f. and g.) If “Yes”, answer questions a - e. If “No”, go to Section 11. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur E3e 9 9 b. The proposed action may occur wholly or partially within, or substantially contiguous to, an area designated as sensitive for archaeological sites on the NY State Historic Preservation Office (SHPO) archaeological site inventory. E3f 9 9 c. The proposed action may occur wholly or partially within, or substantially contiguous to, an archaeological site not included on the NY SHPO inventory. Source: ____________________________________________________________ E3g 9 9 a.The proposed action may occur wholly or partially within, or substantially contiguous to, any buildings, archaeological site or district which is listed on the National or State Register of Historical Places, or that has been determined by the Commissioner of the NYS Office of Parks, Recreation and Historic Preservation to be eligible for listing on the State Register of Historic Places. 4 4 4 4 4 4 4 4 DRAFTPage 7 of 10 d. Other impacts: ______________________________________________________ __________________________________________________________________ 9 9 e.If any of the above (a-d) are answered “Moderate to large impact may occur”, continue with the following questions to help support conclusions in Part 3: i.The proposed action may result in the destruction or alteration of all or part of the site or property. ii.The proposed action may result in the alteration of the property’s setting or integrity. iii.The proposed action may result in the introduction of visual elements which are out of character with the site or property, or may alter its setting. E3e, E3g, E3f E3e, E3f, E3g, E1a, E1b E3e, E3f, E3g, E3h, C2, C3 9 9 9 9 9 9 11. Impact on Open Space and Recreation The proposed action may result in a loss of recreational opportunities or a † NO † YES reduction of an open space resource as designated in any adopted municipal open space plan. (See Part 1. C.2.c, E.1.c., E.2.q.) If “Yes”, answer questions a - e. If “No”, go to Section 12. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may result in an impairment of natural functions, or “ecosystem services”, provided by an undeveloped area, including but not limited to stormwater storage, nutrient cycling, wildlife habitat. D2e, E1b E2h, E2m, E2o, E2n, E2p 9 9 b. The proposed action may result in the loss of a current or future recreational resource.C2a, E1c, C2c, E2q 9 9 c. The proposed action may eliminate open space or recreational resource in an area with few such resources. C2a, C2c E1c, E2q 9 9 d. The proposed action may result in loss of an area now used informally by the community as an open space resource. C2c, E1c 9 9 e. Other impacts: _____________________________________________________ _________________________________________________________________ 9 9 12. Impact on Critical Environmental Areas The proposed action may be located within or adjacent to a critical † NO † YES environmental area (CEA). (See Part 1. E.3.d) If “Yes”, answer questions a - c. If “No”, go to Section 13. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may result in a reduction in the quantity of the resource or characteristic which was the basis for designation of the CEA. E3d 9 9 b. The proposed action may result in a reduction in the quality of the resource or characteristic which was the basis for designation of the CEA. E3d 9 9 c. Other impacts: ______________________________________________________ __________________________________________________________________ 9 9 4 4 DRAFTPage 8 of 10 13. Impact on Transportation The proposed action may result in a change to existing transportation systems.† NO † YES (See Part 1. D.2.j) If “Yes”, answer questions a - f. If “No”, go to Section 14. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. Projected traffic increase may exceed capacity of existing road network.D2j 9 9 b. The proposed action may result in the construction of paved parking area for 500 or more vehicles. D2j 9 9 c. The proposed action will degrade existing transit access.D2j 9 9 d. The proposed action will degrade existing pedestrian or bicycle accommodations.D2j 9 9 e.The proposed action may alter the present pattern of movement of people or goods.D2j 9 9 __________________________________________________________________ 9 9 14. Impact on Energy The proposed action may cause an increase in the use of any form of energy.† NO † YES (See Part 1. D.2.k) If “Yes”, answer questions a - e. If “No”, go to Section 15. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action will require a new, or an upgrade to an existing, substation.D2k 9 9 b. The proposed action will require the creation or extension of an energy transmission or supply system to serve more than 50 single or two-family residences or to serve a commercial or industrial use. D1f, D1q, D2k 9 9 c. The proposed action may utilize more than 2,500 MWhrs per year of electricity.D2k 9 9 d. The proposed action may involve heating and/or cooling of more than 100,000 square feet of building area when completed. D1g 9 9 e. Other Impacts: ________________________________________________________ ____________________________________________________________________ 15. Impact on Noise, Odor, and Light The proposed action may result in an increase in noise, odors, or outdoor lighting. † NO † YES (See Part 1. D.2.m., n., and o.) If “Yes”, answer questions a - f. If “No”, go to Section 16. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may produce sound above noise levels established by local regulation. D2m 9 9 b. The proposed action may result in blasting within 1,500 feet of any residence, hospital, school, licensed day care center, or nursing home. D2m, E1d 9 9 c. The proposed action may result in routine odors for more than one hour per day.D2o 9 9 f. Other impacts: 4 4 4 4 4 4 4 4 Please See Part 3 Please See Part 3 DRAFTPage 9 of 10 d. The proposed action may result in light shining onto adjoining properties.D2n 9 9 e. The proposed action may result in lighting creating sky-glow brighter than existing area conditions. D2n, E1a 9 9 f. Other impacts: ______________________________________________________ __________________________________________________________________ 9 9 16. Impact on Human Health The proposed action may have an impact on human health from exposure † NO † YES to new or existing sources of contaminants. (See Part 1.D.2.q., E.1. d. f. g. and h.) If “Yes”, answer questions a - m. If “No”, go to Section 17. Relevant Part I Question(s) No,or small impact may cccur Moderate to large impact may occur a. The proposed action is located within 1500 feet of a school, hospital, licensed day care center, group home, nursing home or retirement community. E1d 9 9 b. The site of the proposed action is currently undergoing remediation.E1g, E1h 9 9 c. There is a completed emergency spill remediation, or a completed environmental site remediation on, or adjacent to, the site of the proposed action. E1g, E1h 9 9 d.The site of the action is subject to an institutional control limiting the use of the property (e.g., easement or deed restriction). E1g, E1h 9 9 e. The proposed action may affect institutional control measures that were put in place to ensure that the site remains protective of the environment and human health. E1g, E1h 9 9 f. The proposed action has adequate control measures in place to ensure that future generation, treatment and/or disposal of hazardous wastes will be protective of the environment and human health. D2t 9 9 g. The proposed action involves construction or modification of a solid waste management facility. D2q, E1f 9 9 h. The proposed action may result in the unearthing of solid or hazardous waste.D2q, E1f 9 9 i. The proposed action may result in an increase in the rate of disposal, or processing, of solid waste. D2r, D2s 9 9 j. The proposed action may result in excavation or other disturbance within 2000 feet of a site used for the disposal of solid or hazardous waste. E1f, E1g E1h 9 9 k. The proposed action may result in the migration of explosive gases from a landfill site to adjacent off site structures. E1f, E1g 9 9 l. The proposed action may result in the release of contaminated leachate from the project site. D2s, E1f, D2r 9 9 m. Other impacts: ______________________________________________________ __________________________________________________________________ 4 DRAFTPlease See Part 3 DRAFTPage 10 of 10 17. Consistency with Community Plans The proposed action is not consistent with adopted land use plans. † NO † YES (See Part 1. C.1, C.2. and C.3.) If “Yes”, answer questions a - h. If “No”, go to Section 18. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action’s land use components may be different from, or in sharp contrast to, current surrounding land use pattern(s). C2, C3, D1a E1a, E1b 9 9 b. The proposed action will cause the permanent population of the city, town or village in which the project is located to grow by more than 5%. C2 9 9 c. The proposed action is inconsistent with local land use plans or zoning regulations. C2, C2, C3 9 9 d. The proposed action is inconsistent with any County plans, or other regional land use plans. C2, C2 9 9 e. The proposed action may cause a change in the density of development that is not supported by existing infrastructure or is distant from existing infrastructure. C3, D1c, D1d, D1f, D1d, Elb 9 9 f. The proposed action is located in an area characterized by low density development that will require new or expanded public infrastructure. C4, D2c, D2d D2j 9 9 g. The proposed action may induce secondary development impacts (e.g., residential or commercial development not included in the proposed action) C2a 9 9 h. Other: _____________________________________________________________ __________________________________________________________________ 9 9 18. Consistency with Community Character The proposed project is inconsistent with the existing community character. † NO † YES (See Part 1. C.2, C.3, D.2, E.3) If “Yes”, answer questions a - g. If “No”, proceed to Part 3. Relevant Part I Question(s) No, or small impact may occur Moderate to large impact may occur a. The proposed action may replace or eliminate existing facilities, structures, or areas of historic importance to the community. E3e, E3f, E3g 9 9 b. The proposed action may create a demand for additional community services (e.g. schools, police and fire) C4 9 9 c. The proposed action may displace affordable or low-income housing in an area where there is a shortage of such housing. C2, C3, D1f D1g, E1a 9 9 d. The proposed action may interfere with the use or enjoyment of officially recognized or designated public resources. C2, E3 9 9 e. The proposed action is inconsistent with the predominant architectural scale and character. C2, C3 9 9 f. Proposed action is inconsistent with the character of the existing natural landscape. C2, C3 E1a, E1b E2g, E2h 9 9 g. Other impacts: ______________________________________________________ __________________________________________________________________ 9 9 DRAFT Criteria: Selected Map Area New York Nature Explorer http://www.dec.ny.gov/natureexplorer/ Maplewood II EAF Part 2/3 Common Name State Distribution Status Protection Status Conservation RankSubgroup Federal State Global Year Last Documente Animal: Dragonflies and Damselflies Midland Clubtail Dragonflies S3Historically Confirmed G51894 Gomphurus fraternus Mocha Emerald Dragonflies S2S3Historically Confirmed G51926 Somatochlora linearis Rapids Clubtail Dragonflies S3Historically Confirmed G3G4 Phanogomphus quadricolor Spine-crowned Clubtail Dragonflies S1Historically Confirmed G4 Hylogomphus abbreviatus Page 1 of 8/26/24 3:00 PM 2New York State Department of Environmental Conservation New York Nature Explorer Common Name State Distribution Status Protection Status Conservation RankSubgroup Federal State Global Year Last Documente Tiger Spiketail Dragonflies S1Historically Confirmed G4 Cordulegaster erronea Plant: Flowering Plants Delicate Rabbit Tobacco Asters, Goldenrods and Daisies SHHistorically Confirmed G4G5T3?Endangered1919 Pseudognaphalium micradenium Three Birds Orchid Orchids S2Historically Confirmed G4?T4?Threatened1922 Triphora trianthophoros ssp. trianthophoros New York State Department of Environmental Conservation 8/26/24 3:00 PM Page 2 of 2 Note: Restricted plants and animals may also have also been documented in one or more of the Towns or Cities in which your user-defined area is located, but are not listed in these results. This application does not provide information at the level of Town or City on state-listed animals and on other sensitive animals and plants. A list of the restricted animals and plants documented at the corresponding county level can be obtained via the County link(s) on the original User Defined Search Results page. Any individual plant or animal on this county’s restricted list may or may not occur in this particular user-defined area. This list only includes records of rare species and significant natural communities from the databases of the NY Natural Heritage Program. This list is not a definitive statement about the presence or absence of all plants and animals, including rare or state-listed species, or of all significant natural communities. For most areas, comprehensive field surveys have not been conducted, and this list should not be considered a substitute for on-site surveys. --Ua(0i‘.iBI-J1t‘4L1’ PrimeandotherImportantFarmlands---TompkinsCounty,NewYorkMaplewoodIiEAFPart2-3PrimeandotherImportantFarmlandsThistableliststhemapunitsinthesurveyareathatareconsideredimportantfarmlands.Importantfarmlandsconsistofprimefarmland,uniquefarmland,andfarmlandofstatewideorlocalimportance.Thislistdoesnotconstitutearecommendationforaparticularlanduse,Inanefforttoidentifytheextentandlocationofimportantfarmlands,theNaturalResourcesConservationService,incooperationwithotherinterestedFederal,State,andlocalgovernmentorganizations,hasinventoriedlandthatcanbeusedfortheproductionoftheNation’sfoodsupply.PrimefarmlandisofmajorimportanceinmeetingtheNation’sshort-andlong-rangeneedsforfoodandfiber.Becausethesupplyofhigh-qualityfarmlandislimited,theU.S.DepartmentofAgriculturerecognizesthatresponsiblelevelsofgovernment,aswellasindividuals,shouldencourageandfacilitatethewiseuseofourNation’sprimefarmland.Primefarmland,asdefinedbytheU.S.DepartmentofAgriculture,islandthathasthebestcombinationofphysicalandchemicalcharacteristicsforproducingfood,feed,forage,fiber,andoilseedcropsandisavailablefortheseuses.Itcouldbecultivatedland,pastureland,forestland,orotherland,butitisnoturbanorbuilt-uplandorwaterareas.Thesoilquality,growingseason,andmoisturesupplyarethoseneededforthesoiltoeconomicallyproducesustainedhighyieldsofcropswhenpropermanagement,includingwatermanagement,andacceptablefarmingmethodsareapplied.Ingeneral,primefarmlandhasanadequateanddependablesupplyofmoisturefromprecipitationorirrigation,afavorabletemperatureandgrowingseason,acceptableacidityoralkalinity,anacceptablesaltandsodiumcontent,andfewornorocks.Thewatersupplyisdependableandofadequatequality.Primefarmlandispermeabletowaterandair.Itisnotexcessivelyerodibleorsaturatedwithwaterforlongperiods,anditeitherisnotfrequentlyfloodedduringthegrowingseasonorisprotectedfromflooding.Sloperangesmainlyfrom0to6percent.MoredetailedinformationaboutthecriteriaforprimefarmlandisavailableatthelocalofficeoftheNaturalResourcesConservationService.Forsomeofthesoilsidentifiedinthetableasprimefarmland,measuresthatovercomeahazardorlimitation,suchasflooding,wetness,anddroughtiness,areneeded.Onsiteevaluationisneededtodeterminewhetherornotthehazardorlimitationhasbeenovercomebycorrectivemeasures,Arecenttrendinlanduseinsomeareashasbeenthelossofsomeprimefarmlandtoindustrialandurbanuses.Thelossofprimefarmlandtootherusesputspressureonmarginallands,whichgenerallyaremoreerodible,droughty,andlessproductiveandcannotbeeasilycultivated.USDANaturalResourcesWebSoilSurvey8/2612024ConservationServiceNationalcooperativeSoilSurveyPage1of2 PrimeandotherImportantFarmlands-—TompkinsCounty,NewYorkMaplawoodIIEAFPart2-3Uniquefarmlandislandotherthanprimefarmlandthatisusedfortheproductionofspecifichigh-valuefoodandfibercrops,suchascitrus,treenuts,olives,cranberiles,andotherfruitsandvegetables.Ithasthespecialcombinationofsoilquality,growingseason,moisturesupply,temperature,humidity,airdrainage,elevation,andaspectneededforthesoiltoeconomicallyproducesustainablehighyieldsofthesecropswhenproperlymanaged.Thewatersupplyisdependableandofadequatequality.Nearnesstomarketsisanadditionalconsideration.Uniquefarmlandisnotbasedonnationalcriteria.Itcommonlyisinareaswherethereisaspecialmicroclimate,suchasthewinecountryinCalifornia.Insomeareas,landthatdoesnotmeetthecriteriaforprimeoruniquefarmlandisconsideredtobefarmlandofstatewideimportancefortheproductionoffood,feed,fiber,forage,andoilseedcrops.ThecriteriafordefininganddelineatingfarmlandofstatewideimportancearedeterminedbytheappropriateStateagencies.Generally,thislandincludesareasofsoilsthatnearlymeettherequirementsforprimefarmlandandthateconomicallyproducehighyieldsofcropswhentreatedandmanagedaccordingtoacceptablefarmingmethods.Someareasmayproduceashighayieldasprimefarmlandifconditionsarefavorable.FarmlandofstatewideimportancemayincludetractsoflandthathavebeendesignatedforagriculturebyStatelaw.Insomeareasthatarenotidentifiedashavingnationalorstatewideimportance,landisconsideredtobefarmlandoflocalimportancefortheproductionoffood,feed,fiber,forage,andoilseedcrops.Thisfarmlandisidentifiedbytheappropriatelocalagencies.Farmlandoflocalimportancemayincludetractsoflandthathavebeendesignatedforagriculturebylocalordinance.Report—PrimeandotherImportantFarmlandsLPrimeandotherImportantFarmlands—TompkinsCounty,NewYorkEMapSymbolMapUnitNameFarmlandClassificationArBArkportfinesandyloam,2to6percentslopesAllareasareprimefarmlandArCArkporlfinesandyloam,6to12percentslopesFarmlandofstatewideimportanceRkARhinebecksiltloam,0to2percentslopesPrimefarmlandifdrainedWrEWilliamsonveryfinesandyloam,2to6percentslopesAllareasareprimefarmlandDataSourceInformationSoilSurveyArea:TompkinsCounty,NewYorkSurveyAreaData:Version19,Sep5,2023usuiNaturalResources8/26/2024conservauonServicePage2of2WebSoilSurveyNationalcooperativeSoilSurvey .pL&0-a DRAFTFull Environmental Assessment Form Part 3 - Evaluation of the Magnitude and Importance of Project Impacts and Determination of Significance Part 3 provides the reasons in support of the determination of significance. The lead agency must complete Part 3 for every question in Part 2 where the impact has been identified as potentially moderate to large or where there is a need to explain why a particular element of the proposed action will not, or may, result in a significant adverse environmental impact. Based on the analysis in Part 3, the lead agency must decide whether to require an environmental impact statement to further assess the proposed action or whether available information is sufficient for the lead agency to conclude that the proposed action will not have a significant adverse environmental impact. By completing the certification on the next page, the lead agency can complete its determination of significance. Reasons Supporting This Determination: To complete this section: •Identify the impact based on the Part 2 responses and describe its magnitude. Magnitude considers factors such as severity, size or extent of an impact. •Assess the importance of the impact. Importance relates to the geographic scope, duration, probability of the impact occurring, number of people affected by the impact and any additional environmental consequences if the impact were to occur. •The assessment should take into consideration any design element or project changes. •Repeat this process for each Part 2 question where the impact has been identified as potentially moderate to large or where there is a need to explain why a particular element of the proposed action will not, or may, result in a significant adverse environmental impact. •Provide the reason(s) why the impact may, or will not, result in a significant adverse environmental impact •For Conditional Negative Declarations identify the specific condition(s) imposed that will modify the proposed action so that no significant adverse environmental impacts will result. •Attach additional sheets, as needed. Determination of Significance - Type 1 and Unlisted Actions SEQR Status: † Type 1 † Unlisted Identify portions of EAF completed for this Project: † Part 1 † Part 2 † Part 3 Agency Use Only [IfApplicable] Project : Date : FEAF 2019 PLEASE SEE ATTACHMENTS DRAFTUpon review of the information recorded on this EAF, as noted, plus this additional support information and considering both the magnitude and importance of each identified potential impact, it is the conclusion of the as lead agency that: † A. This project will result in no significant adverse impacts on the environment, and, therefore, an environmental impact statement need not be prepared. Accordingly, this negative declaration is issued. † B. Although this project could have a significant adverse impact on the environment, that impact will be avoided or substantially mitigated because of the following conditions which will be required by the lead agency: There will, therefore, be no significant adverse impacts from the project as conditioned, and, therefore, this conditioned negative declaration is issued. A conditioned negative declaration may be used only for UNLISTED actions (see 6 NYCRR 617.7(d)). † C. This Project may result in one or more significant adverse impacts on the environment, and an environmental impact statement must be prepared to further assess the impact(s) and possible mitigation and to explore alternatives to avoid or reduce those impacts. Accordingly, this positive declaration is issued. Name of Action: Name of Lead Agency: Name of Responsible Officer in Lead Agency: Title of Responsible Officer: Signature of Responsible Officer in Lead Agency: Date: Signature of Preparer (if different from Responsible Officer) Date: For Further Information: Contact Person: Address: Telephone Number: E-mail: For Type 1 Actions and Conditioned Negative Declarations, a copy of this Notice is sent to: Chief Executive Officer of the political subdivision in which the action will be principally located (e.g., Town / City / Village of) Other involved agencies (if any) Applicant (if any) Environmental Notice Bulletin: http://www.dec.ny.gov/enb/enb.html Page 2 of 2 (staff will check appropriate box after PB makes determination) 1 Initial draft for PB review – 9-17-2024 Revised for 12/17/24 PB mtg Part 3 – Evaluation of the Magnitude and Importance of Project Impacts & Determination of Significance Maplewood Phase II State Environmental Quality Review Full Environmental Assessment Form Actions: Site Plan Approval, Special Permit, Rezoning to Planned Development Zone Location: Maple Avenue, Tax Parcel No.’s 63.-2-5, 63.-2-6, 63.-2-7.1, 63.-2-7.3 Lead Agency: Town of Ithaca Planning Board Involved Agency: Town of Ithaca Town Board Description: The project is the proposed Maplewood Phase II on Maple Avenue, located between the Maplewood Graduate Student Apartment complex and the East Lawn Cemetery. The project involves consolidating four (4) tax parcels and constructing a community center and six (6) five-story apartment buildings, containing up to 650approximately 615 units/800 beds in studio, one-bedroom, and two-bedroom unit configurations. The project will also include integrated amenity/service spaces, parking areas, trails and pedestrian facilities, open spaces, stormwater facilities, and other site improvements. Site improvements and amenity spaces include an outdoor terrace, fitness and wellness spaces, landscaping, and lighting. The project is located in the Multiple Residence (MR) and High Density Residential (HDR) zoning districts of the town. The Town of Ithaca’s 2014 Comprehensive Plan Future Land Use Map envisions a Traditional Neighborhood Development character area designation for this area of the town. To achieve a neighborhood development style that meets the objectives of the Comprehensive Plan, and complements the adjacent Maplewood I project, the applicants have proposed a Planned Development Zone (PDZ) for the project. This involves a re-zoning from the High Density Residential and Multiple Residence zoning designations to a PDZ, which is a Town Board action. Like the Maplewood Phase I project, the PDZ for Maplewood Phase II will include building design, height, and densities that are complementary to the surrounding area. Along with the re-zoning to a PDZ, the project also requires site plan approval and special permit by the Town of Ithaca Planning Board. The project is a Type I action pursuant to the State Environmental Quality Review Act, 6 NYCRR Part 617, and Chapter 148 of the Town of Ithaca Code - Environmental Quality Review, because it involves a zoning change and the construction of 250 or more residential units (30 or more per Town Code) that will be connected to existing community or public water and sewage systems (NYCRR 617.4 (b)(3) and (b)(5)(iii); Town Code Section 148-5.B(2)). The Town of Ithaca Planning Board reviewed a sketch plan for the Maplewood Phase II project on July 2, 2024. The board declared their intent to be the Lead Agency in the environmental review for the project on August 6, 2024. Having received no objections from involved agencies, the Planning Board established themselves as Lead Agency on September 17, 2024. 2 1. Impact on Land e. The proposed action may involve construction that continues for more than one year or in multiple phases. f. The proposed action may result in increased erosion, whether from physical disturbance or vegetation removal (including from treatment by herbicides) – please see #3 and #5 below, impacts on surface area and flooding. Briefly describe the impact on land: The four parcels associated with the project (referred to as the “project site”) are bound on the north by Maple Avenue, with Cornell University-owned agricultural fields and the East Lawn Cemetery along the easternmost boundary, and the Cornell Maplewood Graduate and Professional Student Apartments on the south and westernmost boundary. There is a City of Ithaca-owned parcel that contains a city water tank located between the project site along Maple Avenue. The project site contains vacant land, Cornell agricultural plots, building foundations, paved drive lanes, paved and gravel parking areas, capped utilities from a former development, some large trees, and a variety of vegetation in various succession. Two of the four parcels that make up the project site contained single-family residences until 2020. The fourth and largest parcel contained the Maple Hill Apartment Complex (later known as Ithaca East), constructed in 1972, and operated by the Abbott family until October 2019. The complex consisted of 82 units in 11 apartment buildings, a small utility shed, and a garage/maintenance building, along with planters, roads, parking areas, playgrounds, and other residential features. The complex was closed and vacated by all tenants shortly after its closing. The current property owner (Cornell University) subsequently installed security fencing around the complex and, after Planning Board approval in February 2020, demolished the apartment complex and the two single-family residences, leaving the foundations, parking areas, and other structures that currently exist on the project site. The application materials and the Full EAF Part 1, page 3, number D.1.e., note that the project will be constructed in one phase but will take more than one year to complete (27 months anticipated). The project is anticipated to generate approximately 500 truckloads of materials, translating to roughly 1000 truck trips, with trucks loaded with materials traveling to or from the site during the site work phase of the project. The applicant has indicated in emails with Christine Balestra, Senior Planner, dated October 21, 2024, and November 15, 2024, that trucks coming to the site from the North would utilize NYS Route 366/Dryden Road, then Pine Tree Road to Maple Avenue (reversed for trucks leaving the site); and trucks coming from the South will use NYS Route 79E/Slaterville Road, then Pine Tree Road to Maple Avenue (reversed for trucks leaving the site). Town Code Chapter 230, this project will require a Road Use Agreement, subject to the directive of the Town of Ithaca Highway Superintendent. All four parcels that make up the project site have been previously disturbed, the largest of which contained a multifamily residential development until 2019. More than half of the proposed Maplewood Phase II development will therefore be constructed over existing impervious surfaces. The submitted Phase I Environmental Assessment, prepared by Matrix Environmental Technologies, Inc., dated April 15, 2024, contains a full history of the project site. 3 Based on the above information, the impact on land identified in this section can be considered small in magnitude. 3. Impact on Surface Water h. The proposed action may cause soil erosion, or otherwise create a source of stormwater discharge that may lead to siltation or other degradation of receiving water bodies. i. The proposed action may affect the water quality of any water bodies within or downstream of the site of the proposed action. 5. Impact on Flooding d. The proposed action may result in, or require, modification of existing drainage patterns. Briefly describe the impact on surface water and flooding: Waterbodies within or downstream of the site: The project site is 9.72+/- acres in size, currently consisting of 6.95.7+/- acres of lawn, planting beds, agricultural fields, and woods, along with 3.52.8+/- acres of impervious surfaces (building foundations, parking areas, concrete, asphalt, gravel areas). The closest water body is Cascadilla Creek, located 600+/- feet north and east of the project site, along Pine Tree Road. The creek will be unaffected by the project. There is also a stream located south of Mitchell Street that drains into the Six Mile Creek watershed, which could be impacted by the project if stormwater management controls are not implemented. Based on information in the FEAF I, physicalsoil disturbance associated with construction and site development will be 9.257 acres. Given this extent of disturbance, the project is required to produce a Full Stormwater Pollution Prevention Plan (SWPPP) to include both temporary erosion controls and permanent stormwater management practices in conformance with the Town of Ithaca Code Chapter 228 and NYS Department of Environmental Conservation (NYSDEC) General Permit GP-0-20X-001. According to the SWPPP (August 16, 2024) submitted by the applicant team, the Maplewood Phase II stormwater will drain through the Maplewood Phase I stormwater collection system and into the municipal-owned system on Mitchell Street. The municipal system discharges to Six Mile Creek, which ultimately discharges into Cayuga Lake. There are otherwise no streams, wetlands, significant slopes, or Unique Natural Areas anywhere on or near the project site. None of the water bodies noted above will be directly impacted by the project. Any potential indirect impacts are expected to be mitigated with the proposed stormwater practices below, which will be reviewed and approved by the Town Engineering Department. Soil Erosion, Water Quantity, Flooding, Water Quality: The project site has been previously disturbed and contains impervious surfaces associated with former development. The Maplewood Phase II project will result in an additional 2.3+/- acres of impervious surface. Redevelopment of a previously disturbed site is encouraged from a watershed protection standpoint because it often provides an opportunity to conserve natural resources in less impacted areas by targeting development to areas with existing services and infrastructure. Redevelopment also provides an opportunity to correct existing problems and reduce pollutant discharges from older developed areas that were constructed without effective stormwater pollution prevention controls. To mitigate soil erosion during construction, the applicant proposes installing temporary practices such as silt fences, sediment traps, temporary swales, check dams, and berms to capture runoff, 4 along with a stabilized construction entrance and erosion control blankets. After construction, the disturbed areas will be seeded with locally appropriate seed mix to prevent soil damage, promote deep root growth, and provide permanent soil stabilization. The site will then be mulched and landscaped per the final approved landscape plan. Permanent water quality practices include the installation of eight bioretention filters and three sand filters. The bioretention filter practices will provide water runoff reduction for the whole site, along with a portion of the water quality volume. The three sand filter practices will provide the remaining required water quality volume reduction. The practices will be installed to maintain sheet flow conditions on the site and to maintain pre-condition drainage patterns and peak discharge rates. Peak discharge rates leaving the site will meet pre-development rates. Additionally, the project includes three bBelow-grade storage chambers and a stormwater retention pond will be utilized to achieve the pre-development discharge rates. stormwater detention systems to provide for the 1-, 2-, 10-, 25-, and 100- year storm events. These and other practices are described in the SWPPP that was submitted to the Town’s Engineering Department for their review and approval. Based on the above information, impact on surface water and flooding identified in this section can be considered small in magnitude. 7. Impact on Plants and Animals j. Other impacts: Loss of vegetation associated with proposed development. Briefly describe the impact on plants and animals: The project includes some tree and vegetation removal, all of which is detailed on sheet C102, Demolition Plan, dated 07-17-2024. Based on the Demolition Plan, site development will require the removal of between 17 and 35 large trees (18”-48” DBH – there are 28 Hemlocks shown on the demolition plan without DBH labeled, so it’s unclear their size).The largest trees to be removed are located near Maple Avenue, in the area where Building A will be located. These include a 48” Silver Maple, 36” Tulip, and 30” Austrian Pine. By contrast, the project will protect and preserve another 36” Tulip, 36” Silver Maple, 28” Butternut Hickory, and other existing site trees. The project also includes a robust landscaping plan that will consist of non- invasive large deciduous and coniferous trees, small deciduous and coniferous trees, deciduous shrubs, perennials, grasses, ferns, and ground covers. There are no known threatened or endangered plant or animal species on the project site that would be affected by the project. According to the NYS DEC Nature Explorer Mapping program, the “Delicate Rabbit Tobacco” and “Three Birds Orchid” plants that have been historically confirmed on the site have not been documented since 1922. Similarly, there are four species of dragonfly that have been historically confirmed on the site, but not documented since 1926. Given this, and the prior site disturbance and development, it is highly unlikely that these plant and animal species are present on the project site. Based on the above information, impact on plants and animals identified in this section can be considered small in magnitude. 8. Impact on Agricultural Resources a. The proposed action may impact soil classified within soil group 1 through 4 of the NYS Land Classification System. 5 Briefly describe the impact on agricultural resources: The project site is not located within a Tompkins County designated, NYS-certified Agricultural District. However, one of the parcels along Maple Avenue is currently utilized for Cornell agricultural and farm research. This parcel contains soils classified as Prime Farmland (Class II) and Farmland of Statewide Importance (Class III). The Town of Ithaca has an Agricultural and Farmland Protection Plan that was adopted in November 2011. Map 9 in the Plan, titled “Farmland Targeted for Protection,” includes a category for “Cornell University and State-Owned Agricultural Research Land.” The parcel that is currently farmed is not included among those targeted for protection and is not considered a high priority to remain in agriculture. The conversion of this land from agriculture to development associated with the Maplewood Phase II project is not in conflict with the Agricultural and Farmland Protection Plan. Based on the above information, impact on agricultural resources identified in this section would be considered small in magnitude. 9. Impact on Aesthetic Resources c. The proposed action may be visible from publicly accessible vantage points (seasonally or year-round). d. The situation or activity in which viewers are engaged while viewing the proposed action is routine travel by residents, including travel to and from work; and recreational of tourism based activities. f. There are similar projects visible within 0-1/2 mile of the proposed project – Maplewood I is adjacent. Briefly describe the impact on aesthetic resources: The Maplewood Phase II development will be situated along Maple Avenue, which is a town-owned public road. Even with proposed landscaping, the portion of the project along Maple Avenue will be seen year round. According to the visual assessment that was provided, the project will also be visible year round from a few points along NYS Route 366 and Pine Tree Road. Finally, it will be visible year round from Maplewood Phase I development, which is immediately adjacent to the project site. The proposed development is in an area that is surrounded by development and other residential apartment complexes. Its view is not unique, and it is not near or within any identified scenic views noted below. The Town of Ithaca and Tompkins County have established Scenic Resources Inventories that identify significant views in the East Hill area. There are no designated scenic views or other identified scenic resources around the project site that would be impacted by the proposed development. Aesthetic and/or visual impacts are mainly limited to those traveling along Maple Avenue or from looking in the direction of the development from across Maple Avenue. Those traveling on Pine Tree Road will only view the development as they pass the Maple Avenue intersection; and those traveling along NYS Route 366 will see the development off in the distance across existing farm fields and through existing vegetation. Based on the above information, impact on aesthetic resources identified in this section would be considered small in magnitude. 10. Impact on Historic and Archaeological Resources a. The proposed action may occur wholly or partially within, or substantially contiguous to, any buildings, archaeological site or district which is listed on the National or State Register of Historic Places, or that has been determined by the Commissioner of the NYS Office of Parks, Recreation, and Historic Preservation to be eligible for listing on the State Register of Historic Places. 6 Briefly describe the impact on historic and archaeological resources: The application materials contain a Phase I Environmental Site Assessment, prepared by Matrix Environmental Technologies, Inc., dated April 15, 2024, that includes a thorough history of the project site, with historical photographs and information about Mitchell Family Cemetery. The Mitchell Family Cemetery was identified as being eligible for listing on the State and National Registers of Historic Places during the Maplewood Phase I review process. The cemetery is located at the northeast corner of the Maplewood Phase I project, which is adjacent to the Maplewood Phase II project. It has been preserved and protected by a permanent black metal fence that surrounds the cemetery. The applicant contacted the New York State Office of Parks, Recreation, and Historic Preservation (SHPO) to inquire if SHPO had any concerns about the proximity of the Maplewood Phase II development to the cemetery. SHPO responded with a letter, dated June 21, 2024 (included with project application materials), that recommended a construction protection plan for historic resources within 90 feet of proposed construction activities. The demolition, grading, and utility plans indicate construction disturbance within 90 feet of the cemetery. The demolition plan (sheet C102) shows an additional temporary construction fence surrounding the cemetery to protect it from any ground disturbance, equipment, or material storage or encroachment. The temporary fence is in addition to the existing permanent fence and another temporary construction fence located along the property boundary that encompasses the entire project site. Building G (new community center) will be located approximately 30 feet from the cemetery after construction. The proposed additional fencing should be enough to protect the cemetery, however this plan should be submitted and approved by SHPO before any building permits are issued for the project. There are no other buildings, structures, or sites of historical or archaeological importance on or near the project that will be impacted by the Maplewood Phase II development. Based on the above information and proposed mitigations, impact on historic and archaeological resources identified in this section would be considered small in magnitude. 13. Impact on Transportation e. The proposed action may alter the present pattern of movement of people or goods. f. Other impacts: Parking discrepancy noted between Traffic Impact Assessment and project plan set. Briefly describe the impact on transportation: The applicant has submitted a Traffic Impact Assessment, prepared by Gordon T. Stansbury, P.E., P.T.O.E., GTS Consulting, dated June 7, 2024, that has evaluated the impact of the proposed Maplewood Phase II development on the existing roadway and multimodal systems. The assessment studied existing traffic volumes and data on several area roadways, and also utilized data from the Maplewood Phase I traffic study, which analyzed several other developments within a 2/3-mile radius that were constructed or were under construction at the time. The Traffic Impact Assessment includes an analysis of existing conditions, along with no-build and build scenarios. Data collection was taken during the academic year, when all schools (primary, secondary, and college) were in session. The collection includes separate heavy vehicle counts as well as pedestrian counts. According to the traffic assessment, the Maplewood Phase II project will 7 generate approximately 21 entering/34 exiting new vehicle trips during the weekday AM peak hour and 39 entering/43 exiting new vehicle trips during the PM peak hour. Level of Service (LOS) qualitatively describes a driver’s experience of the operating conditions of a roadway based on factors such as speed and number of vehicles using the road. The traffic assessment shows that nearly all study intersections currently operate and will continue to operate at vehicle LOS D or better, but that the LOS at all studied intersections would slightly decrease as a result of the Maplewood Phase II development. The decrease in service, mostly resulting in waiting times of an additional 2-5 seconds average delay, is not considered a significant adverse impact. Town of Ithaca Planning staff reviewed the traffic study that was previously submitted for the Maplewood Phase I development and compared the anticipated morning and evening peak hour traffic with the current actual morning and evening peak hour traffic counts. The traffic study for Maplewood I anticipated approximately 78 entering/68 exiting vehicle trips during the weekday AM peak hour and 55 entering/68 exiting vehicle trips during the PM peak hour. These estimates were significantly higher than the existing conditions (page 7 of the traffic assessment), which show that the existing Maplewood Phase I development only generate 24 trips entering/40 trips exiting during the morning peak hour; and 45 entering/50 exiting during evening peak hour. Regarding the existing and proposed pedestrian, bicycle, and multimodal network, the project’s internal elements will include a system of sidewalks and connections throughout the site. Along the frontage, Tthe project will include a new sidewalk and streetscape improvements along the Maple Avenue frontage that will connect to the existing sidewalk in the City of Ithaca and create an inviting and safe streetscape for all modes of transport. There will be a multimodal path in the middle of the Maplewood Phase II project that will connect to the East Ithaca Recreation Way to the south of the project site in the Maplewood I project. There will also be a crosswalk on Maple Avenue to improve the connection to the East Ithaca Recreation Way to the north of the project site. The project includes covered storage for up to 100 bicycles, bike racks/outdoor storage for an additional 42 bicycles, and locations for 8 Ithaca Bikeshare bicycles. As there will be an increase in the population, the project also includes an increase in the number of parking spaces on the site. The Traffic Impact Assessment indicates that the 925+/- bed project will generate a need for up to 202 parking spaces. It is noted that there is a discrepancy in the number of proposed parking spaces between the Traffic Impact Assessment page 10 ‘Parking Demands’ (178 proposed parking spaces) and the Landscaping Plan sheet L-200, revision date 8/23/202412/9/2024 (15560 spaces shown). This isn’t inherently a problem, considering the traffic assessment was based on an overestimation of the proposed parking spaces. Regardless, the proposed number of parking spaces is less than the estimated need. The Traffic Impact Assessment notes that the existing surface parking located in the Maplewood Phase I development is underutilized, with as many as 100 extra parking spaces available that could be used to meet parking demands in the Maplewood Phase II development by paid permit unbundled from rental charges. Additionally, shared parking creates opportunities for more compact development, more space for pedestrian circulation, or more open space and landscaping. The project includes the implementation of a Transportation Demand Management plan (TDM) to mitigate any potential impacts related to the lack of parking for the project. The TDM plan includes unbundled parking (separating the cost of parking from the cost of rent), multimodal pathways 8 (mentioned above), increased public transit opportunities (mentioned below), coordination with area bikeshare and carshare programs, and other programs intended to promote alternative modes of travel. The applicant team has already contacted the Ithaca Carshare and Ithaca Bikeshare program coordinators to explore options to expand services, which already exist in the area. The Planning Board should consider requiring the applicant team to commit to implementing the list of TDM strategies that are recommended on page 9 of the traffic assessment. Regarding public transit service and access, the area currently contains many designated transit stops for the Tompkins Consolidated Area Transit (TCAT) bus service along Maple Avenue, including at least two that are located within ¼ mile of the project. Maple Avenue is well served by TCAT routes 10, 30, 32, 43, 51, and 82. The applicant team has contacted TCAT to explore the idea of creating an additional bus stop along Maple Avenue to serve the residents of the proposed development. In terms of sight distance for the project (the length of a road that a driver can see clearly), the traffic assessment notes that there is “more than adequate sight distance available looking in both directions along Maple Avenue from the proposed site driveways.” However, the sight distance listed for the loop access exit driveway along Maple Avenue, turning left (out of the project and onto Maple Avenue), is very close to the maximum minimum distance required by the American Association of State Highway and Transportation Officials (AASHTO). AASHTO requires 445 of clear sight distance, whereas the available sight distance is 45045 feet. The project includes an entrance-only access for the east driveway loop, which will mitigate potential sight distance impacts by eliminating a left-turn out of the project onto Maple Avenue. The applicant team should carefully choose and locate vegetation and landscaping that does not further impede the sight distance along this 445 foot stretch of Maple Avenue. Overall, the Traffic Impact Assessment that was submitted is thorough and indicates that there will not be a significant impact on transportation associated with the Maplewood Phase II development. Based on the above information and proposed mitigations, impact on transportation identified in this section would be considered small in magnitude. 14. Impact on Energy d. The proposed action may involve heating and/or cooling of more than 100,000 square feet of building area when completed. e. Other impacts: Project must comply with Town of Ithaca Energy Code Supplement. Briefly describe the impact on energy: The Maplewood Phase II development will involve approximately 410,000 square feet of building area when completed. The application materials indicate that the project will comply with the Town of Ithaca Energy Code Supplement. The project will utilize 100% electric energy usage for heating and cooling via air source heat pump systems, and hot water via electric hybrid heat pump technology. The project will also incorporate high-efficiency, LED lighting, electric Energy Star-rated appliances, electric vehicle charging stations, and designated roof areas on the buildings for future solar panels. These and other measures, like purchasing materials with a low carbon footprint, and sourcing local, sustainable, and/or reclaimed and recycled building materials will serve to minimize adverse environmental impacts related to greenhouse gas emissions to the maximum extent practicable. 9 The applicant team has calculated the electrical load for the project but has not yet contacted NYSEG to see if the utility has concerns about the connection of such a large project to the electric grid. Coordination with NYSEG should be a condition of approval for this project, should the Planning Board grant such approval. Based on the above information, impact on energy identified in this section would be considered small in magnitude. 15. Impact on Noise and Light a. The proposed action may produce sound above noise levels established by local regulation. f. Other impacts: The project includes lighting that must comply with the Town of Ithaca Code, Chapter 173, Outdoor Lighting. Briefly describe the impact on noise and light: The project will create noise and vibration impacts from equipment, construction vehicles, worker traffic, and delivery vehicles. These impacts will be temporary and will cease once the project is completed. Noise levels caused by construction activities will vary depending on the phase of construction. To mitigate noise impacts to adjacent and nearby residences, noise-producing construction-related activities on the project site will be limited to the hours of 7am to 4pm, Monday – Friday, and from 7am to 4pm Saturday and Sundays “as needed.” The project includes 78 street and pedestrian light poles, 16- to 20-feet tall, located throughout the site. According to the lighting schedule shown on the landscaping plan (sheet L-200), proposed site lighting will match the lighting that exists in the Maplewood Phase I project. Any proposed outdoor lighting will be required to comply with the provisions of Town of Ithaca Code Chapter 173, Outdoor Lighting. The Code contains provisions related to glare and dark-sky compliance. Proposed outdoor light fixture details (cut sheets) will need to be submitted as part of the site plan submission to ensure compliance with the Town’s Outdoor Lighting Law and a photometric plan will also need to be reviewed by the Planning Board to ensure light trespass to neighboring properties is minimized. Based on the above information, impact on noise and light identified in this section would be considered small in magnitude. 17. Consistency with Community Plans c. The proposed action is inconsistent with local land use plans or zoning regulations. Briefly describe the impact on community plans: The Maplewood Phase II project involves a significant increase in density, from the 82 unit/192 bed development that existed on the site until 2019 to a 615 unit/925+/- bed development that will exist after completion of the project. There will be no change in the residential land use characteristic or the graduate/professional student population demographic that will live in the Maplewood II development. The Town of Ithaca Comprehensive Plan recommends focusing new residential development in areas near major employment centers and the City of Ithaca municipal boundary. The Maplewood Phase II project meets the Plan’s recommendation, as it is located on an infill site just beyond the City of Ithaca municipal boundary. The project is also near the Cornell University campus, is about 1.2 miles east of downtown Ithaca, and is within a 10 to 20 minute walk of East Hill Plaza and the center of Ithaca’s Collegetown area. The Comprehensive Plan also recommends denser, mixed-use development in the 10 Mitchell Street/Maple Avenue/Pine Tree Road area of the town, which includes the Maplewood II site. The Comprehensive Plan has designated the Maplewood Phase II project site as an area where traditional neighborhood development (TND) would be appropriate. The project involves a change in the town’s zoning from the current High Density Residential and Multiple Residence zoning designations to a Planned Development Zone (PDZ). The proposed PDZ language for Maplewood II utilizes a form-based, TND zoning approach that includes design standards for many elements of the development. The height and density of buildings within the project will be mitigated through design that is sensitive to the surrounding area. The TND-PDZ approach aligns with the goals of the Town Comprehensive Plan. Based on the above information, impact on community plans identified in this section would be considered small in magnitude. 18. Consistency with Community Character b. The proposed action may create demand for additional community services (e.g., schools, police, and fire) Briefly describe the impact on community character: The project will create a demand for additional police and fire service and could potentially create a slight demand for additional school service. Most of tThese services appear to be adequate to serve the project. However, it is yet to be confirmed if the project will comply with the fire flow requirements of the NYS Fire Code. The applicant has been working with, and will continue to work with, the Town of Ithaca Director of Code Enforcement (Town of Ithaca Fire Marshall) to find a resolution to the fire flow issue. not confirmed whether the specific site layout elements (emergency/fire aerial access, road widths, separation distances between buildings, number, and location of fire hydrants, etc.) will comply with NYS Fire & Building Code provisions. The applicant will need approval for these elements from the Town of Ithaca Director of Code Enforcement (Town of Ithaca Fire Marshall), in consultation with the Ithaca Fire Department. Should the Planning Board grant site plan approval for the project, the board could add a condition that the Town of Ithaca Director of Code Enforcement must approve the proposed fire flow calculations and processes. The character of the existing neighborhood along Maple Avenue and surrounding the project site is a mix of residential apartment complexes and industrial/institutional structures of varying heights, architectural styles and building massing, along with a Cornell educational research farm plot and field on the north side of Maple Avenue. The East Lawn Cemetery is immediately east of the project, with East Hill Plaza commercial area a little more than ¼ mile east of the project. As such, there is no predominant architectural character. The application materials note that the “architecture and landscape will seamlessly blend to reinforce connectivity and community,” and that the “façade design implements strategies to relate the new buildings with the scale of the Phase I residences.” The Phase I residential buildings are four stories tall, with building lengths along Maple Avenue that are around 200+/- linear feet long. The building massing and scale is broken up via balconies and a brick façade that extends out from the buildings and up from the first floor to the third floor of the buildings in two areas. 11 The proposed Phase II buildings are five stories tall, around 250+/- linear feet long, with massing broken up by small sections of glass and pops of color. The proposed architecture and façade design is different from the Maplewood Phase I project but is not out of character with the surrounding neighborhood. As noted in #9 above (Impact on Aesthetic Resources), there are no scenic resources identified in the Town of Ithaca Scenic Resource Inventory or Tompkins County Scenic Resource Inventory that will be impacted by the proposed development. The development will be very visible from Maple Avenue, the East Lawn Cemetery, Maplewood Phase I, and in the Cornell fields across Maple Avenue. However, any visual impacts of the project will be mitigated by the proposed varied landscaping throughout the project and along all sides of the project. Visual impacts could also be mitigated along Maple Avenue by implementing some of the architectural strategies noted above. These specific mitigation measures, along with other site elements such as signage and lighting, should be further reviewed and evaluated by the Planning Board as part of the site plan review process. Based on the above information, impact on community character identified in this section would be considered small in magnitude. PROPOSED RESOLUTION: Recommendation to the Town Board Proposed Planned Development Zone – Maplewood Phase II Project Maple Avenue, Town of Ithaca Tax Parcel No.’s 63.-2-5, 63.-2-6, 63.-2-7.1, and 63.-2-7.3 Town of Ithaca Planning Board December 17, 2024 WHEREAS: 1. This is consideration of a Recommendation to the Town Board Regarding the Proposed Rezoning for the Maplewood Phase II Project on Maple Avenue, located between the Maplewood Graduate Student Apartment complex and the East Lawn Cemetery. The project, which requires a rezoning from Multiple Residence and High Density Residential Zones to a Planned Development Zone (PDZ), involves consolidating four parcels and constructing six (6) five-story apartment buildings, containing 615 units/800 beds in studio, one bedroom, and two-bedroom unit configurations. The project will also include integrated amenity/service spaces, parking areas, trails and pedestrian facilities, open spaces, stormwater facilities, and other site improvements. The project is a Type I Action under the State Environmental Quality Review Act and is subject to environmental review. Cornell University, Owner/Applicant; Michele Palmer, Whitham Planning, Design, Landscape Architecture, PLLC, Agent, 2. The Maplewood Phase II development project has been determined to be consistent with the Town Comprehensive Plan, which included the project site in the “TND High Density” category, intending the area for a mix of higher density housing types “built to create an intentional neighborhood with linkages and proximity to services, employment, public transit, and recreational areas,” 3. The consultant team drafted language for a Maplewood II Planned Development Zone (PDZ) that utilizes a form-based code approach to guide and regulate the form of the development, following the formatting and language used in the Maplewood Graduate and Professional Student Housing Redevelopment Project PDZ (PDZ No. 16), 4. The Town of Ithaca Planning Committee reviewed the draft Maplewood Phase II PDZ language at their meetings on June 20, 2024, July 18, 2024, August 15, 2024, and September 16, 2024, and referred the draft language to the Town Board for referral to the Planning Board, 5. The consultant team, along with Greystar, a developer/owner/manager of collegiate housing, presented the development proposal and draft PDZ to the Town Board on October 7, 2024, where the Town Board, via resolution, then referred the draft PDZ to the Planning Board for review and a recommendation, and 6. The Planning Board, at a public hearing on December 17, 2024, has reviewed, discussed, and considered the draft Maplewood Phase II PDZ language; NOW, THEREFORE, BE IT RESOLVED: That, per Town Code §270-181 (F), the Planning Board hereby recommends that the Ithaca Town Board adopt a local law creating a Planned Development Zone for the Maplewood Phase II Project, with the recommended changes outlined in the draft document titled “Draft Maplewood II PDZ- for 12-17-24 Planning Board meeting.” 1 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg Introduction The Maplewood II Planned Development (PD) PDZ Zone enables and guides the redevelopment of the Maplewood Phase II housing complex, and its underlying site, into a compact, walkable resident community. This §271-18 uses a form-based zoning approach with objective yet flexible standards, to provide clarity and certainty about site planning and the resulting built environment. The project envisions a high-density housing type with a resident community center and potential future allows for neighborhood commercial use as well. Planned Development Zone No. 15 (Maplewood Phase I, §271-1516) consists of both medium and high-density zones. Phase II will function as an additional high-density zone within the overall Maplewood resident community. Maplewood Phase II will connect to Phase I’s grid of streets with a continuation of Lena Street. The Town of Ithaca Comprehensive Plan recommends focusing on new residential development in areas near major employment centers, walkable to nearby destinations, and near the City of Ithaca boundary. Maplewood II is located on an approximately 9-acre infill site entirely within the Town of Ithaca, and approximately 400 feet from the City of Ithaca boundary. The project is near the Cornell University campus, about 1.2 miles east of downtown Ithaca, and within a 10 to 20-minute walk of both East Hill Plaza and the center of Collegetown. The Comprehensive Plan also recommends denser mixed-use traditional neighborhood development between Mitchell Street and Maple Avenue, including the Maplewood site. 271-18.1 Transect Subzone  A transect subzone defines parts of the larger site that will have certain physical and functional characteristics. Maplewood Phase I and Maplewood Phase II constitute subzones of the larger Maplewood resident community. There are two transect subzones in PDZ 15 of Maplewood Phase I and one subzone in the PDZ 17 Maplewood Phase II site area. Figure 1 is an illustrative example of the transect subzone locations and allocation for Maplewood I PDZ 15 (approved) and Maplewood II PDZ 17.  Figure 1: Example of transect subzone location and allocation. Draft Maplewood II PDZ - for 12-17-24 Planning Board meeting 2 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg 271-18.2 Permitted principal and accessory uses The following table shows permitted uses in PD 17, with specific location limitations where applicable. P = permitted use. • = not allowed. (cs) = commercial space in apartment building (cc) = community center Use (definitions in § 271-18.6) PD-17 Dwelling unit P Health/wellness practice P (cc) (cs) 3 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg Professional office P Day Ccare center P (cc) (cs) Restaurant P (cs) Retail and service: general P (cs) Artisan P (cc) (cs) Place of assembly P Garden Mmarket P Community Ggarden P Dog Ppark P Home occupation (accessory to dwelling unit), subject to Town Code § 270-219.2 or successor code P 271-18.3 Neighborhood design 271-18.3 A. Dwelling units The number of allowable dwelling units for PD 17 is: less than or equal to 615 units. The following table showslists the breakdown range of unit numbers and types in PDZ 17. Studios: 230 to 240 One Bedroom: 180 to 190 Two Bedroom: 175 to 185 Total: 585 to 615 Program Total Units Total Beds Studios 240 240 One Bedroom 190 190 Two Bedroom 185 370 Totals 615 800 271-18.3 B. Civic and open space 1. Required civic building Commented [CB1]: PB requests defining “Garden market” - use same definition as was in MWI PDZ Commented [SB2]: List a permissible range of units and beds for each unit type, with the total remaining at 615 units and 800 beds? That way, the PDZ would not have to be amended if the developer wants to slightly change the mix of unit types. Commented [CB3R2]: PB also requests listing a range of total units in case project ends up with, e.g., 241 studios and 189 one-bedroom units. 4 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg The PDZ 17 site must have at least 4,000 sf space within a civic building assigned for resident community center use. It should be located at or close to the center of a built-up area; next to a civic/open space or at the axial termination of a prominent thoroughfare. 2. Required open space area The PDZ 17 site must have ≥25% of the total site must be assigned to for community open space for Maplewood residents and accessible by the public. Open space types, settings, and requirements include the following. Open space type (definitions in §271-18.6) Park.  A park may be a non-linear area, or linear space following connecting ways or natural corridors  A park can include wooded areas with connecting trails throughout  A dog park  A park may be independent of surrounding building frontages.  Park boundary/edge along a neighborhood interior street or perimeter street ROW: ≥10% must abut a street Green  Green boundary/edge along a neighborhood interior street or perimeter street ROW: ≥50% must abut a street  Garden Plaza  Plaza boundary/edge along a neighborhood interior street or perimeter street ROW: ≥50% must abut a street  Court Community open space calculation does not include the following.  A yard, balcony, patio, or other outdoor space for use or access only by a specific dwelling unit or a limited number of dwelling units.  Public or private thoroughfare/street right-of-way, or integral features (such as sidewalks and tree lawn areas).  Parking area or driveway.  Stormwater detention/retention facility or drainage swale area, unless design allows practical use as an accessible year-round amenity for residents of the development (picnic area, passive recreation Commented [SB4]: Specify at least 4,000? It does not have to be exactly 4,000, right? Commented [CB5]: PB recommends word searching doc and clarifying what the “community” is (MWII residents? Members of the public?) Commented [SB6]: Add court and garden to open space types? They were listed here in the Maplewood I law, and there are standards for “open space” and “court” in this law Commented [SB7]: The Maplewood I law also included this: “Areas inside a site envelope for a residential, commercial, or civic building.” Include something like this in this law? 5 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg area, playground, and the like), or it is a bioswale that visually integrates into the larger open space site.  Entry feature, median, or traffic island. 3. Access An open space area must function as part of the broader public realm and allow community-wide access and passage. 271-18.3 C. Thoroughfares and Trails 1. Thoroughfare and trail types and design There is one thoroughfare type: neighborhood local street.: tThere is one trail type: multi-use trail Thoroughfare type ► ▼ Characteristics Neighborhood local street Purpose Primary street through the entire PD site with two vehicle lanes on the two-way thoroughfare, one lane wide enough to accommodate fire apparatus on the one-way thoroughfare. and Pparking provided on both sides of all thoroughfares. Right-of-way width 56’-64’ Sidewalk width 5’-8’ (one side - on the building side of the street and where parallel parking is located) Tree lawn width * 6’-10’ (one side) Parking lane width 8’ (parallel side) 18’ (perpendicular side) Travel area width 26’ (for two-way traffic, two 13’ lanes, no lane dividing marking; for one-way traffic one 26’ travel lane) where fire access is required; shared lanes marked with sharrows Curb type barrier Trail type ► ▼ Characteristics Multi-use Trail Commented [SB8]: Because of the comma placement, “parking on both sides” seems to apply only to one-way thoroughfares and not also to two-way thoroughfares. Clarify the intent either way. 6 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg Purpose Informal linear paved or stabilized path for pedestrian and bicycle circulation and connectivity to the East Hill Recreation Way and adjacent Planned Development Zone No. 15. Must accommodate all intended users and minimize conflicts. Trail width 10’ with minimum 2’ either side mown grass strip to act as a shoulder Curb type none Commented [SB9]: Who the intended users? List somewhere 7 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg Thoroughfare and Trail sections (illustrative examples) Existing thoroughfares along the perimeter of the PDZ 17 site (Maple Avenue) must have improvements (sidewalks, tree lawns, tree planting, and curbs), so they follow neighborhood local street standards as much as possible. A sidewalk must follow the south side of Maple Avenue along the full PD site frontage. A thoroughfare or trail must have hard surface paving (porous or solid asphalt, concrete, or segmental pavers) for sidewalks, parking lanes, and travel lanes. Neighborhood Local Street Section Multi-use Trail Section Commented [SB10]: The travel lanes add up to 25’, but 26’ are required. Revise the graphic. Change “Landscape” on the left to “Tree lawn" Commented [SB11]: The Multi-use Trail Section provisions are confusing. Why are “thoroughfares” mentioned? State where the multi-use trail is located and allowed modes of use 8 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg 2. Thoroughfare and trail layout A tThoroughfares or and trails must be permanently open to the public and provide community-wide access as part of an overall connected street network. A tThoroughfares or and trails must not have gated access. A thoroughfare must begin and end at other thoroughfares. An intersection must approximate a right angle as much as possible. 271-18.43 D. Utilities Permanent utilities (water, sewer, natural gas [if any], district heating/cooling, electricity, communications, and the like) must be underground. Short-term utility service for construction activities may be above ground. A utility easement must be in a location where maintenance or repair work will cause the least disruption. Utility easement location must not prevent or undermine street tree planting. 271-18.5 Site and building design 271-18.5 A. Performance Standards 1. Notwithstanding the foregoing, any use All buildings and other structures permitted in this PDZ shall be in conformity with the following additional standards: 2. Height. The maximum height of buildings and other structures shall be as follows: a. No building shall be erected, altered, or extended to exceed 65 feet in height as determined by an average grade plane measure, but excluding rooftop appurtenances such as mechanical equipment, exhaust pipes, radio antenna, and elevator overrides, provided such appurtenances do not themselves exceed an additional 12 feet in height. b. Abutting the Maple Avenue frontage between the water tower at 227 Maple Ave. and PD 15-H, no building shall be erected, altered, or extended to exceed 58 feet in height as determined by an average grade plane measure, but excluding rooftop appurtenances such as mechanical equipment, exhaust pipes, radio antenna, and elevator overrides, provided such appurtenances do not themselves exceed an additional 12 feet in height. No structure, other than a building, shall be erected, altered, or extended to exceed 20 feet in height. 3. Ground Lot coverage. Total coverage of ground by buildings, thoroughfares and trails, parking lots and sidewalks, and other structures shall not exceed 55% of the PD. Total maximum ground coverage by buildings alone shall not exceed 25% of the PD. 4. Yards.Setbacks. a. Unless a deviation is authorized by the Planning Board, for good cause shown, theThe building setback yard requirements shall be as follows: i. Front setbackyard: from Maple Avenue Right-of-way, as defined in Town Code Chapter 270, shall be not less than 12 feet. ii. Side setbackyards: from any east-west property line shall be not less than 30 feet. iii. Rear setbackyard: from southern property line shall be not less than 10 feet. 5. Building Separation. Building separation will be as dictated by the NYS Uniform Fire Prevention and Commented [SB12]: Numbering is off from here on Commented [SB13]: What is an “elevator override”? (That phrase is used in b, too.) Commented [SB14]: Chapter 270 uses “lot coverage” and “maximum building area” Commented [SB15]: List the standards the Planning Board applies to determine good cause, or delete the PB’s ability to authorize a deviation Commented [SB16]: What does “yard” mean? In Chapter 270, “yard” is defined in relation to the one principal building, but in this PDZ that does not work. Drop the idea of “yards,” use “setback” instead, and state what cannot happen within a setback? Commented [SB17]: Define “right-of-way,” or replace with “street line” terminology and definition used in Chapter 270 Commented [SB18]: Which line(s)? For ii and iii, do you want this to apply to the line between Maplewood I and Maplewood II as well? 9 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg Building Code for building type and construction method. 271-18.5 B. Building types and disposition Principal building types include the following. Building type ► ▼ Disposition Apartment building Civic building Accessory building (bike storage facility) Illustrative example Building Facade Frontage buildout on a street • ≥50% primary frontage • ≥50% corner side frontage n/a n/a Front façade and main entrance orientation May face street or public green space May face street or public green space May face street or public green space Bulk/Massing Height Gross floor area (GFA, square feet) Street-facing wall length without ≥ 2’ offset: Building length: primary façade • 5 stories n/a ≤ 100’ ground story ≤275’ • 1-3 stories • 5,000 ft² -12,000 ft² n/a n/a • 1 story • 1500 ft² - n/a n/a Façade transparency: primary ≥30% ground story ≥30% ground and upper stories ≥50% ground story Commented [SB19]: What is “primary frontage”? Is it inconsistent to require at least 50% on a street, yet allow the front façade to face public green space? Commented [SB20]: Change to < 5 stories? Commented [SB21]: Change to < 1500 ft²? 10 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg frontage. ≥30% upper story Façade transparency: corner side frontage Façade transparency: side/rear facade (if not a party wall): ≥30% ground story ≥30% upper story ≥30% ground and upper stories ≥30% ground and upper stories ≥30% ground and upper stories ≥50% ground story ≥50% ground story Occupancy Dwelling Units Commercial 90 to 110 per building ≤ 5,000 sq ft. on the ground floor, cumulative for the site n/a n/a n/a n/a Bicycle Storage n/a n/a 100 Zoning code (or successor code) provisions allowing certain building features to encroach beyond setback or height limits also apply. 271-18.5 C. Building form and design 1. Four-sided design A building must have consistent material treatment, architectural details, proportions, and colors on all exterior walls. 2. Accessory structures A permanent accessory building must have material treatment, architectural details, proportions, and colors that are consistent with the principal building. 3. Exterior materials Vinyl siding, and prefabricated and pre-engineered metal buildings, are not allowed. This does not apply to temporary buildings for construction field offices and similar short-term uses. 4. Utility and service areas Rooftop or ground-mounted mechanical equipment, utility areas, and trash enclosure or storage areas, require concealment or screening to hide them from view from adjacent pedestrian walkways and thoroughfares. The form of concealment or screening must be architecturally consistent or integral to the host structure. This does not apply to roof-top mounted photovoltaic solar panel systems, though any panels must have antireflective coatings. 271-18.5 D. Parking 1. Required parking spaces The cumulative total of parking for the PD 17 site is as follows. Commented [SB22]: Why require ground-mounted solar panels to be hidden? That will shade them and make them their deployment impossible. That seems odd, as the Town allows ground-mounted solar in all residential districts 11 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg Use Motor vehicle parking (range) Bicycle parking Residential: studio unit 0.05 to 0.25 spaces/unit ≥61 secure or short-term space / residential building 6 units ≥100 in bike storage facility Residential: 1 bedroom unit 0.05 to 0.25 spaces/unit Residential: 2 bedroom unit 0.05 to 0.5 spaces/unit Non-residential (all uses) 0.05 to 0.5 spaces / 500’² GFA ≥1 short-term space / 2000 ft² GFA Public transit stop n/a ≥4 short-term spaces/stop • A minimum of at least 75 total spaces motor vehicle spaces are required • Parking space count may include dedicated spaces for car/bicycle sharing and charging. • Motor vehicle space size: 8.5’ x 18’ clear rectangle area for on-street perpendicular, 7-8’ x 22’ for on-street parallel. • Secure bicycle space: bicycle locker, dedicated space in a garage, anchored rack space with overhead protection from the elements, andor other fully enclosed or secure areas. • Short-term bicycle space: anchored rack space. On-thoroughfarestreet parking spaces may count towards required parking. Two motorcycle parking spaces (each space ≥4.25’ x 7’) may count as one motor vehicle parking space. 2. Off-street parking lot location Off-street surface parking may be along streets. 3. Off-street parking lot design Building siting, landscaping, or architectural treatment must screen a parking area (not including an individual driveway) from thoroughfares and residential areas outside of the PD site. A parking area must have a sidewalk or paved walkway, to provide pedestrian access from nearby thoroughfares. 4.2. Parking surfaces Parking areas must have a fixed impervious or porous surface. Pavement edge must have a clear definition, using curbs or a different durable material. Curbing allowing water runoff (rollover curb, or barrier curb with gaps) is preferable to curbing that traps stormwater. 5.3. Landscape area A parking lot must have ≥1 landscaped interior island (≥8.5’ wide, ≥160 ft² area) for every 10 parking spaces. A row of parking spaces must have a landscape island (or equivalent landscape area) at each end. Commented [CB23]: PB comments associated with parking: -Consider a range that doesn’t start with 0 for motor vehicle parking (min 75/max 160?) -Indicate minimum bike parking (min 50?) -Reference bike parking and bike sharing in one location Commented [SB24]: 1 bike parking space for every 6 units does not seem like enough. Clarify that the standard applies to all residential uses (repeat it on each line). Commented [SB25]: Clarify the meaning of “along streets”. Right now it reads like “off-street” parking is allowed on streets, which cannot be the intent 12 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg A row of parking that is not interrupted by a landscape island must be ≤10 spaces long. A landscape island should function as part of the larger stormwater management system of the PD site. On-street parallel parking does not require landscape islands. On-street perpendicular parking fully adjacent to a landscaped tree lawn or other landscaped area does not require landscape islands. 6.4. Renewable energy Any parking space (on-street and off-street, for any type of vehicle) may have an electric vehicle charging station. ≥5% of off-street parking spaces will be provided with electric vehicle charging stations. at project opening. ≥20% of off-street parking spaces must have utility provisions for future electric vehicle charging stations. A solar carport may cover any off-street parking space. 271-18.5 E. Landscaping 1. Tree classes Street tree refers to trees in a tree lawn or tree well alongside a street or traffic island. Canopy trees and short trees refer to trees in yards, courts, landscaping areas, open space areas, and similar areas. 2. Thoroughfare tree lawns A tree lawn area on a primary or secondary street must have ≥1 street tree every 20’ to 40’ along its length, with an average spacing of ≤30’ along the block length. A maximum of 25% of the trees on the entire site in PDZ 17 may be from a single tree species. A parking lot landscape island must have ≥1 canopy tree for every 160 ft² of landscape island area. 3. Other Llandscape areas Landscaped islands must have ≥1 canopy tree for every 160 ft² of landscape island area. 4. Other Landscape areas A green, court, or garden (§ 271-18.43 B 2) must have ≥1 canopy tree for every ≤2000 ft² of contiguous open space area. For ≤50% of all required canopy trees in other landscape areas, 2 short trees may substitute for 1 canopy tree. 4.5. Tree species for the required plantings Tree species for required plantings must have these traits.  Native or adapted to upstate New York (USDA hardiness zone 5a, 5b, 6a).  Not invasive (according to the most recent Tompkins County Regional Invasive Species and Worst Invasive Species lists), or species with known parasites or pathogens including ash and hemlock. Follow requirements for allowed or prohibited tree species in Town zoning regulations, if applicable. Street tree species must also have these traits: Commented [SB26]: Use a different standard, because “project opening” is too vague. Replace it with “”by the time of the issuance of the first certificate of occupancy”? Commented [SB27]: Parking lot standards need to be under their own heading, (as with Maplewood I), not lumped in under the Thoroughfare section Commented [SB28]: Only “green” is listed in the cited section, although I think “court” and “garden” should be listed in the cited section, too 13 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg  Mature height of ≥30’ except where restricted by fire access requirements.  A crown that can grow to shade a sidewalk and street.  Downward-oriented root system.  Salt tolerant.  Not brittle, or prone to dropping heavy fruit. Canopy tree species must have a mature height of ≥40’ except where restricted by fire access requirements. Short tree species must have a mature height of ≥20’. A street tree or canopy tree planting must have a diameter at breast height (DBH) of ≥2”. A short tree planting must have a DBH of ≥1.5”. 5.6. Other landscaping requirements Exposed ground surfaces must have groundcover planting or mulch to cover otherwise exposed soil. 271-18.5 F. Fences and walls Maximum fence or wall height is 5’ in a front setback area and 8’ elsewhere. Acceptable materials for walls include brick, stone, split-faced blocks, decorative blocks, cast stone, and glass blocks. Acceptable materials for fences include wood, composite fencing, or wrought iron, PVC/vinyl,or PVC coated/color coated chain link (limited to water tank fencing as required by the City of Ithaca, or welded wire panels. This does not apply to deer fencing, snow fencing, and temporary fencing for construction and short-term activities. Barbed wire, concertina wire, and un-coated (galvanized) chain link are not acceptable. This does not apply to temporary fencing for construction activities. 271-18.5 G. Signs Signs must conform to then-current Town of Ithaca sign code (or successor code) standards for the following:  Attached signs on storefronts: standards for the NC-Neighborhood Commercial (or successor) zone  Residential and other uses: standards for the MR-Multiple Residence (or successor) zone. 271-18.5 IH. Outdoor Llighting 1. Light output Photometric performance must conform to the then-current Town of Ithaca outdoor lighting law (or successor code) standards. 2. Freestanding fixtures/poles Height:  Neighborhood local streets: ≤16’ Commented [SB29]: Right now the law does not list any setbacks. Why are the fence/wall heights higher than those allowed in Maplewood I? Commented [SB30]: Chapter 270 does not allow chain link fences. Why allow them in this PDZ? If allowed, restrict their use to specific uses, such as a sports field? Commented [SB31]: Same comment 14 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg  Elsewhere: ≤12’ Design and location:  Pole design should have a distinct base, middle, and top.  Maximum form base/Sono tubeSonotube top is ≤4” above grade.  Poles must not block sidewalks or walkways. 3. Attached fixtures  Fixture design should be consistent with the architectural style and detailing of the host structure.  Sconces, gooseneck fixtures, and recessed fixtures are allowed. Wall-pack lighting is not acceptable. 271-18.6 Definitions These words or terms have a special meaning in § 271-18 for this PD. Apartment building (building type in § 271-18.5): Building with >3 dwelling units, vertically and horizontally integrated, connected with one or more shared entries. Artisan (use in § 271-18.3): Establishment or studio where people make art or products by hand, using handheld tools or small-scale table-mounted equipment. This includes related sales onsite. Average Grade Plane: Is a reference plane representing the average of finished ground level adjoining the building at exterior walls. Where the finished ground level slopes along the exterior walls, the reference plane shall be established by averaging the two lowest grade points and the two highest grade points on the exterior to establish the overall building height. Block (context of roads or thoroughfares): area bounded by thoroughfares, or a combination of thoroughfares and barriers to continued development (examples: public land, waterway). Civic building (building type in § 271-18.5): A building that accommodates a place of assembly, civic, or community use. Court (open space type in § 271-18.4): Open space for civic purposes, passive or active recreation, or connectivity within or through the site. Building frontages spatially defines define a court. Day care center (use in § 271-18.3): Establishment providing any of the following services, as defined by the NYS Department of Social Services or its successor agency in the following or successor regulations, for all or part of a day: child day care (18 NYCRR §418.1), small day care (18 NYCRR §418.2), school-age child care (18 NYCRR §414). Dog Ppark: A park for dogs to exercise and play off-leash in a controlled environment under the supervision of their owners. Dwelling unit (use in § 271-18.3): An apartment, or a room or group of connected rooms, occupied or set up as separate living quarters for living, sleeping, cooking, eating, bathing, and sanitation purposes. Frontage: Area between a building facade and a neighboring thoroughfare or court, including built and vegetated components. Garden (open space type in § 271-18.4): Open space for a playground or resident community garden. Commented [SB32]: Revise section cross-references throughout once numbering is set Commented [SB33]: Changed wording back to that used in the Maplewood I law, because the NYCRR lists “day care” and “child care” as two words, not one Commented [SB34]: Why were the “Frontage buildout” and “Garden market” definitions from the Maplewood I law not included in this law? This law uses both of those terms 15 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg Garden Market: (use in § 271-16.3) Sale of produce or value-added farm and food products (as that term is defined in NY Agriculture and Markets Law §282(2), or its successor statute), or community supported agriculture (CSA) share or farm-to-table. Green (open space type in § 271-18.4): Open space for the resident or public community gathering, or passive or active recreation, with prominent (≥50%) softscape or vegetative cover (such as lawn, trees, shrubs, plant beds). Landscaping and/or street frontages define its space more so than building frontages. Health/wellness practice (use in § 271-18.3): Establishment providing outpatient medical, medical allied health care, or alternative medical services. Park (open space type in § 271-18.4): Open space for recreation, including dog recreation, or aesthetic enjoyment. Prominent (≥50%) landscape includes paths and trails, fields and meadows, water bodies, woodland, lawns, gardens, and open shelters. PavementSurface, fixed: Durable, fixed surface formed from asphalt, concrete, tightly spaced segmental pavers, and/or similar durable materials, both pervious and impervious. PavementSurface, porous: Durable surface allowing easy passage of water through pores. This includes segmental pavers, open cell pavers, and similar products; and ribbon/double track driveways with wheel strips of a durable pavement material. This does not include crushed stone, wood chips, dirt, grass, or other loose or unimproved surfaces. Place of assembly (use in § 271-18.3): Facility used mainly for public/resident assembly for worship, meeting, or community purposes. (Examples: religious congregation, secular assembly, community center, common house, amenity center.) Plaza (open space type in § 271-18.4): Open space for resident or public community gathering, or passive or active recreation, with prominent (≥50%) hardscape cover. Building and street frontages define its space more so than landscaping. Primary frontage: the area between the building or structure and the thoroughfare to which it is oriented. Professional office (use in § 271-18.3): Establishment providing professional, administrative, clerical, or information processing services. Restaurant (use in § 271-18.3): Establishment preparing and selling food, drinks, and/or alcoholic beverages in a ready-to-consume state, to customers onsite or delivery offsite. Retail and service - general (use in § 271-18.3): Establishment selling or renting a tangible good or product to the public, and/or providing a service to customers onsite. Stubout thoroughfare: improved dead-end thoroughfare ending at the boundary of a development site, serving as a provision for later extension and connection to thoroughfares and development beyond the site. Thoroughfare: paved travel way with travel lanes for vehicles and bicycles, parking lanes, and/or sidewalks or paths; and related infrastructure and/or amenities. Transparency: building wall length occupied by functioning doors and/or windows ≥5’ tall. 271-18.7 Administration 271-18.7 A. Site plan Commented [SB35]: Deleted “stubout thoroughfare” because that term is not used in this law 16 For 12-17-24 PB meeting: Red-lined: Attorney for Town edits & PB recommended edits at 10-15-24 mtg Blue-lined: Applicant team response edits after 10-15-24 PB mtg A final site plan approved by the Town Planning Board pursuant to Chapter 270, Zoning, is required for development in this PDZ zone. 271-18.7 B. Miscellaneous 1. Violations and enforcement Any violations of the terms of this section shall constitute a violation of the Town of Ithaca Zoning Ordinance and shall be punishable as set forth in said ordinance and § 268 of the Town Law of the State of New York. Each week's continued violation shall constitute a separate offense. Notwithstanding the foregoing, the Town reserves for itself, its agencies and all other persons having an interest, all remedies and rights to enforce the provisions of this section, including, without limitation, actions for any injunction or other equitable remedy, or action and damages, in the event the owners or lessees of the parcels covered by this section fail to comply with any of the provisions hereof. If any building or land development activity is installed or conducted in violation of this section, the Code Enforcement Officer may withhold any building permit, certificate of occupancy, or certificate of compliance, and/or prevent the occupancy of said building or land. 2. Town Code applicability Except as otherwise specified in this section, all provisions of the Town of Ithaca Code shall apply to all development, structures, and uses in Planned Development Zone No. 17. 271-18.8 PDZ area Area rezoned. The area encompassed and rezoned in accordance with this section to be Planned Development Zone No. 1817 is described below. The Official Zoning Map of the Town of Ithaca is hereby amended by adding such district at the location described. Description of Area Rezoned to Planned Development Zone No. 17 All that tract or parcels of land situatedsituate in the Town of Ithaca, County of Tompkins, State of New York, bounded and described as follows: ALL THAT TRACT OR PARCEL OF LAND situatedsituate in the Town of Ithaca, County of Tompkins, State of New York, being bounded and described as follows: Legal Description to follow. Greystar Maplewood Phase II Phone: 607.272.1290 Email: admin@whithamdesign.com 404 North Cayuga Street, Ithaca NY 14850 1 November 15, 2024 CJ Randall Director of Planning The Town of Ithaca 215 North Tioga Street, Ithaca, NY 14850 Re: Maplewood Phase II – Updated Preliminary Site Plan Review – Town of Ithaca Planning Board Dear CJ and all, On behalf of the project team, please find updated submission materials attached for the Maplewood Phase II proposed project. With this submission, we are updating drawings and documents for SEQR review and Preliminary Site Plan Review. We request that the Town consider these materials as additional updated information and request to be added to the agenda at the December 17 Planning Board meeting to continue the SEQR review process. The project proposes a redevelopment of the former East Hill Apartments with new construction of apartment units for graduate and professional students at Cornell. This development will be an extension of the existing Maplewood Phase I site, and it is proposed that a new PDZ be created for Phase II to include the project area. Residents will share amenities and open spaces with the existing Maplewood project. Maplewood Phase II proposes approximately 800 new beds, spread among approximately 650 new units between six new residential buildings and a community center. The project team is composed of: • Greystar Development East, LLC – Sponsor/Developer • CBT – Architects • GTS Consulting – Traffic Engineers • T.G. Miller, P.C. – Project Civil Engineers • Whitham Planning & Design – Landscape Architects, Approvals & Project Coordinators This submission is intended to provide an update on the progress of design and planning for this project. The updated materials included in this submission are as follows: • Rendered Site Plan • Updated Landscape Plans • Updated Civil Drawings • Updated SWPPP • Parcel Consolidation Form We look forward to our further conversation with the Planning Board and Town staff. Please let us know if there are any questions. Sincerely, Michele A Palmer RLA, ASLA, LEED GA Senior Associate Whitham Planning Design Landscape Architecture, PLLC C101EXISTING CONDITIONSPLANSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 C102DEMOLITIONPLANSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 ABCDEFGTSTSTTSTT C103UTILITY PLANSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 ABCDEFGC104GRADINGPLANSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 ABCDEFGTSTSTT STT C105DRAINAGEPLANSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 C105ASTORM STRUCTURETABLESSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 BCDEFGAC106ESC PLAN:MOBILIZATIONSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 BCDEFGAC107ESC PLAN:BUILDING D,E,GSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 ABCDEFGC108ESC PLAN:BUILDING A,B,C,FSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 ABCDEFGC109ESC PLAN:STABILIZATION PHASESCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/15/2024 Greystar Maplewood Phase II Phone: 607.272.1290 Email: admin@whithamdesign.com 404 North Cayuga Street, Ithaca NY 14850 1 December 9, 2024 CJ Randall Director of Planning The Town of Ithaca 215 North Tioga Street, Ithaca, NY 14850 Re: Maplewood Phase II – Updated Preliminary Site Plan Review – Town of Ithaca Planning Board Dear CJ and all, On behalf of the project team, please find attached additional updated submission materials for the Maplewood Phase II proposed project. With this submission, we are updating drawings and documents for SEQR review and Preliminary Site Plan Review. We request that the Town consider these materials supplemental to those submitted on November 15 for review at the December 17 Planning Board meeting to continue the SEQR review process. The project proposes a redevelopment of the former East Hill Apartments with new construction of apartment units for graduate and professional students at Cornell. This development will be an extension of the existing Maplewood Phase I site, and it is proposed that a new PDZ be created for Phase II to include the project area. Residents will share amenities and open spaces with the existing Maplewood project. Maplewood Phase II proposes approximately 800 new beds, spread among approximately 615 new units between six new residential buildings and a community center. The project team is composed of: • Greystar Development East, LLC – Sponsor/Developer • CBT – Architects • GTS Consulting – Traffic Engineers • T.G. Miller, P.C. – Project Civil Engineers • Whitham Planning & Design – Landscape Architects, Approvals & Project Coordinators This submission is intended to provide an update on the progress of design and planning for this project. The following describes the changes to the previously submitted materials. SITE PLANNING • Minor adjustments to building locations were made to allow for more space between buildings and parking areas thus allowing for reduced retaining walls and improved sightlines from units. • An access road was added between D/E and C/F buildings per fire department request. This also resulted in minor adjustments to building locations to allow for more space between the buildings. • An active recreation location plan was added identifying activity zones. • Several parking spaces were removed to accommodate the above site changes. The total number of proposed parking spaces on the site has been reduced from 161 to 155. Public, Accessible, EV Charging, and Car Share parking spaces were not impacted. BUILDING ARCHITECTURE • The Residential Building Material Palette was updated. The materiality of Level 1 changed from natural stone to fiber cement due to cost escalation. Greystar Maplewood Phase II Phone: 607.272.1290 Email: admin@whithamdesign.com 404 North Cayuga Street, Ithaca NY 14850 2 • Building A was mirrored and rotated. The main entrance from Maple Ave shifted west (closer to Phase 1) to provide an accessible entry from the main Maple Avenue walk/trail without modifications to existing roadway grades. • Building A was adjusted. We heard concerns about the height and massing of Building A as related to Phase 1 adjacent building. The updated massing provides a better transition between the Phase 1 and Phase 2 buildings by recessing the northwest corner mass and stepping it away from Maple Ave. • The use of glass in the residential building’s main entrances and study lounge curtainwall was adjusted to reduce the total amount of glass and create a better relationship with the vertical cement siding expression. • The building paint colors were refined. A wood-tone color palette will provide more variety and identity for the six residential buildings. The updated materials included in this submission are as follows: • Rendered views for visual assessment • Updated building floorplans • Updated building elevations • Updated Site Plan • Updated Traffic/Parking diagram • Updated Fire Access plan • Activity location diagram We look forward to our further conversation with the Planning Board and Town staff. Please let us know if there are any questions. Sincerely, Michele A Palmer RLA, ASLA, LEED GA Senior Associate Whitham Planning Design Landscape Architecture, PLLC PLANNING BOARD11-15-2024 MAPLEWOOD II ABCDEFGSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/26/20241 OF 2E24-09AS SHOWN11/26/2024IFD ACCESS PLAN GCDEFCDEFSCALEDATE ISSUEDPROJECT #REVISIONS#DATEDESCRIPTIONCornell - MaplewoodPhase 2301 Maple Ave, Ithaca, NY 14850PRELIMINARY SITE PLANSUBMISSIONE24-09AS SHOWN11/26/20242 OF 2E24-09AS SHOWNIFD ACCESS PLAN 09-17-2024 MAPLEWOOD II POTENTIAL PRE-FABRICATED BIKE SHELTER (100 BIKES) 09-19-2024 MAPLEWOOD II BIKE RACK EXAMPLE (MATCH MAPLEWOOD I)