HomeMy WebLinkAboutPWC Minutes 1999-12-26 DISPOSITION DATE
s/*r 4
Town of Ithaca Public Works Committee Meeting l
October 26, 1999, 8:00 a.m.
Town of Ithaca Highway Facility
1. Approval of Minutes
December, 1998
May 25, 1999
June 22, 1999
August 24, 1999
2. Discussion on Wycoff Road Water Main.
3. Update on Park Lane Project.
4. Discussion on Sidewalks on Renwick Heights Road.
5. Discussion Tareyton Drive 2000 Project.
6. Review of New Town Hall Plan and Schedule.
7. Update on Integrated Water System.
8. Update on Integrated Sewer System.
ghk
pc: Mary Bryant, Administrative Assistant
Joan Lent Noteboom,Town Clerk
Andrew Frost, Director of Zoning/Building
Jonathan Kanter, Director of Planning
w
DISPOSITION DATE
C/4/41
Town of Ithaca Public Works Committee Meeting
October 26, 1999,8:00 a.m.
Town of Ithaca Highway Facility
Present: David Klein, Chairperson; Fred Noteboom,Cathy Valentino, Dan Walker,
Gene Redman,and Rich Schoch
The meeting started at 8:10 a.m.
The minutes from December 1998, May 25, 1999,June 22, 1999, and August 24, 1999
were approved.
Wycoff Road Water Line
Fred Noteboom said that in conjunction with the Renwick Drive Bridge reconstruction,
the Town would like to put in an 8" water main. This line would start at the Sunset
Park in the Village of Cayuga Heights and go into the Town of Ithaca.
Dan informed the Committee that he would like to have the Town's forces do the work
before the spring of 2000, when we anticipate Tompkins County starting work on the
bridge. Currently the water comes down Renwick Drive,curves, and then goes to E.
Shore Drive. During the bridge construction they will still put in the valves so this
system would then be a"looping" system. It would cost between$30,000 and $40,000.
A temporary system, which is what the County is proposing,would cost between
$15,000 and $20,000. A permanent water line going down Wycoff Road seems the better
alternative. Dan does not want the Town to pay for a temporary water line while the
Renwick Drive Bridge is being rebuilt.
David asked if Cayuga Heights has been informed of our intentions. Dan indicated that
he will talk to them, and that this line will not serve any Village customers. David said
that we should put our intentions in writing.
Dan indicated that there is some money in the fund balance for Water Maintenance.
David was concerned for the safety of the public if the Town starts working on water
lines and has a lot of holes in the earth. Dan said that the Town's forces would have to
put in a length of pipe and bury then go to the next. We also need to talk to the School
district about the bus schedule on Wycoff Road. Dan estimates it to take about two
weeks to complete. The Committee agreed that they do not want the roads closed all
Public Works Committee Minutes,October 26,1999 Page 2
winter, so we need to keep in contact with the County, so the Renwick Drive Bridge
work is either started and completed during the winter or not started until spring.
Fred indicated that Tompkins County has sent the Town one or two updates on this
bridge and the King Road Bridge. Fred indicated that Tompkins County, in their
agreement,has agreed to maintain the deck of the Renwick Drive Bridge for 15 years.
This project needs to be added to the December Town Board Meeting for their
discussion.
Renwick Heights Sidewalk
Fred informed the Committee that Renwick Heights Road is on the schedule for
reconstruction in 2000. There is a sidewalk (from the dead end to E. Shore Drive) that is
in bad shape; there are also two box culverts that need to be replaced. According to the
sidewalk ordinance, it appears that we will have to ask the residents to pay for redoing
the sidewalk. We will have a meeting with the residents to discuss this and the
construction that will be taking place. If the area residents decide they want to pay for
the sidewalk, the Town forces will be able to realign the sidewalk and put in new box
culverts at the same time as we redo the road.
Cathy Valentino felt that the sidewalk ordinance should be discussed with the Town
Board. We will put this on the Town Board's December meeting agenda. Cathy asked
that Fred supply a map of the area so the Board will know what the area looks like. She
would like to have the estimated cost for rebuilding the sidewalk also. David said that
a rule of thumb is $4.00 to $4.50 a square foot.
Update on Park Lane
Fred said the work on Park Lane is coming along good. We have been in touch with the
winery and they have been cooperative. There is more work to be done than we
expected, but work can continue throughout the winter.
Fred said that the road cut for the Quick's property has been done, along with some
drainage work. This work is part of the Storm Water Management project.
Fred said that Park Lane,from Brian Drive to Route 79,would be re-paved in the year
2000.
Cathy indicated that a neighborhood sign would be nice to have on Park Lane
indicating that the area is residential.
Public Works Committee Minutes,October 26,1999 Page 3
Snow and Ice Removal Questions
Cathy asked if the Town has certain places to salt before others. Fred indicated that we
do and that on the East Hill Honness Lane and Snyder Hill are two roads that we go to
first.
Fred indicated that we have been talking to Tompkins County about the snow and ice
contract. This year the Town will be plowing and salting all the roads in the
Northeast—including County roads—this year. Tompkins County will now be plowing
and salting Ellis Hollow Road, Game Farm Road, Maple Avenue, and Pine Tree Road
from Route 366 to Ellis Hollow Road. We will to do this for a year and then evaluate it.
David asked about the costs. Fred indicated that there is a formula used to figure out
the cost which is based on actual costs from the year before.
Tareyton Drive Project
In 2000 the Town will be reconstructing Tareyton Drive. Mainly, we will be working on
the drainage and re-paving the road. Fred indicated that at the meeting with the
residents of the Northeast,Tareyton Drive was one of the areas of concern for drainage.
We are looking at open ditching and, perhaps,replacing culvert pipes under the
driveways. David asked if the Town re-seeds the ditches after we clean them. Rich
Schoch said yes. We will have a meeting with the residents of the area to answer any
questions they may have.
The survey work has already been done. We will be taking out the "bubble" in the
road. This "bubble" is an old cul-de-sac—before the road was extended.
There was a discussion on the reconstruction of the sharp curve on Kay Street.
New Town Hall and Schedule for Building
Dan Walker indicated that he has the plans,which were reviewed by the Committee.
The authorization to bid the New Town Hall construction project will be presented to
the Town Board at their November meeting. The bid specifications will then be
available on November 8 or 9. The bids will be due to the Town December 9, 1999. The
authorization to award the bids will be presented to the Town Board at their December
meeting. Dan says that construction should begin in January.
Public Works Committee Minutes,October 26,1999 Page 4
Dan indicated that plans include about$400,000 for the additions in the basement, and
about$38,500 for the documents. Currently the cost to rebuild the building is
approximately$1.7 miIlion.
Dan indicated that the Post Office drawings are available for review also. Dan will have
HOLT review them.
Dan said that it will cost the Town$62 a set to make specifications for bidders. We will
need about 50 sets. Dan indicated that we will charge the bidders $100 for a set of
specifications.
Intergrated Water and Sewer Systems
Dan indicated that these projects are in the same place as last year. Cathy said that she
feels that nothing more will be done until after the elections. They are continuing to
meet on a regular basis.
Fred indicated that Agenda #15 on the Town Board Meeting agenda,will not be
needed. We will cut out the blacktop from the sidewalk that is on the private property.
The meeting was adjourned at 10:30 a.m.
ghk