Loading...
HomeMy WebLinkAboutTB Minutes 1985-09-10 PLANNING AND ENGINEERING REPORT Lawrence P . Fabbroni , P . E . . Town Engineer SEPTEMBER 10 , 1985 through OCTOBER 7 , 1985 Water - Contract Administration Watermains Phase II - - PRV main and installation , private PRV installation , dry hookups, citizen Sewer inquiries , applications , special low pressure boosting conditions - Monitor Wage Compliance Watermains Phase II - Planning future watermain extensions Parks - Awaiting Town Attorney review of Sand Bank Road -Buttermilk improvement agreement - Awaiting Town Attorney review of permanent easement Town Hall - Preliminary design investigations for heating -cooling rear building Highways - Burns Road -- Property Closings -- still pending Town Attorney action -- NYSDOT Permit Application - - Continued placement of fill through gravel -- Compensation to City for gravel in helping excavation of the Silt Dan -- Project inspection for S . O . S . with NYSDOT - Park Lane -- Design of drainage interconnections at Rt . 79 intersection with NYSDOT E . I . C . - - Permit Application to NYSDOT Maintenance -- Design of Gas Line Support Bridge in consultation with NYSEG - Forest Horne Drive -- Delivery of gabion baskets - - Preliminary coordination with City Transit - Circulation of NET Contracts Hospital - Refinement of design with Hospital - Meeting with Hospital on Route 96 alternative - Meeting with NYSDOT and Hospital on Route 96 alternative Planning & Engineering Report 9 / 10 / 85 thru 10 / 7 / 85 Page 2 Sewer - Brief SJS Committee and subcommittee on contract progress and Treatment change orders , progress payments and requests for Contracts 1 , Plant 21 3 , 4 , 5 , 61 7 , 3A, 4A, 5A, 6A - Monitor compliance with MBE /WBE, Labor rates , CPM - Monitor completion of final punch list items for Contract 1 - Land Outfal l - Monitor replacement of end section at overflow in Cascadilla Creek - Monitor changed site conditions and construction approach on First and Franklin Streets - Monitor progress of water quality study of Cayuga Lake - Monitor inspection adequacy , efficiency , and timeliness of Stearns & Wheler inspection and project management , particularly : Influent Building -- Block and Brick Work, Screen Installation , Concrete Finishes , Pre -Cast Plank Cutouts Secondary Digester -- Continued Warranty questions and painting Primary Digester -- Insulation Cascadilla Creek - Overflow reconstruction, liability for MH4 cofferdam Lake -- Contract claims , documentation of delays , issuance of change orders First and Franklin Streets -- Unforeseen Conditions - Monitor steel placement , concrete placement , etc . ( form, steel , and concrete ) , base slab one phostrip tank complete , base slab all galleries except # 2 complete , 1 / 2 primary tank walls complete , forming for gallery decks continues , primary trusses and bottom plate ( top side) completely painted , secondary digester truss and bottom plate 1 / 2 completed painting , completed welding , cofferdam for manholes in place along Franklin Street , Contract 1 completed with exception of Cornell plantings , block work and placement of precast roof plank complete , brick work 9 / 10 complete, fascia panel supports begun , pump piping with motor and valves 3 / 5 complete , installation of screeds 2/ 5 complete, conduit from influent building to transformer pad complete , conduit from generator building to plant 1 / 4 complete , conduit under administration building slab complete , generator building block walls and precast roof complete , MCC and HVAC units lifted into influent building , patching of secondary digester leaks , concrete finishing 3 / 4 complete , shear ring secondary digester complete , shear ring primary digester being poured , top roof plates blasted and painted 1 side 1 /4 complete - Open bids Contract 7 -- Monitoring Stations - Preconstruction meeting Contract 7 Drainage - Fall Creek Wall repair - Gabions delivered - Cobbles being staged LPF/ nmf 10 / 7 / 85 ASSISTANT TOWN ENGINEER ' S MONTHLY REPORT SEPTEMBER 10 , 1985 to OCTOBER 7 , 1985 Robert R . Flumerfelt , P . E . 1 . Burns Road a . Stakeout for finish grades - Phase I . b . Construction progress : Phase I all gravel sub - base placed , crushed stone base course placed , ready for final grading . Phase II earthwork approximately 75 % complete , gravel sub - base and drainage fabric placement approximately 60o complete . 2 . Park Lane Extension a . Design of intersection with Rt . 79 and coordination of design of drainage structures with NYSDOT . b . Preliminary design of structure to support existing 10 " gas main . 3 . Snyder Hill Road a . Stakeout of control for lowering approximately 100 feet of existing 8 " sanitary sewer main . 40 1985 Water Improvements - Phase II a . Contract administration , construction inspection . b . Watermains , services , and Elm Street pressure reducing vault completes minor cleanup remaining . 5 . Fall Creek Gabion Retaining Wall along Forest Home Drive a . Preliminary planning for start of construction this month . RRF / nf 10 / 7 / 85