HomeMy WebLinkAboutTB Minutes 1985-09-10 PLANNING AND ENGINEERING REPORT
Lawrence P . Fabbroni , P . E .
. Town Engineer
SEPTEMBER 10 , 1985 through OCTOBER 7 , 1985
Water - Contract Administration Watermains Phase II - - PRV main
and installation , private PRV installation , dry hookups, citizen
Sewer inquiries , applications , special low pressure boosting
conditions
- Monitor Wage Compliance Watermains Phase II
- Planning future watermain extensions
Parks - Awaiting Town Attorney review of Sand Bank Road -Buttermilk
improvement agreement
- Awaiting Town Attorney review of permanent easement
Town Hall - Preliminary design investigations for heating -cooling rear
building
Highways - Burns Road -- Property Closings -- still pending Town Attorney
action
-- NYSDOT Permit Application
- - Continued placement of fill through gravel
-- Compensation to City for gravel in helping
excavation of the Silt Dan
-- Project inspection for S . O . S . with NYSDOT
- Park Lane -- Design of drainage interconnections at Rt . 79
intersection with NYSDOT E . I . C .
- - Permit Application to NYSDOT Maintenance
-- Design of Gas Line Support Bridge in consultation
with NYSEG
- Forest Horne Drive -- Delivery of gabion baskets
- - Preliminary coordination with City
Transit - Circulation of NET Contracts
Hospital - Refinement of design with Hospital
- Meeting with Hospital on Route 96 alternative
- Meeting with NYSDOT and Hospital on Route 96 alternative
Planning & Engineering Report 9 / 10 / 85 thru 10 / 7 / 85 Page 2
Sewer - Brief SJS Committee and subcommittee on contract progress and
Treatment change orders , progress payments and requests for Contracts 1 ,
Plant 21 3 , 4 , 5 , 61 7 , 3A, 4A, 5A, 6A
- Monitor compliance with MBE /WBE, Labor rates , CPM
- Monitor completion of final punch list items for Contract 1 - Land
Outfal l
- Monitor replacement of end section at overflow in Cascadilla Creek
- Monitor changed site conditions and construction approach on First
and Franklin Streets
- Monitor progress of water quality study of Cayuga Lake
- Monitor inspection adequacy , efficiency , and timeliness of Stearns
& Wheler inspection and project management , particularly :
Influent Building -- Block and Brick Work, Screen
Installation , Concrete Finishes ,
Pre -Cast Plank Cutouts
Secondary Digester -- Continued Warranty questions and
painting
Primary Digester -- Insulation
Cascadilla Creek - Overflow reconstruction, liability for
MH4 cofferdam
Lake -- Contract claims , documentation of delays , issuance
of change orders
First and Franklin Streets -- Unforeseen Conditions
- Monitor steel placement , concrete placement , etc . ( form, steel ,
and concrete ) , base slab one phostrip tank complete , base slab
all galleries except # 2 complete , 1 / 2 primary tank walls
complete , forming for gallery decks continues , primary trusses
and bottom plate ( top side) completely painted , secondary
digester truss and bottom plate 1 / 2 completed painting ,
completed welding , cofferdam for manholes in place along
Franklin Street , Contract 1 completed with exception of Cornell
plantings , block work and placement of precast roof plank
complete , brick work 9 / 10 complete, fascia panel supports
begun , pump piping with motor and valves 3 / 5 complete ,
installation of screeds 2/ 5 complete, conduit from influent
building to transformer pad complete , conduit from generator
building to plant 1 / 4 complete , conduit under administration
building slab complete , generator building block walls and
precast roof complete , MCC and HVAC units lifted into influent
building , patching of secondary digester leaks , concrete
finishing 3 / 4 complete , shear ring secondary digester complete ,
shear ring primary digester being poured , top roof plates
blasted and painted 1 side 1 /4 complete
- Open bids Contract 7 -- Monitoring Stations
- Preconstruction meeting Contract 7
Drainage - Fall Creek Wall repair
- Gabions delivered
- Cobbles being staged
LPF/ nmf
10 / 7 / 85
ASSISTANT TOWN ENGINEER ' S MONTHLY REPORT
SEPTEMBER 10 , 1985 to OCTOBER 7 , 1985
Robert R . Flumerfelt , P . E .
1 . Burns Road
a . Stakeout for finish grades - Phase I .
b . Construction progress :
Phase I
all gravel sub - base placed ,
crushed stone base course placed , ready for
final grading .
Phase II
earthwork approximately 75 % complete ,
gravel sub - base and drainage fabric
placement approximately 60o complete .
2 . Park Lane Extension
a . Design of intersection with Rt . 79 and coordination of
design of drainage structures with NYSDOT .
b . Preliminary design of structure to support existing 10 "
gas main .
3 . Snyder Hill Road
a . Stakeout of control for lowering approximately 100 feet
of existing 8 " sanitary sewer main .
40 1985 Water Improvements - Phase II
a . Contract administration , construction inspection .
b . Watermains , services , and Elm Street pressure reducing
vault completes minor cleanup remaining .
5 . Fall Creek Gabion Retaining Wall along Forest Home Drive
a . Preliminary planning for start of construction this
month .
RRF / nf
10 / 7 / 85