HomeMy WebLinkAboutPB Resolution 25-07 1767 E Shore Dr Site Plan Approval ZamboniRESOLUTION PB 25-07
TOWN OF LANSING PLANNING BOARD RESOLUTION
ZAMBONI STORAGE FACILITY LOCATED AT "THE RINK"
SEQRA NEG DEC & FINAL SITE PLAN APPROVAL
WHEREAS; an application was made by Gerry Pendell, general contractor, for Site Plan Review of a 30' x
40' pole barn type storage structure (as shown in the drawing set "Community Recreation Center Machine
Storage Building Site Plan" dated 1/28/2025) on land owned by the Community Rec Center INC located at TPN
37.1-6-9. The purpose of this storage facility is to house The Rink's new electric Zamboni machine. The project
consists of the erecting of a 30' x 40' pole barn structure as well as installation of related underground electrical
utility lines. This project is located in the R2 — Residential Moderate Density zoning district which does permit
the construction of a commercial accessory structure pending site plan approval; and
WHEREAS, 6 NYCRR § 617 of the State Environmental Quality Review Act ("SEQRA") requires that a Lead
Agency be established for conducting environmental review of projects in accordance with state environmental
law, and the Lead Agency shall be that local agency which has primary responsibility for approving and funding
or carrying out the action; and
WHEREAS, the Planning Board, being the local agency which has primary responsibility for approving
the action declares itself the Lead Agency for the xeview of this action under SEQRA; and
WHEREAS, 6 NYCRR § 617.5 (C)(9) determines "construction or expansion of a primary or
accessory/appurtenant, non-residential structure or facility involving less than 4,000 square feet of gross floor
area and not involving a change in zoning or a use variance and consistent with local land use controls, but not
radio communication or microwave transmission facilities" 'to be a Type II action, which is not subject to
further review under SEQRA; and
WHEREAS, the action noted above is exempt from NYS General Municipal Law § 239 -1, -m, and -n, and will
not require further review from the Tompkins County Planning and Sustainability Department; and
WHEREAS; the Town of Lansing Planning Board, the agency with authority to approve this action, determined
that, due to insignificant size and location, no public hearing was necessary for this project; and
WHEREAS, the Town of Lansing Planning Board has evaluated this project under the applicable standards for
Site Plan Review outlined in Town Code § 270-27; and
WHEREAS, the Planning Board has considered and carefully reviewed the requirements of the Town code
relative to`site plan review, the unique needs of the Town due to the topography, the soil types and distribution,
and other natural and man-made features upon and surrounding the area of the proposed site plan, and the Planning
Board has also considered the zoning in the area and the project in light of the Town's Comprehensive Plan and
compliance therewith, and as the underlying use is a permitted use in the zone in which located; and
Page 1 of 2
NOW, THEREFORE, BE IT RESOLVED AS FOLLOWS:
That the Planning Board of the Town of Lansing does hereby grant Site Plan Review approval to construct a 30'
x 40' pole barn type storage structure (as shown in the drawing set "Community Recreation Center Machine
Storage Building Site Plan" dated 1/28/2025) on land located at TPN 37.1-6-9, as well as all applications, forms
and materials.
Dated: 24 March 2025
Motion by: Al Fiorille
Seconded by: Christine Hass
VOTE AS FOLLOWS:
Tom Butler - Aye
Sandy Conlon - Absent
John Duthie — Aye
Al Fiorille - Aye
Christine Hass - Aye
Danielle Hautaniemi - Aye
John Licitra - Aye
Fredric Villano — Not Voting
Dean Shea - Aye
Received in the Lansing Town Clerk's Office on
Debbie Munson, Town Clerk
Town of Lansing
Tompkins County, New York
Page 2 of 2