Anticipated Life of Wind Turbines
Megawatt-scale wind turbine generators available on the market today have a life expectancy of more than 20 years.
The tubular steel towers supporting the generators have a simple, rugged design and with basic routine maintenance
will serve many years beyond the life expectancy of the generators.
As the turbines to be installed for the Black Oak Wind Farm (the Project) approach the end of their serviceable life,
technological advances should make available more efficient and cost-effective generators that will economically
drive the replacement of the existing generators and thus prolong the economic life of the Project. In the event that
this doesn’t happen and the turbines need to be decommissioned, the following plan provides a description of the
decommissioning work and the estimated costs associated to perform it.
Estimated Cost of Decommissioning
The estimated decommissioning costs per turbine were prepared using available information from a variety of
credible industry sources. The current cost of decommissioning turbines is estimated to be approximately $50,000
per turbine, although this cost will be offset by the salvage value of the towers and the turbine components. The
estimated $45,000 salvage value of the each wind turbine was based upon the worst case scenario assuming the
only salvage value of the wind turbine is from scrapping the steel. The estimate was based on the total weight of one
wind turbine, which is 230 tons consisting primarily of steel. However, because it did not separate the scrap value of
all the constituent materials, this was a very conservative estimate considering approximately 31 tons of the total
weight is copper (generator windings), which would yield a higher value than steel. Also, there would be
opportunities for re-sale for reuse of all or some wind turbines or their components (Falmouth, MA Mitigation Plan,
2011; Knauth, Ridgeline Wind 2011; New Grange Wind Farm DEIS, 2008).
In reality, in the unlikely event that the Project had to be decommissioned it is more likely that turbines and
associated equipment would be sold to another power provider rather than sold for scrap for the value of the raw
materials. Individual rotors, generating equipment and towers would likely have value and demand on the open
market.
Ensuring Decommissioning and Site Restoration Funds
According to the Town of Enfield Wind Energy Facilities Local Law, the Project will continuously maintain a fund,
bond, letter of credit, or equivalent financial security instrument payable to the Town of Enfield for the removal of non-
functioning wind turbines and appurtenant facilities, in a form and amount approved by the Town Board for the period
of the life of the facility. Prior to approval of the project by the Building Department of the Town of Enfield, the
Project will, in writing, provide a surety bond or financial security instrument in a proposed amount not less than
$125,000 per turbine, or a total of $875,000 (assuming 7 turbines), renewable on an annual basis, for the removal of
non-functioning turbines and associated facilities. Per the local law, this amount may be periodically reviewed by the
Town at its discretion, and the amount altered accordingly for the estimated costs of removal, decommissioning, and
restoration. The Project Sponsor will fully comply with the local law concerning decommissioning and site
restoration.
Decommissioning Process
Black Oak Wind Farm Decommissioning Plan 2
All decommissioning and restoration activities will adhere to the requirements of appropriate governing authorities,
and will be in accordance with all applicable federal, state, and local permits. The decommissioning and restoration
process comprises removal of above-ground structures; removal of below-ground structures to a depth of 36 inches;
restoration of topsoil, re-vegetation and seeding; and a two year monitoring and remediation period. Access roads,
fencing and residual minor improvements will not be removed unless the landowner requests that they be removed.
Above-ground structures include the turbines, transformers, overhead collection lines, wind farm-owned portions of
the substation, maintenance buildings, and access gates. Below-ground structures include turbine foundations,
collection system conduits, and drainage structures. The process of removing structures involves evaluating and
categorizing all components and materials into categories of recondition and reuse, salvage, recycling, and disposal.
In the interest of increased efficiency and minimal transportation impacts, components and material may be stored
on-site in a pre-approved location until the bulk of similar components or materials are ready for transport. The
components and material will be transported to the appropriate facilities for reconditioning, salvage, recycling, or
disposal. The presence of Teet’s Scrap Recycling within the project boundary makes the recycling of all metal
components an easy and cost effective process.
Wind turbine removal
Access roads to turbines may be widened temporarily to sufficient width to accommodate movement of
appropriately sized cranes or other machinery required for the disassembly and removal of the turbines.
High value components will be stripped. The remaining material will be reduced to shippable dimensions
and transported off site for proper disposal. Control cabinets, electronic components, and internal cables
will be removed. The blades, hub and nacelle will be lowered to grade for disassembly. The tower sections
will be lowered to the ground where they will be further disassembled into transportable sections. The
blades, hub, nacelle, and tower sections will either be transported whole for reconditioning and reuse or
dissembled into salvageable, recyclable, or disposable components. Useable parts will be sold into the
secondary market for parts or installation elsewhere. The area will be thoroughly cleaned and all debris
removed.
Wind turbine foundation removal
Topsoil will be removed from an area surrounding the foundation and stored for later replacement. Turbine
foundations will be excavated to a depth sufficient to remove all anchor bolts, rebar, conduits, cable, and
concrete to a depth of 36 inches below grade. After removal of all noted foundation materials, the hole will
be filled with clean sub-grade material of quality comparable to the immediate surrounding area. The sub-
grade material will be compacted to a density similar to surrounding sub-grade material. All unexcavated
areas compacted by equipment used in decommissioning shall be de-compacted in a manner to adequately
restore the topsoil and sub-grade material to the proper density consistent and compatible with the
surrounding area. The area will be thoroughly cleaned and all debris removed, and re-seeded to vegetation
acceptable to the landowner.
Underground electrical collection system
The cables and conduits contain no materials known to be harmful to the environment and will be cut back
to a depth of at least 36 inches. All cable and conduit buried greater than 36 inches will be left in place and
abandoned.
Substation
The Project substation is generally valuable to the local transmission owner. As per the interconnection
rules of the NYISO, the Project substation reverts to the ownership of the transmission owner and thus the
Project Sponsor does not intend to decommission the substation.
Black Oak Wind Farm Decommissioning Plan 3
Site Restoration Process
To the extent necessary, topsoil will be removed prior to removal of structures from all work areas and stockpiled,
clearly designated, and separate from other excavated material. Prior to topsoil replacement, all rocks six (6) inches
or greater will be removed from the surface of the subsoil. The topsoil will be de-compacted to match the density and
consistency of the immediate surrounding area. The topsoil will be replaced to original depth, and original surface
contours reestablished where possible. All rocks six (6) inches or larger will be removed from the surface of the
topsoil. Any topsoil deficiency and trench settling shall be mitigated with imported topsoil consistent with the quality of
the affected site.
In accordance with guidelines provided by New York State Department of Agriculture and Markets, topsoil de-
compaction and replacement will be avoided after October 1, unless approved by the landowner in consultation with
the New York State Department of Agriculture and Markets since areas restored after October 1 may not obtain
sufficient growth to prevent erosion over the winter months. If areas are restored after October 1, provision will be
made to restore any eroded areas in the springtime to establish proper growth. Following decommissioning
activities, the sub-grade material and topsoil from all affected agricultural areas will be de-compacted and restored to
a density and depth consistent with the surrounding fields or to a depth of 18 inches. The affected areas will be
inspected, thoroughly cleaned, and all debris removed.
All disturbed soil surfaces within agricultural fields will be seeded with a seed mix agreed upon with the landowner in
order to maintain consistency with the surrounding agricultural uses. All other disturbed areas will be restored to a
condition and forage density reasonably similar to original condition. In all areas restoration shall include, as
reasonably required, leveling, terracing, mulching, and other necessary steps to prevent soil erosion, to ensure
establishment of suitable grasses and forbs, and to control noxious weeds and pests.
In accordance with the guidelines of the New York State Department of Agriculture and Markets, a monitoring and
remediation period of two years immediately following the completion of any decommissioning and restoration
activities will be provided. The two-year period allows for the effects of climatic cycles such as frost action,
precipitation and growing seasons to occur from which various monitoring determinations can be made. Any
remaining agricultural impacts can be identified during this period and follow-up restoration efforts will be
implemented.
In addition, all Town, County, and State roads, impacted by Project decommissioning activity, if any, will be restored
to original condition upon completion of decommissioning.
References
Tetra Tech. 2008. New Grange Wind Farm DEIS, Exhibit 9: Decommissioning Plan. Available at:
http://www.horizonwindfarms.com/northeast-region/documents/underdev/arkwright/Exhibit9_DecomissioningPlan.pdf.
Weston and Sampson. 2011. Town of Falmouth MA Wind Energy Facility Mitigation Alternatives Analysis. Available
at: http://www.falmouthmass.us/selectmen/falmouth%20turbine%20mitigation%20study.pdf.
Knauth, Jonathan. 2011. Knauth’s Analysis of cost to decommission turbines, Public commentary on the Ridgeline
Energy LLC Monticello Hills Application, Decommissioning estimate. Available at:
http://www.protectrichfield.com/documents/Decommissioning%20Estimate%20for%20Ridgeline%20Energy%20Monti