HomeMy WebLinkAboutMinutes 05-05-2021 Town of Enfield Planning Board Meeting and Public Hearing DraftTown of Enfield Planning Board Meeting
Wednesday May 5, 2021 7 PM
Zoom.us/j/863 0628 6687
Call: landline or smartphone 646-876-9923
Password 14850
Draft Minutes
Attendance: Planning Board Members; Dan Walker, Ann Chaffee, Henry Hansteen, , Aaron
Abb, Joe Dawson, Mike Carpenter
Enfield Town Supervisor Stephanie Redmond, Enfield Town Councilperson Robert Lynch
Rick Snavely (Family Life Network), John Coulter (Family Life Network),
Patrick Head
Deputy Clerk Laura Norman,
Call to order: 07:10 PM
Motion to Approve Minutes: Minutes for March, and April 2021 will be approved at the next
Planning Board meeting.
2nd:
Vote:
All Aye:
All Nay:
Public Hearing for Site Plan Approval of Family Life Network Radio Tower
North of Enfield Center Road
Dan Shared a google image of the Family Life tower site.
Rick described the project
Family Life is looking to put up a tower, they have one in horseheads and are looking to move it
to the Ithaca area. This site gives them better coverage of this area, the land owner is excited to
have the tower on their property, tower is 199 feet tall (under 200 feet means it does not need to
be painted our lighted)
Self-Supporting tower, it is straight not tapered, you need straight for an FM signal
Dan Walker
Site is on Enfield Center Road, it is more than about 1500 feet from Enfield Center Road, 1800
Feet from Sheffield Road, Dan shared a diagram of the town showing how it will look.
Dan also shared an image of the tax parcel showing the site that will be leased from the property
owner
Comments from the public:
Roberta Drake
48 E Enfield Center Road
Roberta Drake: : Where you guys going in to put the road to the tower?
Rick Snavely: We are going to create a road off of Enfield center road. where there is a small
existing driveway.
Roberta Drake: Is family life going to maintain the driveway?
Rick Snavely: Yes, we will maintain
Roberta Drake: How long will it take to put up the Tower?
Rick Snavely: A month to 6 weeks
Roberta Drake: How safe are the towers, any health risks?
Rick Snavely: it’s very safe, FCC requires they post signs, will be 50x50 chain link area to
prevent anyone from entering, as far as interference, any radio station that interferes will be at
low end of dial in this is in the middle so shouldn’t be much if any interference, FCC requires
that if they are notified of any interference they are required to take care of it,
Dan Walker: How would you take care of that?
Rick Snavely: The only issue was a translator on top of an apartment building and a gentleman
had rabbit ears that had some interference and they put filters on his antenna to block that
particular signal.
Dan Walker: Roberta’s property is 210ft from property line.
Rick Snavely: The tower is designed to collapse if there are any structural issues, the towers are
made by Velmont and we have had very good success with the towers.
John Drake
354 Sheffield Road
Dan Walker: It’s over 1000 feet from property line, pretty much screened by trees
John Drake: Has a pacemaker will the tower cause issues
Rick Snavely: It will not
John Drake: Will there be more towers after they build this one
Rick Snavely: No, multiple towers are just AM stations
Marcus Gingerich
101 Rumsey Hill Road
Marcus Gingerich: How may watts is the Ithaca translator?
Rick Snavely: Ithaca translator is 50 watts,
Marcus: How many watts is tower? Does this tower replace Ithaca translator?
Rick Snavely: Yes the Ithaca repeater will be moved, this will go out 25-30 miles vs the 5 miles
of the translator
Marcus Gingerich: What is the power of the spencer station?
Rick Snavely: 17k watts, FM is line of sight, where other signals get week this tower will take
over with a strong signal. Ithaca Connecticut hill 50k watt tower, needs a translator in Ithaca as
well cause of gaps, there is a balance between heights and power, the higher you go the lower the
power output you can put out.
Dan Walker: What is the Frequency of station?
Rick Snavely: its 101.1, satellite dish with in the 50x50 compound (6ft ground mounted)
Dan Walker: anyone else from public
How is the signal going to come in?
Rick Snavely: we use satellite delivery there will be a dish within the 50x50 compound, the dish
is 6ft ground mounted.
FCC application went in on April 7th, Family Life expects to have the station on the air by
September 2021, if everything goes well.
Robert Lynch
175 Grey Road
Robert Lynch: I sent invination to Rick Snavely in April 2021 and did not receive a response.
Rick Snavely: I did not receive it
Robert Lynch: It was sent right after last planning board meeting, the town board meeting was on
14th
Rick Snavely: sorry I would have loved to be there and would like to go to the next town board
meeting.
Robert Lynch: The next town board meeting is a week from tonight. How do you plan on getting
electricity to the Tower site?
Rick Snavely: We plan on burying the line
Robert Lynch: Primary or secondary?
John Coulter: Primary burred back through to power company specifications, buried 3ft down in
sand within 200ft of transformer
Robert Lynch: Driveway needs to be a specific width so that emergency vehicles can get
through, has the fire dept. or code enforcement officer been contacted about it?
John Coulter: not as of yet
Dan Walker: That will be dealt with during site plan review.
Rick Snavely: Is the board meeting virtual or in person?
Robert Lynch: Virtual
Rick Snavely: I will be present
Dan Walker: Any other member of public wish to speak if not then closing the public hearing.
Maybe we should have a diagram that shows road on tax map? Will connect to existing path that
is viewable on the map
Do you need a 20 foot road?
Alan Teeter: I think it needs to be a 20 foot road which will probably be there any to get a crane
back there but I will look it up and check for sure.
John Coulter: Does the town of Enfield have zoning code or use NYS
Dan Walker: use NYS unified building code and fire dept.
John Coulter: was asking, because most locations only require 12 foot road with pull outs
Alan Teeter: perhaps 12 foot is ok but I have to look it up.
Dan Walker: any other discussion from the planning board, Basic site plan concept questions?
No one had any questions
Dan Walker: Environmental review needs to be done on site, type 1 for SEQR, needs to be long
form not short form.
Rick Snavely: Only one other time they had to do the long form, and that was because people on
the zoning board were upset it was not on their property.
Dan Walker: We do not have zoning, the SEQR says a structure over 100 ft unless the town has
zoning that deals with structure heights. We do have in site plan review law, if it is over 100 ft,
needs site plan approval, will ask for more official determination from town attorney if
references to towers in our site plan law would cover the zoning statement. will cover the SEQR
next month, Can’t approve until a SEQR is done. In agreement with site plan needing more detail
prior to final approval.
Rick Snavely: I am puzzled that there has not been a long form SEQR in past but one is required
here?
Dan Walker: SEQR has been updated in last couple of years, heights of structures is mentioned
in site plan law but we do not have zoning.
Rick Snavely: So it is because of site plan law that we need long form?
Dan Walker: Section 617.4 TYPE ONE ACTIONS, paragraph B the following actions are type
one, sub paragraph 7. any structure exceeding 100 feet above ground level in a locality without
any zoning regulation pertaining to height. That’s why I am saying that it is type 1 which
required long form.
Based on SEQR law (NYS) Enfield does not have its own SEQR law, does not see any
environmental impacts but have to do this because of state law, Dan will contact rick this week
and will have family life on the agenda for June meeting.
Rick Snavely: The application was filed on April 7 th with FCC, usually takes 3-4 months to
approve application, will probably start road work (look to be on the air around September if
everything goes well)
Discussion of Norbut Solar Enfield Applegate Road SEQRA Review
Environmental Review of Norbut Solar Farms Applegate Road Project Proposal
The Planning Board proceeded on an uncoordinated review of the proposed project as an
Unlisted action which was incorrect as the size of the project makes it a Type I action according
to the SEQRA regulations.
Type I actions require a coordinated review with the requirement that Planning Board acting as
lead agency must Declare the intent to be lead agency and issue a notice of intent to other
involved or potentially interested agencies prior to finalizing the environmental review.
The Involved agencies are ones that have an approval to be issued for the Norbut solar farm
project include:
• The Enfield Town Board, approval of a PILOT Agreement and financial surety for
decommissioning
• The Town of Enfield Planning Board, Site Plan approval and solar permit
• Tompkins County IDA, PILOT Agreement
• Tompkins County Planning, 239 Review
• Ithaca City School District, Pilot
• NYSERDA, Funding
• NYSDEC. SWPPP
• SHPO, Historical review
• US Army Corps of Engineers, Wetland Jurisdictional Determination
The Enfield Planning Board will send notice of intent to all listed agencies to complete the
formal notification process.
A 20-30 day time to state we should be the lead agency or contest that we are, we did a thorough
tech review
The technical review of the Project was completed in accordance of the Site Plan review law and
completion of the Environmental was completed and the project was modified as requested by
the Planning Board to be in compliance with the Solar Addendum.
After the notification and comment period is completed the planning Board will review
documentation and issue a determination.
Next step, planning board reviews documentation and reissue a resolution of determination. We
issued a site plan approval which is considered a preliminary approval pending completion of
SEQR.
Discussion:
Henry Hansteen: Do we need to hold another public hearing because of the changes to the site
layout?
Dan Walker: No, it's not required. No need for any more public hearing unless the planning
board wants to do it. The site layout was in compliance with town regulations
Henry Hansteen: What was it about size that makes it type one?
Dan Walker: Because the site is over 10 acres, 2 acres of roadway, not disturbing land under
panels
Discussion about correspondence from legal counsel, anything to do with money is under the
Town Board not the Planning Board, the Town Board will discuss Surety Bonds at next meeting.
The planning Board is welcome to give input on it.
Discussion on difference in bond types, Performance Bonds, Surety Bonds are not a sure thing,
the town needs guaranteed money.
Norbut should be informed sooner rather than later is Surety Bonds will not be allowed.
John should be invited to the next Town Board meeting when the Board discusses Surety bonds
for the Norbut Solar Farms. The land owner and project owner are same entity.
Next step, planning board did all work for reviewing SEQR, then send out notification, when we
hear back we can go ahead and proceed as if notifications were done properly, then final
subdivision and solar permit.
Mike Carpenter, In last month’s meeting. Norbut sent letter that they have not found examples of
what it would look like for us to have policy for complaints.
Dan we do have policy, it will be in the permit, standard property complaint issues with code
enforcement, can also contact Norbut directly as well. Official complaint resolution through code
office.
Mike, In the solar law there distinct way that we wanted complaints done, solar law askes for
written complaint resolution process, would like Norbut to write out the steps in a document, in
keeping with letter and spirit of the law. Helpful if someone has a complaint that you have a
document to give them with the process. This should be a standard in all applications so that a
future project doesn't state. "Well Norbut didn't submit one".
Dan will call john and see if we can get a letter stating what was discussed for the complaint
process.
Any planning board have comments on what next: none moving on
Sketch Plan Review Head Subdivision Enfield Center Road
Patrick Head: Multifamily project Enfield center and Van Dorn, now have different concept,
decided against the 4 unit building because of amount of taxes, putting up for separate houses
instead. have a house going in right now, 3 lots on Enfield center rd. 188x244, one slender on
Van Dorn 155 wide x 244, 5 acres, about 1 acre each, will that work for septic and wells, yes the
health dept. looked at it.
Subdivision plan and bring it in , TG Miller is going to put it together and will bring it in
Any comments,
Henry Hansteen: Taxes on 4 unit building vs houses
Patrick Head; selling houses, instead of renting units less in taxes
What process needed for approval?
Sketch plan tonight, not type one action, cause it’s not enough lots, less than 10 acres, will check
to see if property is AG district, not listed as AG exceptions
Dan Walker will look at AG district map and check on it.
Not keeping with subdivision law, what kind of review
Skeet, Preliminary, final get surveyed, and plat map drawn up, anything needed for DEC, Dan
Walker doesn’t think so, since they are individual lots.
Right now one property, in order to give approval for subdivision its anticipating so much
ground disturbance over the course of the project. Only if Patrick does all 4 at one time. SWPP
looks at whole use of property over course of time, still have to get SWPP done
If it was a traditional subdivision were building roads then yes, subdivision plat, single family
homes should not require, but will check into it. Single family homes are exempt from SWPP
requirements but subdivisions may require Dan Walker will check into it.
Dan Walker: will you have final plat ready by next month,
Patrick Head: better be, l'm gonna push them,
Dan Walker: short form SEQR
Mike Carpenter: My advice is to get a copy of subdivision law and read it through, make sure
that nothing will trip you up, it will go through much quicker that way as well.
Any general comments from Planning Board Members
Discussion from Town of Enfield Legal Counsel about surety bond from an email to Town
Supervisor Stephanie Redmond from Town Legal Council that was forwarded to Planning Board
members.
Henry Hansteen, mike’s question on surety for decommission, was reading forwarded email,
once town board delegated to planning form then the waiver was solar law, Guy email bond in
lew of cash deposit. Quote from guy email, decision was not made by planning board, guy said
decision was made, not sure if he is referring to law not sure, he is saying that
Mike Carpenter, things it was the delegation of authority to the planning board, not sure what
guy is talking about.
The Planning Board did not make a determination any recommendations on surety bonds for
Norbut Solar Farms. The planning Board did not issue a waiver to Norbut Solar Farms for the
Bond. Approval last month was site plan and amount of funds needed for surety needed, not the
form of funds. Planning board did not give waiver.
Would be good to hear from Norbut to see what they think they have approval for, if a bond is
approved then a waiver would be required.
Supervisor Stephanie Redmond, we will invite the Planning Board to the board meeting and will
unmute them.
Adjournment: Anne Chaffee made motion, Henry Hansteen seconded,
Adjourned at 8:44pm