HomeMy WebLinkAboutNSF Enfield - Solar Decommissioning Plan Without Scrap Value - 3.23.20211
Solar System Decommissioning
Plan Without Scrap Value
Decommissioning costs are equal for all three sites listed below:
NSF Enfield Site 1, LLC
NSF Enfield Site 2, LLC
NSF Enfield Site 3, LLC
Synopsis
A. Solar System Lifespan
B. Cost of Decommissioning
C. Ensuring Funds For Decommissioning and Site Restoration
D. Solar System Decommissioning Description
D.1. Removal of Electrical Components, Racks & Rack Wiring
D.2. PV Module Dismantling & Panel Removal
D.3. Breakup and Remove Concrete Pads or Ballast
D.4. Remove Cables
D.5. Remove Fence
D.6. Grading and Road Removal
D.7. Seed Disturbed Area
A. Solar System Lifespan
Owner of Sites located at 00 Applegate Road South, Ithaca, NY 14850 (“Project”), to be subdivided, is
responsible for decommissioning the Project. Commercial-scale solar fields are designed for a minimum
expected operational life of 25 years but may operate for 40 years or more.
As the solar field approaches the end of its operational life, it is expected that technological advances
will make more efficient and cost-effective solar arrays that will economically drive the replacement of
the existing solar arrays.
The decommissioning plan provides financial assurance that there will be sufficient funds available for
decommissioning and site restoration when the solar arrays have reached the end of their useful life.
B. Cost of Decommissioning
The cost of decommissioning a solar array more than 20 years into the future cannot be known with
exact certainty.
2
NSF Enfield Decommissioning Costs Per 5 MW System
# Task Estimated Cost
D1 Remove Electrical Components, Racks & Rack Wiring $ 35,000
D2 PV Module Dismantling Removing Panels $ 45,000
D3 Breakup and Remove Concrete Pad $ 25,000
D4 Remove Cable $ 30,000
D5 Remove Fence $ 37,500
D6 Grading/Roadway $ 10,000
D7 Seed Disturbed Area $ 5,000
Cost: Labor and Equipment to Decommission $ 187,500
Total After 20 Years (2% Inflation Rate) $ 278,615
Three 5 MW systems, each with a Current Net Cost of $187,500 per system, totaling $562,500.
C. Ensuring Funds for Decommissioning and Site Restoration
The estimated cost of decommissioning as provided above will be updated upon commencement of
commercial operations.
On or prior to December 31 of each calendar year beginning with the calendar year in which the Project
commences commercial operations through and including calendar year 10, an amount based on the
estimate provided herein, if any, to be updated upon commencement of commercial operations, shall be
reserved for decommissioning and site restoration.
Such annual amounts may be in the form of a performance bond, surety bond, letter of credit, parental
guaranty, or other form of financial assurance acceptable to the Siting Council (the “Financial
Assurance”).
On or prior to the end of calendar year 15 of the Project’s operation, the estimated costs of
decommissioning will be reassessed and an amount equal to the balance of such updated estimated cost
of decommissioning less the amounts reserved, if any, will be reserved for decommissioning and site
restoration.
The Financial Assurance shall be kept in place until such time as the decommissioning work has been
completed, provided, however, to the extent available as liquid funds, the Financial Assurance may be
used to offset the costs of the decommissioning.
D. Solar System Decommissioning Description
Decommissioning and restoration activities will adhere to the requirements of appropriate governing
authorities, and will be in accordance with applicable federal, state, and local permits.
The decommissioning and restoration process comprise removal of above-ground structures; grading, to
the extent necessary; restoration of topsoil (if needed) and seeding.
The process of removing structures involves evaluating and categorizing all components and materials
into categories of recondition and reuse, salvage, recycling, and disposal.
3
The above-ground structures and below-ground structures are collectively referred to herein as the
“Project Components.”
Temporary erosion and sedimentation control best management practices will be used during the
decommissioning phase of the Project.
Control features will be regularly inspected during the decommissioning phase and removed at the end
at the process.
D.1. Removal of Electrical Components, Racks & Rack Wiring
Control cabinets, electronic components, and internal cables will be removed. The panels, racks and
inverters will be lowered to the ground where they may be transported whole for reconditioning and
reuse or disassembled/cut into more easily transportable sections for salvageable, recyclable, or
disposable components.
D.2. PV Module Dismantling & Panel Removal
Solar photovoltaic modules used in the Project are manufactured within regulatory requirements for
toxicity based on Toxicity Characteristic Leaching Procedure (TCLP). The solar panels are not
considered hazardous waste.
The panels used in the Project will contain silicon, glass, and aluminum which have value for recycling.
Modules will be dismantled and packaged per manufacturer or approved recyclers specifications and
shipped to an approved off-site approved recycler.
D.3. Breakup and Remove Concrete Pads or Ballast
Pads will be excavated to a depth sufficient to remove all anchor bolts, rebar, conduits, cable, and
concrete to a depth of 24 inches below grade. The remaining excavation will be filled with clear sub-
grade material of quality comparable to the immediate surrounding area. The sub-grade material will be
compacted to a density similar to surrounding subgrade material.
All unexcavated areas compacted by equipment used in decommissioning shall be de-compacted in a
manner to adequately restore the topsoil and sub-grade material to the proper density consistent and
compatible with the surrounding area.
Concrete slabs used as equipment pads will be broken and removed to a depth of two feet below grade.
Clean concrete will be crushed and disposed of off-site and/or recycled and reused either on or off-site.
D.4. Electrical Cable Removal
Electric wire made from copper or aluminum has value for recycling. DC wiring can be removed
manually from the panels to the inverter. Underground wire in the area of the array will be pulled and
removed from the ground. Overhead cabling for the interconnection will be removed from poles. All
wire will be sent to an approved recycling facility.
D.5. Fencing and Racking Removal
All racking and fencing material will be broken down into manageable units and removed from facility
and sent to an approved recycler. All racking posts driven into the ground will be pulled and removed.
4
D.6. Grading and Road Removal
During decommissioning, the processed stone access roads will be maintained for access and future use.
D.7. Seed Disturbed Areas
Following decommissioning activities, the sub-grade material and topsoil from affected areas may need
to be de-compacted and restored to a density and depth consistent with the surrounding areas. If the
subsequent use for the Project site will involve agriculture, a deep till of the Project site may be
undertaken.
The affected areas will be inspected, thoroughly cleaned, and all construction-related debris removed.
Disturbed areas will be reseeded to promote re-vegetation of the area unless the area is to be
immediately redeveloped.
In all areas, restoration shall include, as reasonably required, leveling, terracing, mulching, and other
necessary steps to prevent soil erosion, to ensure establishment of suitable grasses and forbs, and to
control noxious weeds and pests.
Decommissioning and Restoration Terms
The Project shall be decommissioned within 360 days of the end of the Project’s operational life.
Areas disturbed during the decommissioning phase will be with seeded with a drought-tolerant grass
seed mix appropriate for the area unless such areas are being immediately redeveloped for other uses.
The gravel access road will remain intact.