HomeMy WebLinkAboutAngelica Sites 1-4 Decommissioning Cost Breakdown- STAMPED 6-3-2020
Decommissioning costs are equal for all four sites listed below:
▪ NSF Angelica Site 1, LLC
▪ NSF Angelica Site 2, LLC
▪ NSF Angelica Site 3, LLC
▪ NSF Angelica Site 4, LLC
Synopsis
A. Cost of Decommissioning
B. Solar System Decommissioning Description
B.1. Removal of Electrical Components, Racks & Rack Wiring
B.2. PV Module Dismantling & Panel Removal
B.3. Breakup and Remove Concrete Pads or Ballast
B.4. Remove Cables
B.5. Remove Fence
B.6. Grading and Road Removal
B.7. Seed Disturbed Area
A. Cost of Decommissioning
Angelica Decommissioning Costs Per 5 MW System
# Task Estimated Cost
B1 Remove Electrical Components, Racks & Rack Wiring $ 35,000
B2 PV Module Dismantling Removing Panels $ 45,000
B3 Breakup and Remove Concrete Pad or Ballast $ 25,000
B4 Remove Cable $ 30,000
B5 Remove Fence $ 37,500
B6 Grading/Roadway Removal $ 10,000
B7 Seed Disturbed Area $ 5,000
Cost: Labor and Equipment to Decommission $ 187,500
Four 5 MW systems, each with a decommission cost of $187,500 per system, totaling
$750,000.
B. Solar System Decommissioning Description
Decommissioning and restoration activities will adhere to the requirements of appropriate
governing authorities, and will be in accordance with applicable federal, state, and local permits.
The decommissioning and restoration process is comprised of removal of above-ground
structures; grading, to the extent necessary; restoration of topsoil (if needed) and seeding.
The above-ground structures and below-ground structures are collectively referred to herein as
the “Project Components.”
Temporary erosion and sedimentation control best management practices will be used during the
decommissioning phase of the Project.
Control features will be regularly inspected during the decommissioning phase and removed at
the end at the process.
B.1. Removal of Electrical Components, Racks & Rack Wiring
Control cabinets, electronic components, and internal cables will be removed. The panels, racks
and inverters will be lowered to the ground where they may be transported whole for
reconditioning and reuse or disassembled/cut into more easily transportable sections for
salvageable, recyclable, or disposable components.
B.2. PV Module Dismantling & Panel Removal
Solar photovoltaic modules used in the Project are manufactured within regulatory requirements
for toxicity based on Toxicity Characteristic Leaching Procedure (TCLP). The solar panels are
not considered hazardous waste.
The panels used in the Project will contain silicon, glass, and aluminum which have value for
recycling. Modules will be dismantled and packaged per manufacturer or approved recyclers
specifications and shipped to an approved off-site approved recycler.
B.3. Breakup and Remove Concrete Pads or Ballast
Pads will be excavated to a depth sufficient to remove all anchor bolts, rebar, conduits, cable,
and concrete to a depth of 24 inches below grade. The remaining excavation will be filled with
clear sub-grade material of quality comparable to the immediate surrounding area. The sub-grade
material will be compacted to a density similar to surrounding subgrade material.
All unexcavated areas compacted by equipment used in decommissioning shall be de-compacted
in a manner to adequately restore the topsoil and sub-grade material to the proper density
consistent and compatible with the surrounding area.
Concrete slabs used as equipment pads will be broken and removed to a depth of two feet below
grade. Clean concrete will be crushed and disposed of off-site and/or recycled and reused either
on or off-site.
B.4. Electrical Cable Removal
Electric wire made from copper or aluminum has value for recycling. DC wiring can be removed
manually from the panels to the inverter. Underground wire in the array of the array will pulled
and removed from the ground. Overhead cabling for the interconnection will be removed from
poles. All wire will be sent to an approved recycling facility.
B.5. Fencing and Racking Removal
All racking and fencing material will be broken down into manageable units and removed from
facility and sent to an approved recycler. All racking posts driven into the ground will be pulled
and removed.
B.6. Grading and Road Removal
During decommissioning, the processed stone access roads will be stripped exposing the
geotextile beneath. The geotextile will then be removed and disposed revealing the original soil
surface.
The compacted soil beneath the road fill may require ripping with a subsoiler plow to loosen it
before it can be returned to crop production.
B.7. Seed Disturbed Areas
Following decommissioning activities, the sub-grade material and topsoil from affected areas
will be de-compacted and restored to a density and depth consistent with the surrounding areas.
If the subsequent use for the Project site will involve agriculture, a deep till of the Project site
will be undertaken.
The affected areas will be inspected, thoroughly cleaned, and all construction-related debris
removed. Disturbed areas will be reseeded to promote re-vegetation of the area, unless the area is
to be immediately redeveloped.
In all areas, restoration shall include, as reasonably required, leveling, terracing, mulching, and
other necessary steps to prevent soil erosion, to ensure establishment of suitable grasses and
forbs, and to control noxious weeds and pests.
Stephen Kane
Co-Owner // Director of Technical Services
NABCEP Certified PV Installation Professional
303.447.0300 x308
stephen.kane@namastesolar.com
namastesolar.com
Andrew Humphrey, PE
(AK, AZ, DC, CA, CO, FL, HI, IN, KS, MA, MD, ME, MN, MT,
NC, NE, NV, NY, OK, OH, OR, PA, RI, SD, TX, VA, VT, WY)
Andrew Humphrey Engineering, LLC
303-590-5976
ahumphrey@andrewhumphreyengineering.com
AndrewHumphreyEngineering.com