Loading...
HomeMy WebLinkAboutBlack Oak Response to the Jude Lemke's Letter of April 12, 2016 Black Oak Response to Jude Lemke's Letter of April 12,2016 April 26,2016 Excerpts from Lemke's letter are in black and our responses are in red.Lemke's further responses are in green. It is apparent that BOWF's owners are anxious to begin construction immediately because Congress is phasing out financial incentives(tax credits)for wind generators over the next five years, beginning in December 2016.The owner of the Project must begin construction this yearto receive the full credits. Not correct.This project plans to Use the Investment Tax Credits, not Production Tax Credits,which do not expire for S years.This is outlined carefully in our investment prospectus. Whether we are talking about the Production Tax Credits or the Investment Tax Credits,the answer is still the same. BOWF needs to start construction by the end of the year to secure 100%of those benefits. Section 48(a)(5)(C)of the Internal Revenue Code permits BOWF to elect a 30%Investment Tax Credit in lieu of claiming the Production Tax Credits. On December 18,2015,President Obama signed into law the"Protecting Americans from Tax Hikes Act of 2015" (PATH). PATH amends Section 48(a)(5)(C)to phase out the Investment Tax Credit beginning in 2017. Any construction beginning after December 31, 2016 will result in the Investment Tax Credit being reduced by 20%for projects beginning construction in 2017,40%in 2018 and 60%in 2019. For projects beginning construction after 2019, -. the credit is repealed: The definition of"construction"for purposes of both the ITC and the PTC<are the"same. BOWF justifies the construction they undertook without a SEQR or Enfield Town Wind Energy Permit in December 2014 as necessary to claim the Investment Tax Credit. But the IRS rules at that time required that they: 1) Begin"physical work of a significant nature" before Jan. 1,2015,which can include the purchase of infrastructure but which must be substantial and CONTINUOUS physical work activities,or 2)Spend at least 5%(i.e.,about$2 million)on construction and/or infrastructure purchases. (That 5%cannot include"planning or designing,securing financing,exploring,researching, obtaining permits,licensing,conducting surveys,environmental and engineering studies, clearing a site,test drilling to determine soil condition,or excavation to change the contour of the land(as-distinguished from excavation for foundations and footings).) There is no way BOWF meets the continuous test for physical work and they clearly haven't spent$2 million on qualifying construction/infrastructure. The PATH legislation mentioned above,extends the deadline for BOWF to either commence physical work of a'significant nature or spend at least 5%of the project costs on construction and/or infrastructure purchases to December 31,2016. If they don't do either,the Investment Tax Credits will be reduced as outlined above depending upon when they do meet such test. {33667/30473/TJF/01201177.DOCX) 1 What is worse,the Town's handling of this Project has been cloaked in secrecy,which calls into question the ability of our Town Government and its paid contractors to protect their citizens.Many aspects of this Project are still unclear.It is not yet known exactly where all the turbine towers and other infrastructure will be located,and it certainly is not clear that this proposal is the final expansion of the Project's footprint.Many hard questions need to be asked by the Town Board as lead agency under SEQR. I raise some of them in this letter. The only reason we proposed to change the layout was to accommodate the wishes of a landowner,who has been under a lease for six years,who no longer wants to participate in the project.The layout we got approved a year ago was perfectly acceptable from our point of view, but we were trying to be good neighbors and not force landowners to do things they've had a change of heart about. BOWF is being disingenuous. The good neighbors in this case are really the landowners themselves! BOWF had to move the substation because they have no right to force that landowner to sell land to them for the substation and it is unclear,at best,whether they still have a legal right to require him to allow a turbine on his property. Distressed neighbors of this landowner,who hadn't spoken to him in over 7 years since he first signed his lease,are thrilled by his recent actions to distance himself from this project and these old friends are now on speaking terms once,again.-Furthermore,it appears that BOWF is unable to meet the town's legal setback requirements on another landowner's property without that landowner's permission given the larger blades of the GE 2.3MW turbines. As of today, that landowner has refused to grant that permission because he is realizes the hardship it imposes on his next door neighbor who had planned to build on the land next to where'-that turbine would go. I believe that the Town of Enfield has failed to make Black Oak comply with the substantive and procedural requirements of SEQR.Additionally,I believe it is clear that a majority of the Town Board has placed the economic interests of Black Oak ahead of the safety of its citizens. Further review of this Project is needed before any_approval of the modification is granted'. Charging"that a majority of the Town Board has placed the economic interests of Black Oak ahead of the safety of its citizens"seems a bit premature since the Board has only voted to accept the Draft SEIS as complete and has said nothing about the substance of the document. There are plenty of substantive and procedural steps that have already occurred with little or no real review by the Board. The Project and the SEQR Review Is Shrouded in Secrecy in Violation of Law The Town's files and its communications with BOWF concerning this Project should be oPen and readily available for examination.New York's Freedom of Information Law("FOIL") requires broad access to the inner workings of government to ensure transparency and to hold leaders accountable for their actions.The legislative declaration when FOIL was enacted says it all: The legislature hereby finds that a free society is maintained when government is responsive and responsible to the public,and when the public is aware of governmental actions.The more open a government is with its citizenry,the greater the understanding and participation of the public in government.NYS Public Officer's Law,§84. FOIL's expansive scope has been confirmed'repeatedly by judicial decisions and the opinions of New York's Committee on Open Government.They instruct that FOIL is intended to ensure maximum access I33667/30473/T1F/01201177.D000I 2 to government records and any exception which acts to limit access must be very narrowly construed. The burden is on government agencies that seek to limit disclosure of public records to justify denial of access to public records.SEQR also requires public disclosure of information arising during the environmental review of an action.According to the SEQR regulations enacted by NYSDEC: [a]ll SEQR documents and notices,including but not limited to[Environmental Assessment Forms],negative declarations,positive declarations,scopes,notices of completion of an [Environmental Impact Statement(EIS)], EISs,notices of hearing and findings must be maintained in files that are readily accessible to the public and made-available on request. Ms. Lemke has been keeping the Town Clerk of Enfield busy with her many FOIL requests,which to our knowledge are being handled properly.Black Oak has always made the various EIS documents and 2 findings statement available on its website.To our knowledge,we are not required(nor has anyone ever asked)that we post on our website every past public notice,record of vote,and email conversation regarding the project. In our opinion,charging that the SEQR Review is"in violation of the law"on this matter is not justified. I think the explanation outlined above speaks for itself. I should riot have to constantly file FOIL requests to obtain these documents. I am sure the Town Clerk would welcome any relief from these FOIL requests BOWF can provide her complying with the FOIL and Open Meeting laws going forward. Later,a BOWF representative admitted at a Wind Advisory Committee meeting that the Town's consultant had already received a draft of the SEIS(although a copy was not available to the public). requested a copy of that document from the Town Clerk under FOIL. In response,I was told that BOWF claimed that it was a "draft"so it was not available to the public until the Town Board determined that it was"complete." Our understanding at the time,supported by our attorneys{though not Ms.Lemke's),was that until a document was approved by the Town Board, it wasn't available for publicreview.We were simply following the legal advice of the attorneys. Ms.Lemke did FOIL that-unapproved draft document and it ' was provided to her. It was provided to me because it was a public document! BOWF's rationale for denying my request has been expressly rejected by Department of State's Committee on Open Government on several different occasions. Attached is an advisory opinion from the Committee that is right on point.. Completeness for purposes of SEQRA is separate and distinct from access for purposes of the New York State Freedom of Information Law. My concern for this violation of FOIL is heightened,because of the apparent relationship between Mr. Krogh and the original principal of the Project,John Rancich.According to a May 4,2007 on-line article in National Wind Watch which was attributed to a reporter from ithacajournal.com,Guy Krogh was originally introduced to the Town Board by John Rancich,to"help answer questions"posed by residents.. Guy Krogh is the municipal attorney for many towns in the area,including Enfield. He does not generally represent Enfield on wind-related subject matters,which are the purview of Frank Pavia of Harris Beach.:.. But he does represent the town with respect to the interpretation of FOIL and Open Government. 133667/30473/rJF/01201177.DOCX} 3 My consultant needed the Town's data so he could run it through his own software and verify the results. I asked the Town to provide me with such data in a usable electronic format and 1 was informed that the Town's SEQRA attorney,Frank Pavia,had denied that request and was only willing to provide the data in paper form(a stack of over 100 pages that was useless to my consultant).Again,I was forced to have my own lawyer(at my expense)point out to Mr. Pavia that the express language of FOIL applies to the request: "Per Public Officers Law§87(5)(a) 'An agency shall provide records on the medium requested by a person,if the agency can reasonably make such copy or have such copy made by engaging an outside professional service.Records provided in a computer format shall not be encrypted'The Town is required to provide the document in the format that it possesses. The Town only has a pdf,which is what it provided to Ms.Lemke.We only have a pdf as well,and do not have it available In any other format either. BOWF is being cagey again. We have asked for the underlying data that was input into a sound model that is commonly used throughout the profession in order to derive the output discussed.in the SETS. This type of data is commonly shared among sound experts and my sound expert,who has 20 years of experience,cannot ever recall having this data denied to him. The pdf referred to by BOWF in its answer above is simply a copy of the noise report included in the original DEIS and only contains the outputs,not the inputs we have requested. In fact,BOWF and its consultants undoubtedly have these records and they are undoubtedly in machine readable form as that is format in which they collected the data to begin with. We have their"answer"(i.e.the outputs)in the SETS as to what they believe the sound levels are. We are simply asking them to"show the math"(i.e.,the inputs)used to derive those answers. Imagine if my sound expert were to just present data without the underlying data to prove how he derived it. BOWF would certainly call foul. Who Controlled this SEQR Review?As previously stated,I recently learned that representatives of BOWF and the Town's paid consultants have been inconstant communication about the draft SEIS since as early as January 21,2016 when BOWF first forwarded the SEIS to LaBella. It is now clear that from that time forward,IBOWF pressured LaBella to expedite its review,and both sets of consultants acted to ensure that the public was not aware of this process. For example,by email dated January 21,2016,James Pippin("Pippin"), project managerfor BOWF's consultant Haley&Aldrich, forwarded the Draft SETS(without attachments). His email directed: "[p)iease begin your review.If you are available either tomorrow or,Monday,I would like to have a call to go over the schedule for your review.We anticipate that this should not-take more than 1 week to complete(emphasis added)." In other words,BOWF's consultant told LaBella how long the Town's review should take.On February,1, 2016, Kathy Spencer of Haley&Aldrich advised Pippen by email,with a copy to the Town's SEQR lawyer Frank Pavia("Pavia"),that LaBella had already submitted preliminary comments to Haley&Aldrich about the SEIS,and that such comments should not be leaked to the public:"Jim,as we discussed, here is preliminary comments from LaBella on the SEIS dated January 2016 forthe Black Oak Wind Project'' Our understanding throughout the process was that there is a stage at which the document is fit for public review,and a draft stage at which it isn't a public document.We were indeed trying to expedite the process of getting the document drafted, not because of an expiring tax deadline, but because local I33667/30473/TJF/01201177.DOCXI 4 people had been clamoring to see the proposed changes,and the only way we knew of to get it to them was to have the Draft SEIS approved as"complete,"which made the document available to the public. See my answer above regarding the public nature of the draft SEIS. I think the emails above speak for themselves. If BOWF had really wanted to share the status of those proposed changes with the public, they had plenty of opportunities during the Wind Farm Advisory Committee meetings to do so. We certainly asked them about the status of the project often enough. The email asked Labella to "[p]lease review and let me know ASAP if there is anything substantive that needs revision or clarification in the SETS prior to Wednesday evening's meeting" (during which the SEIS was accepted by the Town Board) (emphasis added).On March 8,2016,LaBella emailed Pippen advising him that LaBella would recommend acceptance of the draft SETS as"complete" despite continuing reservations about the document: "Jim,I have reviewed the Draft SETS dated 3-7-16,and am in agreement that the most critical changes to the Draft SEIS have been made in the latest set of revisions.I have indicated in a memo to Frank Pavia that the document can be accepted as adequate for public review.Although I am prepared to conclude that the document is complete for the purpose of commencing public review,some of the issues identified during the review process remain a concern, and I would expect that the project sponsor will address such issues as part of the Final SEIS before that later document is accepted(emphasis added')." Geotechnical soil borings are not a requirement of SEQRA,since it has no relevance to environmental impact. It's an engineering requirement typically performed just prior to construction.The borings happened to have been done during the previous round of EIS,so LaBella was once again requiring it even though it is not part of SEQRA per se.Our compromise was to do the borings during the Draft EIS phase,and provide them for the Final EIS.Another area of confusion involved whether the permanent met tower required guy wires. It was the project's opinion that these issues were relatively minor,and could be resolved during the Draft phase,while public comment was taking place,and didn't need to delay further the public's ability to review the SEIS. The SEAR DEIS Final Scoping Document adopted by Enfield as the Lead Agency states:"The DEIS will include all elements required by 6NYCRR 617.9,including:... "This section will evaluate and describe surface and subsurface soils and bedrock conditions within the Project area....Constraints imposed by existing soils,geology and topographic conditions will be evaluated. Limiting characteristics relating to soil texture,soil-bearing;capacity,depth to water table, hydric and non-hydric soils should be identified and evaluated....The need for grounding or excavation in areas of shallow bedrock and anticipated methods to remove or penetrate bedrock will be described....etc." It is hard to see how these items can be addressed without soil borings. The Town Board should direct BOWF to revise the Draft SEIS now to address the deficiencies described in the memo from LaBella to Pavia,and the additional concerns described in this letter. See the statement above. f 33667/30473/TJF/01201177.D000 5 Enactment of the Wind Law and the Need to Change the Law Again Inadequate Setbacks There can be little dispute that setbacks provide a basic and proven form of mitigation of many of the adverse impacts caused by wind turbines including noise,ice throw,and mechanical failure.The Town of Enfield initially adopted its Wind Law in December,2007 which atthat time required setbacks of 1,250 feet or,1.5 times the height of the turbine whichever is greater,from property lines,communication,and electrical lines, transmission facilities such as substations,inhabitable structures, public roads,the Robert Tremain.State Park and neighboring municipal boundaries.Although that law took many months to adopt,the Ithaca Journal reported that BOWF contended that the law was hastily enacted and it threatened to take legal action tor►ullify:the law.Lessthan a month later,a new majority of the Town Board began'theirterms and voted to repeal the Wind Law.In November 2008,they enacted a new,vastly diluted version of the Wind Law,a version which was obviously much more suitable to Black Oak.Itreduced the setbacks considerably to structures and property lines of non participating'landowners The 2007 law was repealed because it was wriften hastily,after the entire Town Board had been voted. out of office.The outgoing members wanted to make the wind law-their last act of business,so they rushed to complete it after the election,passing it in a closed session without public review or SEQRA review.The setbacks in it were expressly made very large to prevent a wind project from being sited in Enfield,since no parcel in the Town is 2500'.across,which would have been required by that particular Town law.The State Attorney General then approached the Town of Enfield,said the law was passed illegally,and needed to be done correctly.The new Town Board took it upon itself to write a more carefully considered law,and tasked the Planning Board with the job.They took 9 months to craft the existing law,with the express aim of protecting town residents while allowing a project to be built.The 4 project had no hand in writing that law;it was solely the product of the Planning Board.which considered laws from around the U.S.and the world. I find it interesting that BOWF always says that the State's Attorney General approached the town to say the law was illegal whereas the January 9,2008 Enfield Town Board minutes indicate otherwise: "John Rancich welcomed the new board members. He stated that the previous board had passed a law,which may be illegal,pertinent to wind farms in Enfield. Supervisor Podufaski [newly elected]is seeking legal counsel from the Attorney from the Town.[the newly appointed Guy Krogh]and will proceed as counsel instructs." The February 13,2008 resolution repealing..the law,then states.in its whereas clauses: "WHEREAS,TowmCounsel,Guy.K Krogh,Esq.,has examined these.problems and recommended that the Town of Enfield:{i)file objections to the recognition of these local laws with the New York State Attorney General's'Office,and (2)consider the adoption of Local Law #1 of 2008 to repeal the Wind Tower Local Law and Ethics Local Law:" 1 also find it interesting to review he historic Planning Board minutes regarding the wind energy law deliberations. The minutes related to the repealed law are much more detailed and show a great deal of thought and consideration whereas there is little or no discussion in the minutes of the Planning Board about the new wind law between the time the law was repealed and the time a new law was passed. 133667/30473/TJF/01201177.DOCX] 6 In fact,as recently as February 2016 in the Madison County Town of Fenner,it was reported that a 113 foot long turbine blade detached from its hub and fell over 200 feet to the ground_I spoke with a man who lives across the street fromthat turbine. He told me he personally measured how far the blade was thrown as a result of that incident.He said it landed 323 feet from the turbine and then bounced another 148 feetfor a total distance of 471 feet.This is a recent example of why Enfield's setbacks are not adequate to protect its citizens. Since Black Oak proposes turbines no closer than 1000'to a home,and town law is 532',it looks to me ; that setbacks are in fact doing their jobs even in rare accidents like the one reported in Fenner. Fenner seems to have many"rare"accidents. In the last few years,they have had a turbine fall over, one catch fire and another throw a blade almost 500 feet. Measuring setbacks to residences completely ignores the fact that this is a residential area where people utilize most of their property for various activities such as hunting,hiking,picnic areas,corrals for animals,potential sites for homes for children or retirement houses. We live in the country so we can enjoy the outdoors,not hunker down in our homes to avoid being injured by wind turbines. GE's policy recommends the following setbacks[i]f icing is likely at the wind turbine site: ...1.5 times (Hub Height+rotor diameter)",to residences and public use areas. Black Oak complies with this standard. GE also recommends a setback of 1.1 times the total height of the turbine to remote property boundaries not owned or controlled by the project sponsor. This is not factual.See the attached GE setback document.It clearly states 1.1x Blade Length to a property line,which is identical to Enfield law,and is the standard with which Black Oak complies. This interpretation of the GE setbacks conveniently ignores footnote 4 which clearly assumes,in designating this setback,that the turbines are located in remote areas where the land will not be used by the landowners. I use all 46 acres of my property for recreational purposes. Many of my neighbors do likewise and a number of them have specific plans to further develop areas of their property that will be impacted by the turbine setbacks. Monumentally Inadequate Noise Limits In addition to setbacks,enforceable noise limits are necessary to address unforeseen noise impacts that arise during the operation of any wind farm.The Town's Local Law establishes a noise limit of"60 decibels above ambient sound levels measured at the nearest Off Site Residence." The language here is widely recognized as a typo in the Town's law,which should have read "60 decibels measured at the nearest Off-Site Residence."At any rate,our noise consultant concluded that noise from our turbines would never exceed 46 dBA.The annual average nighttime sound level at non-participating residences will not exceed 37 dBA. As Ronald Reagan liked to say,"There they go again!"BOWF is once again only measuring impacts at the residence. This completely ignores the impacts of noise on the whole of a resident's property. Furthermore,my sound expert has determined that the nighttime ambient sound levels for our area are much lower than 37 dBA and this represents a very large increase in the noise levels we will experience at night. Finally,there is no enforcement mechanism provided when the Black C)ak {33667/30473/TJF/01201177.D0CXI 7 projects fails to abide by these measurements(as so many wind farms do). At an absolute minimum, the wind law noise limits should be amended on retroactive basis to conform to the noise limits that Black Oak is proposing so the town residents have recourse to a nuisance suit when and if these noise limits are exceeded. My attorney provided the Town with strong legal precedent demonstrating that a municipality has every right to enact legislation related to health and safety(police powers),and make such legislation apply retroactively,as long as the owner has not already acquired "vested rights." In New York,a landowner acquires"vested rights"when it has already undertaken"substantial construction and made substantial expenditures prior to the effective date of the amendment_" Even if BOWF has already begun ordering turbine infrastructure(there is absolutely no evidence indicating that it has);that would not be considered a"substantial expenditure"if it can recoup its cost by reselling the equipment in the market. Additionally,the concept of"substantial expenditures"is not even relevant unless the landowner has also already undertaken "substantial construction. We have expended$3.2 million,out of a total$40 million project cost. I consider this to be substantial expenditure,and it includes a transformer costing$560,000,which was custom built and delivered based on existing town approvals,and cannot be re-sold for anything like its purchase price.There is substantial case law in NYS where gravel mines,for example, have been found to have vested rights even before securing their permits,based on the substantial investment required to even obtain a permit in the first place.Gravel mines, like wind farms,are very site specific,and require a great deal of work to locate and go through extensive permitting work even before construction begins. That's funny. The gravel mine case in NY that I found states: "However,"[n]eitherthe issuance of a permit. . nor the landowner's substantial improvements and expenditures,standing alone,will establish the right.The landowner's actions relying on a valid permit must be so substantial that the municipal action results in serious loss rendering the improvements essentially valueless"(Town of Orangetown,88 NY2d at 47-48).Further,no vested rights will accrue to a landowner"jw]here substantial construction has been commenced,but expenditures thereon are unsubstantial... [or]where substantial'expenditures have been made but substantial construction has not commenced (Matter of Putnam Armonk v Town of Southeast,52 AD2d 10,14[19761;see Matter of Berman v Warshaysky,256 AD2d 334,335-336[1998]) As my attorney has said on numerous occasions,it is not enough to spend money. There must be substantial construction as well. (See the first point for an idea of what substantial construction looks like!) Violation of SEQR Procedures Involving the Turbine Located in Newfield Although BOWF has not yet committed to any actual location for placement of the two turbines that will be relocated(it has merely identified possible combinations of locations),one of the potential sites is located in the Town of Newfield.This has important ramifications under SEQR.First,there is no indication in the SETS that BOWF has applied for any approval to construct any turbine in the Town of Newfield.Further,there is no indication in the SEIS or in any resolution of the Town of Enfield as to which agency will conduct the SEQR review for the turbine in the Town of Newfield or whether review will be coordinated. Because the Newfield turbine is identified in the SEIS,it appears that BOWF intends to assess its impacts along with 133667/30473/TJF/01201177.DOCX} those caused bythe Enfield turbines,as part of Enfield's pending SEAR review.of the Project If true, BOWF and Enfield have violated several of,SEQR's procedural requirements.The SEQR regulations provide that In]o agency may undertake,fund or approve the action until it has complied with.the. provisions of SEAR"(6 NYCRR§617.3(a)).The BOWF project is cl'earlya Type.I action for purposes of SEQR(it is"deemed"aType 1 action under the Enfield Wind Law).Presumably,Newfield has discretionary approval authority over construction of the turbine,either under its own wind law,or under a typical site plan review law.That"discretionary approval"authority makes Newfield.an "i.nvolved agency"for purposes of SEQR(defined as"an agency[state or local]that has jurisdiction by lawto fund;: approve or directly undertake an action"(6 NYCRR§617.2(s)). The Town of Newfield has been involved throughout the past five years of SEQRA.Now that we have proposed a turbine in Newfield,it has approval jurisdiction over that turbine location,and is a participant in the SEQRA process alongside Enfield.The two Town Attorneys have been working togei:her to comply with SEQRA procedure throughout. If nothing else,the recently passed moratorium in Newfield on wind facilities makes it clear they have been duly notified and are actively participating in the process_ Lots of jargon here. The difference between an"interested"party and an"involved"party under the SEQR rules is important. Suffice it to say that The Town of Newfield has rights to control its own destiny with regard to the assessment of the environmental impacts of the portion of the Project in Newfield. Apart from the expansion in the capacity of the facility that was previously proposed,it is believed that the changes to the configuration and location of the electrical substation will result in significantly more "cut and fill"of land. No,we moved the substation location within the same landowner's field to reduce the amount of cut and fill,not increase it.The new site is flatter.Also it was moved because the landowner preferred the new location.Reducing impact and improving landowner happiness seemed like adequate reasons.to deem the move not worthy of larger review. I am just confused by this answer. The substation moved from one,landowner's property-to another landowner's property because BOWF had no right to purchase the first landowner's property and:he- didn't want to sell. The owner of the parcel's continued participation in the Project may also be unclear which might cause further design changes.There is still uncertainty concerning the very basic issue of the heightof the towers which is relevant to several different anticipated environmental impacts.For example,according to LaBella's February 1,2016 comments on the January 2016 draft SETS(a version that was never made` " public): "In the Acoustic Study Update(Appendix E)it is indicated that hub height of the proposed turbines is 94 meters is this correct?(Based on our records,the hub heightof the former turbine model in the FEIS/Findings statement was 96 meters or 315 feet.In June 2615,the use of the currently proposed model turbines was approved,which involved an increase in hub heightof 8 feet,resulting in a., total hub height of 323 ft.or 98 meters.) Is the AcousticStudy accurate given this anomaly in hub height (sic)."Similarly,in its February 8 comments,LaBella continued to question BOWF as to the height-of Its towers in a comment on the issue of shadow flicker: "There remains confusion with regard-to the heights of the turbine which has been indicated to be 94 m.... More explanation is needed of the heights in f 33667/30473/TJF/01201177.D000 9 the following statement in 2.8.2.1.3: 'These changes are due to shifting the Project layout,changes in turbine specifications'inci iding a net increase in overall structure height of 5 m(from 196 m to 201 m) and increase in rotor diameter(from 100 m to 1,07:m),which affects the intersection of the sun;turbine and receptor."' This reflects confusion.on the part of the town's consultants.The height changes had nothing to do with moving turbines in the iandscape;we were not proposing to do so at that point.The old turbines:were on 96 m hubs,with 100 m rotors,for a total structure height of 475'.'The newer turbines,approved last . summer,have 94m hubs;with 107:m rotors,,for a total height of 483'.The towers got shorter.:by 2'm,the. blades got longer by 3.5 m{each blade got 15m longer, making the rotor size,:a.k:a the diameter of the. circle,7 m larger,3.5+3.5).This has no impact on noise-the two turbines are designed to have exactly the same noise output.It is also imperceptible visually. Any confusion created here rests with BOWF's own documents. Their letter of June 24,2015 to the town's lawyer,Frank Pavia,clearly states that the change from the GE 1.7MW-100 turbine to the GE 2.3MW-107 turbines will increaseln height by 8 feet. As for any noise impacts,the noise modeling for the newer turbines dearly shows an increase In noise compared to the modeling using the older turbines. In fact,the maps show that the lands exposed to 55 dBA or more grew by 195%;50 dBA or more,by 81%. With respect to the ownership of the Project,by letter dated September 17,2015,Black Oak Wind Farm, LLC requested a transfer of Black Oak's Payment-In-Lieu of Taxes("PILOT")and tax abatement to a"new owner"called Onyx Black Oak Wind,LLC,of 126 E.56th St.,New York, NY.Nothing in the SETS indicates a change in ownership.According to a September 17,2015 email from Marguerite Wells of Black Oak Wind Farm,LLC to Heather McDaniel of Tompkins County Area Development concerning the status of local investors:"The investors will still be members of the Black Oak LLC,which doesn't go away.only (sic)the assets of the company are being sold.They'll get their eventual payments as distributions according to their shares."The matter was scheduled to be considered by the Tompkins County IDA at its September 2015 meeting.On September 19, Black Oak requested that the"revision"be put off until the Board's October meeting: "Afterconferring a bit further with my board and.Onyx,I think it would be better to put our PILOT revision off until the October meeting if possible,as we have been holding off making the info public(even to our investors)until after the deal closes.onthe 29th.1 had forgotten how public the IDA meeting agenda would be. It's no matter that we're listed on'the agenda on the website,if it stays that's ok,we can still forego actual public discussion of the details until after deal closure.Is that workable?"The matter was not.heard at the.:October 2015 meeting.It was put off.until November and then December and apparently it has still not been returned to the agenda The sole owner of.the project remains BlackOak.Wind Farm, LLC.How we end up financing the project is not:a matter for SEQRA. So here's some more confusion of BOWF's own.making. BOWF continually touts this project as . community owned but BOWF'.s letter to the.IDA quite clearly states that the assets are being sold to Onyx Black Oak Wind.LLC,not remaining with Black Oak Wind Farm,LLC.All that remains with Black. Oak Wind Farm,LLC is the right to receive the sales price over time. So much for community owned.. And while the financing is not a,SEQR matter per se,the town's windlaw,among other things,requires the Town Board's approval to transfer ownership flf the project. {33667/30473/TJF/01201177.DOCXI 10 Noise Impacts I will submit separate suite of comments that address noise impacts as will my noise expert, Les Blomberg.In short, it is clear that BOWF's SEIS does not adequately assess,avoid and/or mitigate the anticipated noise impacts from the modification of the Project. It contains no discussion of the impacts from low frequency noise and/or infrasound.Similarly,there is no adequate discussion as to mitigation of noise related impacts.Finally,there is no enforceable mechanism including realistic decibel limits to address actual noise impacts that arise during the operation of the wind farm_ There is extensive discussion of sound in the Draft and Final EIS from the original layout,which did not appreciably change in the SDEIS.Since there is a total lack of peer-reviewed science on noise-related impacts of wind farms, beyond annoyance of some residents,we do not discuss it detail. Many court cases have been brought suing for damages caused by"wind turbine syndrome"and nearly all get thrown out due to lack of credible evidence--see hftp://www.energyandpolicy.org/wind-health- impactsdismissed-in-court. Infrasound is a natural phenomenon which is present at high levels in windy areas,since wind in trees is one of the largest sources of infrasound. The Draft EIS lacks any discussion of noise impacts at all-audible or infrasound. The Draft EIS does not tell nearby home owners if they will be able to escape the turbine noise by going into their homes, or if the noise will follow them into their homes and even into their beds(it will). The Draft EIS does not mention sleep interference. The only impact mentioned is whether turbine noise in the 31.5 and 63 Hz frequency range is annoying,and that was in an appendix. There is no excuse for the lack of analysis of noise impacts. There are plenty of peer reviewed papers on audible noise and its effects. Shadow Flicker LaBella's February 8 comments to BOWF direct it to "[i]nclude text and a table summarizing the information in Section 5 of the Shadow Flicker Analysis regarding the general timing (time of year,time of day)of the shadow flicker effects for each alternative combination."The comments provide an example for BOWF to use but no such language is contained in the March 2016 draft SEIS. With respect to proposed "mitigation"of shadow flicker, LaBella states "[g]iven that some new residences will now experience shadow flicker hours approaching the 30 hour threshold (26 and 27 hours),it is recommended that the Mitigation Section refer to the Complaint Resolution Procedure should unanticipated shadow flicker effects arise"(LaBella February 8,2016 comments, No.72). The original idea of the Wind Advisory Committee was to help design a complaint resolution process to help deal with individual problems as they come up.Since there is plenty of time before Black Oak begins operation,it seems like a plan could be developed that meets people's needs. The"original idea"of the Wind Advisory Committee was to review and advise the Town Board and citizens on wind issues. Enforceability of the Wind Law and related mitigation measures is part of that. We look forward to hearing what types of compromises BOWF is willing to consider. Visual. Impacts The modification of the Project involves new locations for two towers and the substation; and construction of an intrusive MET tower,as well as a significant amount of clearing and grubbing of mature trees and land for the installation of electrical lines.Although notindicated anywhere in the SEIS narrative,it also appears clear that BOWF is moving the location of turbine 6(that is evident from reviewing the very last page of Exhibit E of the SEIS,entitled "Project Layout Comparison"which shows 7 that the footprint of turbine 6 has slightly changed).The movement of turbine 6 is not even mentioned in the Draft SEIS;the impact of such movement has clearly not been assessed. {33667/30473/TJF/01201177.DOCXI 11 Turbine 6 was moved 40',which is imperceptible from an impacts standpoint,and was only done to better comply with setbacks to Ms.Lemke's own property line. As it turns out,I had a professional review the BOWF maps and,in fact,ALL of the turbines are moving. BOWF's narrative in the Draft SEIS gives no indication of that. Although I know where my home is located, I cannot tell from the Figure how many turbines I will actually be able to see from my home:INowhere in the report is there a narrative I can refer to in order to determine how many turbines]will see. In addition,there is no discussion as to the relationship between the number of turbines that can be seen and the significance of the visual impacts I will suffer. LaBella agrees.In its February 8,2016 comments, LaBella tells BOWF's consultant that the Draft SETS "needs to include more information than just the percentages of the area with views of the turbines" (LaBella Comments,No.61,pg.1).Finally;there are very few photosimulations generally concerning the new proposed facilities and there are none depicting the view from my home or property,even though my home is eligible for inclusion on the Register of Historic Places and therefore is a resource of significant local importance. Any home over 50 years old is eligible for the.National Register of Historic Places. It is impractical and without precedent to provide photo simulations from every possible home and viewpoint in a project area. What is the point of photo simulations if they-don't convey in a realistic manner what the view shed will look like for those most impacted by.the project? My property and that of Ron Riddle on Harvey Hill Road,which is also a NRHP property,vAn apparently have the worst view sheds. Despite the fact that Ron's house is now even more,dearlyampacted than before(where he could still see 7 turbines), there is no discussion whatsoever.on that:impact to his home. Impacts to the Future Use of My Property and Valuation My property is notvacant,it is inhabited. Moreover, I use my property and want want to maintain my right to further develop it with structures. Black Oak has done nothing to impair Ms.Lemke's use of her property.The Town Board,by accepting the original EIS has indicated its agreement with us that the wind farm as proposed would pose no significant health or safety issues that would impinge on her property rights. The fad that GE suggests setbacks of 994 feet and another manufacturer's safety regulations provide for 1,300 feet indicate to me that it is not safe to use those parts of my property that are within those zones. That amountsto about half my property. Furthermore,it is highly unlikely that the town would permit any structures to be built within 994 feet of the turbine given its setback laws which further impairs my property. But most likely,I will never be able to develop over half of my land which is located within the 994 foot recommended setback.it is like a restrictive covenant or easement which l will never be compensated for.I have been told that once the wind farm is approved, I will most likely never be given approval to build any structure on the portion of my land'which is located within that recommended protective zone. BOWF should be required to compensate me for what is essentially a "taking"of my land without compensation.It should also compensate me for my proximity to this proposed facility,and the impact it will surely have on my property values. {33667/30473/T)F/01201177.DOCXI 12 In a town with no zoning,a neighboring property can do anything at all which impinges on a neighbor's property and could be considered a "taking."For example,we could start a motocross track,a hog farm, strip club,or scrapyard,and it would surely impact the neighbor's property value and enjoyment,but there is no"taking"i-n those cases.Those are all existing enterprises in Enfield that do, in the eyes of their neighbors, negatively impact their property values. No compensation has ever been required of them.Why target our business when no one else is? I'm glad to see that BOWF finally recognizes the type of"good neighbor"it will be. There is,however, at least one big difference between a strip club and BOWF. BOWFs pole dance isn't hidden from sight, but is nearly 500 feet in the air. Size matters. Furthermore,residents always have the ability to challenge a neighbor that installs a nuisance next . door,but the ridiculous wind law we have in place will make bringing any nuisance suit more difficult. Currently,there is no required mitigation in the SEIS for the devaluation of my property.Other communities,such as the Town of Hammond,New York,require mandatory guarantees of property values as part of any wind farm approval.I have seen a copy of the guarantee agreement in Hammond which is a condition of any wind permit issued by the Town.21 Section 2.6.1.2 of the Draft SEIS acknowledges that future development on certain properties such as mine will be curtailed due to the proximity of turbines from the Project to the property lines.That impact must be mitigated in the SEIS. And there are no wind turbines in Hammond,NY,either. No wind company can afford to pay people the theoretical value difference in their property value,especially when there is no statistically significant expectation of devaluation in the first place. No projects get built in towns with un-financeable restrictions in place.See the Realtor.org list of studies that demonstrate with near unanimity that wind farms do not devalue properties.Only a couple of studies have shown a negative impact over the years,., while the vast majority of these studies do not. It defies common sense to believe that these turbines won't have a negative impact on our property values. Look at how controversial these projects are all around the world. I can see my realtor's banner now: Nice house with great views(of noisy turbines)! No one,given the choice,would buy a property with turbines nearby. Furthermore,most property value studies are flawed. They look at homes in a 5 mile radius as opposed to homes within 1,000-2,000 feet from a turbine,some are limited to urban areas,many lack reasonable controls on the data,or mostly look only at the visual impacts and ignore all the health and safety issues. Impacts on Area Roads.Roads in the area of the Project area are already crumbling, reportedly because the Town has delayed maintenance for over nine years in anticipation of the Project.Those delays were apparently suggested or requested by John Rancich,the Project's initial sponsor,who indicated at the January 3,2007 Town Planning meeting that the Project would degrade the condition of the road so it was better to wait.The Town's Highway Supervisor has repeatedly expressed concerns that heavy truck traffic during construction of the Project will permanently damage the road'bed. No"Road Use Agreement"has been made public yet,and the Highway Supervisor has indicated that he has yet to see any draft.The Draft SEIS should identify impacts on roads during construction and provide clear,specific and enforceable standards for mitigating impacts to such roads, not just a general and unenforceable promise that standards will be developed and adhered to.The SEIS needs to describe how BOWF will shore up the roads before construction,ensure safety during construction,and repair damage followin {33667/30473fr)F/01201177.DOCXI 13 construction.The Highway Supervisor has acknowledged that he has not been consulted by the Town Board in over a year concerning this important issue. That is also not factual.The Highway Supervisor has seen several drafts of the proposed road use agreements,and has attended meetings with the County on the subject;it has been under discussion for a couple of years. Furthermore,construction projects are only required to return roads to pre- construction condition, but Black Oak has all along proposed to restore the roads to NEW condition after construction.We will be entirely rebuilding Black Oak and Connecticut Hill roads.This is well in excess of requirements.The SEIS is not the venue to discuss-the details of the road use agreement,except to provide a draft,which we did.The Agreement itself is the place to discuss those details,and we will do so. In fact,this was most recently discussed at the last town board meeting on April 13th. The purpose of an EIS,including a draft SETS,is to assess the anticipated environmental impacts of an action and to ensure that such impacts are avoided or mitigated to the extent practicable. A road use agreement is just one example of necessary mitigation that is not adequately discussed in the Draft SETS. But the secrecy continues. So far,the residents have not been provided with drafts of this agreement to review other than one copyset out briefly at the beginning of the last Town Board meeting. I tried to look at it when the agreement came up at the meeting but by then it had been removed. Once again,I have had to submit a FOIL request.to get it. As for the Highway Supervisor's review,I have spoken with him at length on a number of occasions and in each of those calls he maintained that he has,not seen drafts(other than the initial draft included in the DEIS which was nothing more than an agreement from another town with the name blacked out). I spoke with him shortly before submitting my comments and he had still not seen the drafts that were circulating. 1 do believe he may have been provided a copy of the most recent document between the time 1 spoke with him and the date of this letter. But,at the last Board meeting,Dan Walker of our Planning Board who has been handling this matter,said he hadn't seen this most recent draft which appears to be more of a road use policy document than a contract. 133667/30473/TJF/01201177.D0CX) 14