B. Caldwell: Called meeting to order at 6:40 pm and stated Natan had
brought up some proposed road and bridge projects that the
County Highway people are considering where they might
get federal aid and several of these are in the Town of
Dryden. She asked George Franz if he was familiar with
any of these projects.
G. Franz: Stated some of the bridges such as Red Mill is going
forward and was not sure about Freese Road.
B. Caldwell: Noted they were talking about changing the angle of Freese
Road and making it a two lane bridge which would change
the traffic considerably.
J. Layuatra, Jr.: Stated there was concern about Freese Road and Route 366
as it is already a dangerous intersection. Asked if the
Planning Board had any obligation or right to provide input
on these situations'?
B. Caldwell: Noted the Planning Board has a right to comment on
anything they wish but there is not an obligation.
J. Layuatra, Jr.: Stated obligation was not what he meant rather wanted to
know if they had to listen to the Planning Board's input or
was the County roads under their complete control.
B. Caldwell: Suspected that if the Board wanted to make a formal input
the Planning Board may want to do it via the Town Board.
G. Franz: Stated Freese Road is a Town Road.
B. Caldwell: But the bridge is longer than so many feet that it becomes a
County bridge.
G. Franz: Stated over 25 feet.
J. Layuatra, Jr.: Suggested the Planning Board make a recommendation to
the Town Board that Freese Road remain a one -lane bridge
and that it is there for a reason as a traffic calming.
G. Franz: Knows that they came up with an.overall solution that the
traffic in Varna on Freese Road that it should remain a one
lane bridge.
B. Caldwell: Noted they should do what's necessary to stabilize the
bridge as there are some issues on the Route 366 side bank.
u
cA
0
r
•I
l�
�J
G. Franz: Stabilize it or again it may very well need to be rebuilt.
"There is precedent for rebuilding it a one -lane bridge.
B. Caldwell: They did some work on it after the flood in the 1970's.
G. Franz: The flood of 197E where it took out the one end of the
abutment. Stated he is familiar with the intersection.
N. Huffman: Stated our perspective of planning and land use within the
town, does not feel this is complimentary.
G. Franz: Feels the process before any work makes any list for
federal funding they need to make it to the Tompkins
County Transportation Board and feels at this point, the
Planning Board needs to put together a response to go to
the Transportation Board.
B. Caldwell: Asked Tom Hatfield if it would be best to make a
recommendation to the Town Board so they can pass on
their comments. She stated she feels reluctant as a
Planning Board to pass the comments directly to the
Transportation Board.
T. Hatfield: Stated that would be the appropriate avenue to take and
noted they may direct the Planning Board to take the issues
directly to the Transportation Board.