HomeMy WebLinkAboutTB 2026-09-17 attTB 9-17-26
Page 1 of 12
TOWN OF DRYDEN
TOWN BOARD MEETING
September 17, 2026
Zoom Hybrid
Present: Supervisor Jason Leifer, Cl Daniel Lamb, Cl Leonardo Vargas-
Mendez, Cl Christina Dravis, Cl Spring Buck
Other Officials: Loren Sparling, Town Clerk (appointed)
Other Town Staff: Amanda Anderson, Bookkeeper
Ray Burger, Planning Director
*Cassie Byrnes, Secretary to the Supervisor
Shelley Knickerbocker, Senior Code Enforcement Officer
Dave Makar, Dryden Fiber Executive Director
Guest(s): Pete Tyler, Dryden Fire Chief
*denotes attendance via Zoom
Supv Leifer opened the meeting at 6:06 p.m. Board members and audience recited the
pledge of allegiance.
TOWN CLERK
RESOLUTION #188 (2026)
APPROVE MINUTES
Supv Leifer offered the following resolution and asked for its adoption:
RESOLVED, that this Town Board hereby approves the meeting minutes of August 13
and August 20, 2026.
2nd Cl Lamb
Roll Call Vote Cl Vargas-Mendez Yes
Cl Buck Yes
Cl Dravis Yes
Cl Lamb Yes
Supv Leifer Yes
PUBLIC HEARING (cont.)
LOCAL LAW REPEALING AND REPLACING ARTICLE IX OF CHAPTER 240 OF THE TOWN
CODE REGARDING CONSERVATION SUBDIVISIONS AND ADDRESSING RELATED
MATTERS
The public hearing on the “Local Law Repealing and Replacing Article IX of Chapter 240
of the Town Code Regarding Conservation Subdivisions and Addressing Related Matters”
remained open from last month’s meeting and was continued at 6:07 p.m. No member of the
public provided additional comment, so the Board used the time to resolve the one substantive
question left hanging from its August 20 discussion.
As drafted and posted, Section 240-9.2 (Applicability) states that the Article applies to
all major subdivisions proposed in the Rural Agricultural (RA) and Conservation (CV) districts
(amounting to over 60% of the Town), thus making the use of conservation subdivisions
mandatory in these areas. The Rural Residential (RR) district was deliberately left out,
TB 9-17-26
Page 2 of 12
rendering the use of conservation subdivisions optional in these areas. Board members recalled
that an earlier draft had included RR. R Burger clarified that the Planning Board removed it
after feedback that the law would otherwise impact too much (over 90%) of the Town.
Cl Buck revisited that decision, arguing that public comment from the farming
community, as well as the Town’s Agriculture Advisory Committee, supported bringing RR back
in, but only where it overlaps a New York State agricultural district. With this addition,
conservation subdivisions would be applicable to major subdivisions in about 75% of the Town.
Cl Lamb added that so much of RR is qualitatively open space that excluding it would undercut
the law’s purpose of preserving it.
Two concerns surfaced. The first was administrative. State agricultural districts are
renewed on an eight-year cycle, so the overlay shifts over time, and the Town would have to
track it. Several members judged this a light burden, as the County publishes the district list,
the parcels are already identified for tax purposes, and the applicant would be the one
establishing whether the overlap applies. One counterpoint was that the Town does not have
in-house GIS capability and would still need a way to verify an applicant’s claim.
The second was whether the change restricts housing. The answer given was that it
does not reduce how much housing can be built; it changes the process by which it is laid out.
A parcel in the overlap area would still be developable, but under the conservation subdivision
law rather than the standard subdivision law.
The Board reached consensus consistent with the August 20 discussion. The agreed
path forward is as follows:
∙ Amend 240-9.2 to extend applicability to “RR districts that overlap with New York
State Agriculture Districts;”
∙ Fold in the edits due to typos and formatting errors;
∙ Recirculate the consolidated draft to the Board for a final look; and
∙ Notice the result as a new draft local law for a fresh public hearing next month.
R Burger characterized the applicability change as the only edit substantial enough to
require re-noticing. The clarifying edits on their own would not have justified a rehearing.
There were no additional comments from the public, and the public hearing was left
open at 6:18 p.m.
PUBLIC HEARING
LOCAL LAW TO OVERRIDE THE TAX LEVY CAP
The Board opened the public hearing on the local law overriding the State tax levy cap
at 6:18 p.m. It was described as the annual measure the Town adopts each year with only the
dates changed. The override is a precautionary authorization; it preserves the Board’s ability to
exceed the cap if the 2027 budget requires it, without committing the Town to doing so. There
were no comments and the public hearing was left open at 6:19 p.m.
ANNOUNCEMENTS
Budget workshops were scheduled for October 1, October 8, and October 15. The
October 1 workshop will follow the joint fire district session that evening. The October 8 and
October 15 workshops will follow the regularly scheduled Board meetings. Supv Leifer noted
there is room to add a session if needed.
PLANNING DEPARTMENT
TB 9-17-26
Page 3 of 12
R Burger informed the Board that the Department’s monthly report was circulated to
them.
He highlighted that the abutments and wing walls for the Rail Trail bridge over Route
13 are complete. The bridge structure is fabricated and waiting in Oklahoma to ship east. A
tentative schedule had delivery on September 23 and installation on September 24, with
overnight storage at the NYSEG parking lot and the crane mobilized the following morning for
same-day placement. Several approvals remained pending, and R Burger cautioned the date
could easily move. Installation will happen within a few weeks, but no firm date was available.
The original traffic plan required shutting down Route 13 for the day with a detour out to
Lower Creek Road and down through Varna. That has been reworked into a single-lane closure
with alternating flow all day, avoiding both the detour and a very large number of unhappy
commuters.
The company invited to present on Battery Energy Storage Systems (BESS) has scaled
back its New York operations, is no longer interested in the Dryden project, and is investing
elsewhere. There will be no presentation this month. The company was unrelated to the earlier
NYSEG discussions. NYSERDA separately presented to the Planning Board and is releasing a
second version of its model BESS law.
The Town is proceeding with a battery storage law regardless, as part of the Phase 1
zoning rewrite, with the Zoning Advisory Group drafting. It will cover both commercial and
residential installations but is focused on commercial. Residential battery systems – the Tesla
Powerwall class of product – are already accommodated under existing code as something akin
to an HVAC system. Board members noted growing interest in home storage charged during
off-peak hours and discharged at peak, both for household cost and grid leveling.
DISCUSSION/ACTION ITEMS
Authorize Dryden Town Court to Apply for 2026-2027 JCAP Grant
The Court has asked for authorization to apply for a Justice Court Assistance Program
(JCAP) grant. The resolution under consideration is identical to the one adopted last year
except for the grant cycle years. The Board can approve an application for up to $30,000. The
Court has requested an amount of $4,849.03 for filing cabinets.
RESOLUTION #189 (2026)
AUTHORIZE JCAP GRANT APPLICATION
Supv Leifer offered the following resolution and asked for its adoption:
WHEREAS, the Town of Dryden Justice Court is in need of certain equipment for its
offices and has made the Town Board aware of a grant opportunity to cover the expense of that
equipment, therefore be it
RESOLVED, that this Town Board of the Town of Dryden hereby authorizes the Dryden
Town Court to apply for a JCAP grant in the 2026-2027 grant cycle up to $30,000.00.
2nd Cl Dravis
Roll Call Vote Cl Vargas-Mendez Yes
Cl Buck Yes
Cl Dravis Yes
Cl Lamb Yes
Supv Leifer Yes
TB 9-17-26
Page 4 of 12
Approve 2027 Cost of Living Increase for Non-Union Staff
A Anderson informed the Board of a decision it needed to make before the 2027 pay
schedule – and therefore the 2027 budget – could be finalized. Two reference articles were
circulated by email earlier in the afternoon regarding expected CPI (Consumer Price Index)
rates for 2027. One was from the Bureau of Labor Statistics’ (BLS) regional report for the
Northeast, which lists CPI at 3.9% (regional figure). The other was an article about the
projected Social Security COLA increase for 2027, which lists COLA at 3.4% (national figure).
(CPI and COLA are similar measures.)
The Board opted for the 3.9% COLA increase, reasoning consistency, as the Northeast
BLS figure is what the Town has used since A Anderson began preparing the schedule.
A Anderson noted in passing that grocery, fuel, and electricity costs supported the
higher regional number over the national one, and that the national figure reflects a larger and
more diluted basket.
RESOLUTION #190 (2026)
APPROVAL OF 2027 COST OF LIVING INCREASE FOR NONUNION STAFF
Supv Leifer offered the following resolution and asked for its adoption:
WHEREAS, the Town Board established a Pay Schedule which set the hiring minimum
hourly rate for all positions, which may be increased each year based on a Cost of Living
Adjustment (COLA);
WHEREAS, the Town Board has reviewed the current and projected 2027 COLA reports
for determining the annual payrate increases for the 2027 Pay Schedule;
RESOLVED, that this Town Board hereby approves a 3.9% COLA increase for the 2027
Pay Schedule for all nonunion employees.
2nd Cl Dravis
Roll Call Vote Cl Vargas-Mendez Yes
Cl Buck Yes
Cl Dravis Yes
Cl Lamb Yes
Supv Leifer Yes
PUBLIC HEARING (cont.)
LOCAL LAW TO OVERRIDE THE TAX LEVY CAP
Supv Leifer closed the public hearing at 6:33 p.m.
RESOLUTION #191 (2026)
ADOPT LOCAL LAW TO EXCEED THE TAX LEVY CAP
Supv Leifer offered the following local law and asked for its adoption:
RESOLVED, that this Town Board hereby adopts the following local law and directs the
Town Clerk to file the same with the Secretary of State of the State of New York:
A Law to Override the Tax Levy Limit Established in General Municipal Law §3-c
TB 9-17-26
Page 5 of 12
Section 1. Legislative Intent: It is the intent of this local law to override the limit on
the amount of real property taxes that may be levied by the Town of Dryden, County of
Tompkins pursuant to General Municipal Law §3-c, and to allow the Town of Dryden, County of
Tompkins to adopt a town budget for (a) town purposes, (b) fire protection districts, and (c) any
other special or improvement district, and Town improvements provided pursuant to Town Law
Article 12-C, governed by the Town Board for the fiscal year beginning January 1, 2027 and
ending December 31, 2027 that requires a real property tax levy in excess of the “tax levy limit”
as defined by General Municipal Law §3-c.
Section 2. Authority: This local law is adopted pursuant to subdivision 5 of General
Municipal Law §3-c, which expressly authorizes the Town Board to override the tax levy limit
by the adoption of a local law approved by vote of at least sixty percent (60%) of the Town Board.
Section 3. Tax Levy Limit Override: The Town Board of the Town of Dryden, County
of Tompkins is hereby authorized to adopt a budget for the fiscal year 2027 that requires a real
property tax levy in excess of the limit specified in General Municipal Law §3-c.
Section 4. Severability: If any clause, sentence, paragraph, subdivision, or part of this
Local Law or the application thereof to any person, firm or corporation, or circumstance, shall
be adjusted by any court of competent jurisdiction to be invalid or unconstitutional, such order
or judgment shall not affect, impair, or invalidate the remainder thereof, but shall be confined in
its operation to the clause, sentence, paragraph, subdivision, or part of this Local Law or in its
application to the person, individual, firm or corporation or circumstance, directly involved in
the controversy in which such judgment or order shall be rendered.
Section 5. Effective date: This local law shall take effect immediately upon filing with
the Secretary of State.
2nd Cl Lamb
Roll Call Vote Cl Vargas-Mendez Yes
Cl Buck Yes
Cl Dravis Yes
Cl Lamb Yes
Supv Leifer Yes
DRYDEN FIRE
P Tyler reported on a difficult morning: a head-on collision on Slaterville Road requiring
extensive extrication and a multi-department response. The Department was called relatively
late and was on scene an additional fifteen minutes beyond arrival. It was the second such
incident in a few weeks, following a box truck extrication, and was described as another
demonstration of the value of the recently purchased extrication tools.
He provided the following details from the August call report:
Total calls: 40
Structure fires: 1
Medical calls: 13
Rescue calls: 5
Motor vehicle accidents: 5
Extrications performed: 5
Service calls: 11
Alarm calls: 4
Average personnel per call: 6.7
Average response time: Just over 3 minutes
TB 9-17-26
Page 6 of 12
Two figures were highlighted. Five extrications in a single month were offered as direct
support for the cost-benefit case made when the tools were purchased. There being only four
alarm calls was presented as evidence that the Department’s working relationship with TC3 is
having its intended effect – alarms are being taken more seriously at the source and repeat
calls are down. The Department hopes the trend holds into the school year.
Two public events were announced: 1) the Dryden Fire Department open house on
October 11, 11 a.m. to 2 p.m., with apparatus displays, food trucks, and activities, to be held
rain or shine; and 2) Fire Prevention Week soon thereafter. District business is also underway.
Supv Leifer added that Dryden Ambulance marks its 50th anniversary on September 26
at 1 p.m. P Tyler encouraged attendance, with praise for the service’s sustained performance.
ADVISORY BOARD UPDATES
Affordable and Workforce Housing Committee
Cl Vargas-Mendez reported that the Affordable and Workforce Housing Committee
undertook no action items. The Committee heard a presentation from Broome County BOCES
on its tiny house construction program, which members found promising, and thus is following
up locally with TST BOCES. Board members confirmed the Committee had not discussed
zoning because tiny houses are already permitted under the current code; the missing
ingredient is someone to build them.
Agriculture Advisory Committee
Supv Leifer reported that the Agriculture Advisory Committee did not meet last week.
Their next session will occur in October.
Climate Action Committee
Cl Dravis reported that the Climate Action Committee is hosting two events at the
Dryden Center for Community.
On Tuesday, September 22, 6:30-8:30 p.m., the first installment of a speaker series will
take place. This presentation will introduce the Committee itself, how it formed, and what it is
working on.
On Saturday, September 26, 9 a.m. – 12 p.m., the next Repair Café will occur.
Conservation Board
Cl Buck reported that the Conservation Board did not meet this month.
DRYC (Dryden Recreation and Youth Commission)
Supv Leifer reported that the DRYC meets next week. Current business is County
program (i.e., OURS, YOURS) requests, which will arrive before month’s end.
On grants, the budgeted grant writer position was discussed with a consultant who was
used for Town grants a few years ago and who is currently available to work on recreation and
other grants. The Board agreed to let the Commission decide and then engage her under
whatever her current agreement terms are. The Commission intends to apply for the NY PLAYS
grant for playground updates.
TB 9-17-26
Page 7 of 12
Planning Board
Cl Lamb reported that the Planning Board heard a presentation from Alan Lord, the
developer of the 172 Ed Hill Road project, on revised lot designs. The plan now shows 15 lots,
each ranging from 5 to 12 acres – most of which are substantially smaller than originally
presented. Cl Lamb characterized this as a positive development still under review.
The developer will provide the Town access on the rail bed, preserving the option of a
trail there. There are no immediate plans to build out the Rail Trail there, but Cl Lamb wanted
access secured. R Burger noted that access to some of the homes originally ran off the trail,
meaning the trail would function as a shared driveway for a portion of its length. Cl Lamb said
plainly that co-using the Rail Trail as a driveway is not something he is enthusiastic about,
while acknowledging it may be a trade-off the Town has to accept.
Trillium Woods is to be conveyed to the Town. Cl Lamb remarked that the Town had not
anticipated becoming the holder of that property but welcomed it.
There was also discussion about the need to develop a BESS policy for the Town.
The Zoning Advisory Group (ZAG) met and spent considerable time on manufactured
homes, clarifying the language and ensuring the zoning rewrite is as open as possible to
manufactured housing.
R Burger added that the preliminary plat hearing on the Ed Hill Road development is
scheduled for next Thursday’s meeting of the Planning Board.
Rail Trail Task Force
The Rail Trail Task Force last met on August 17, so Cl Lamb had nothing new to offer
since his last report on August 20. The next meeting of the Task Force is scheduled for next
Monday at 7:00 p.m.
Veterans Committee
Cl Dravis reported that planning continues on the Hometown Heroes banners, with the
Committee chair in contact with both villages. The chair is also exploring the possibility of
banners in Varna. For Varna, the Town’s role would be limited to hanging the banners, as
NYSEG owns the poles and the Town owns the light fixtures. The chair is also coordinating
with the Climate Action Committee. Operation Green Light returns in November, with 500 light
bulbs secured – more than expected, with surplus to be stored.
DRYDEN FIBER
D Makar reported that the project needs easements primarily along highway-by-use
roads in order to do underground work in the right-of-way.
Easements fully executed (as of September 1, 2026): 75 (compared to 47 in August)
Easements fully executed (as of this meeting): ~79
Easements verbally accepted, but not yet signed: 25
Estimated completion: About one-third
Easements originally identified: ~240
Easements after verification: ~180
Easements added since May 1 (newly discovered need): +60
TB 9-17-26
Page 8 of 12
The 60 newly discovered locations are largely a consequence of missing pole licensing.
Where a pole is not ready for the project’s use, there are two options. The first is to pursue a
pole license – coordinating with NYSEG and engineering firms, replacing poles, moving existing
attachments – which takes six to 12 months. The second is to come down from the last usable
pole, run underground parallel to the road, and go back up at the next ready pole; this process
takes about 22 days. Given the project deadline, the second is the working default. That choice
converts a licensing problem into an easement problem, which is why the denominator keeps
growing.
Dryden Fiber has a count of 593 customers, a net gain of 10 in August – 14 added, four
lost. Three of the four lost customers moved out of town; one relocated beyond the service area
and asked to stay on the list. New owners of the relocated property are expected to sign up.
There were 78 inbound service requests in August, 17 more than July. Construction is
ongoing all over town.
The firm originally engaged for the project did not install grounding in the cabinets,
requiring a remediation project that took months, largely waiting on supplies. Completed last
month, with an added upgrade giving cabinets both AC and DC power so different server and
network device types can be housed, this was described as a major unlock for adding houses to
the network, with that work starting within 30 days.
Milestone two under the New York State grant required progress on the Caroline hut
and 44 miles of construction built – 30% of the project. Both have been met. The associated
reimbursement is $3.2 million, expected within 60 days, though D Makar cautioned it is the
first reimbursement tied to mileage and the State will scrutinize the claimed miles. Payment
could slip to January.
Pre-installation – running service from the street to the building ahead of activation, to
save time in winter – has begun. Of 43 previously signed-up households emailed in areas
expected to activate soon, 37 confirmed they still want service. Installations are underway.
About 100 new customers have been added this year against roughly 600 new sign-ups.
Demand is well ahead of capacity to serve it.
The Municipal Infrastructure Program (MIP) portion totals 147 miles – about 57 in
Dryden and about 90 in Caroline. Dryden’s final payment is contingent on the entire project
being complete, Caroline included, which is why both builds are being pushed in parallel. D
Makar introduced a distinction the Board should carry forward, because the two mileage
figures displayed tell opposite stories:
Miles constructed and credited (44.1) – Counts toward state reimbursement
milestones, about 30% of the required build
Miles connected into the live network (5.1) – About 3.4% of the project is actually
serviceable
The discrepancy exists because gaps in State highway permits, pole readiness, and
easements prevent segments from being tied together. Crews can earn milestone credit by
building three miles here and five miles there – e.g., on Peruville, Bone Plain, West Dryden,
Hanshaw, and Etna Roads – without those segments forming a continuous path back to a
point of presence. Progress toward the grant and progress toward customers are, for now,
different things.
Of the first 106 easements processed, 96 owners said yes and 10 said no, about 90%
acceptance. Roughly three-quarters of the owners who signed went on to request service
TB 9-17-26
Page 9 of 12
themselves, often the same day. Only a small share of easement targets was already on the
waitlist; an early sample put it at about 25 of 150, or 12%. Easement outreach is functioning
as customer acquisition.
The obstacle in easement acquisition is not refusal; it is contact. For most parcels, the
Town has only the tax mailing address – no phone number, no email. Staff resort to search
engines, white pages listings, and asking the Planning Department and Clerk’s Office. Once
contact is made, the average time to a signed and notarized easement is about 22 days. Where
the owner already knows the presenter or the easement specialist, it drops to five or six days.
Making first contact can itself take weeks.
More than 100 easement packages have been mailed cold (after attempts to contact
owners by phone or email have failed), and not one has come back. Every executed easement
followed a human conversation. Three or four in the sampled set signed only because staff
went to the door in person.
The countermeasure is a short advance postcard: “Dryden Fiber is coming. We need
your help. It concerns the frontage along the road. Expect a call or a package in the next 10
days.” D Makar described the effect on response as a complete reversal. Without it, cold calls
are heard as sales calls. Owners who already have service hear a pitch to switch and never
register the word “easement.” The postcard costs about seven days in mail transit, which is
now built into the front of the process alongside drafting.
Residential customers do not receive a static IP; it is a business-tier benefit. The
original add-on product offered five additional addresses for $40 per month, priced
competitively against the market. In practice, most businesses needing more than one do not
need five and allocating five to a customer who uses only one or two addresses strands the
remainder. The revised policy, brought though the Broadband Committee, keeps one address
with the business tier and sells additional addresses individually at $10 per month each.
Customers pay only for what they use, and the Town preserves its address inventory.
A declination letter is sent to those owners who decline an easement. This letter was
developed over recent months with Cl Lamb. It is explicit about the consequences assumed due
to the declination, as follows:
∙ The parcel will not be included in Dryden Fiber’s construction.
∙ The parcel will not be eligible to connect to the network through the primary build.
∙ Any future connection, if technically feasible, will be at the property owner’s expense –
estimated at $3,000 to $5,000 to remobilize engineering, construction crews, directional
drilling equipment, and to place a vault and run service.
∙ The parcel’s status will appear on the public service map, shown in red with an
explanation that needed property access was not provided.
∙ The owner has 30 days from the date of the letter to reconsider.
Four such letters have already been sent by email. One owner reversed within 12 hours.
Letters are also sent by certified mail, so the Town holds a signed record that the owner was
informed – closing off a future claim of ignorance, including by a subsequent purchaser. Board
reaction was favorable, describing it as a fair process that lets people understand what they are
declining.
Roughly 103 miles remain to be built against a June 30 deadline, about eight-and-a-
half months away. Three representatives of New York State’s ConnectALL office are visiting
Dryden in person on Monday, from 9 a.m. to roughly 2 p.m., with a fourth joining virtually, to
discuss this; engineering staff will also be in attendance. The agenda comprises pole readiness,
TB 9-17-26
Page 10 of 12
permits, materials, construction plans, and how the remaining miles get built in the time
available. It is the Town’s first in-person meeting with the Empire State Development team.
Engineering is currently handled by Vantage Point as primary firm and ECC of
Rochester as secondary. The State has asked the Town to bring a role in-house rather than rely
solely on outsourced consultants and requested the hire of a Fiber Deployment Manager to own
the technical side of delivery: pole readiness, pole licensing, coordination with NYSEG and
DOT, and holding subcontractors to the deployment rates their firms have represented as
achievable. This sits alongside the existing financial, account management, outreach, and
easement functions. The position was posted in July, screened in August, and interviewed the
week before the Board meeting. A finalist has been offered the job, paperwork is scheduled for
tomorrow, and a Monday start is expected. The name will come before the Board for approval
at its first October meeting.
All 16 New York State DOT permits are in hand and being implemented. All points of
presence (POPs) have been upgraded. Some parcels are expected to go live in the green zone
within four weeks. D Makar closed with a request for public patience, framing the network as a
40+ year asset that is worth building correctly now.
OTHER ITEMS
Tompkins County Council of Governments (TCCOG)
Cl Lamb flagged next week’s Tompkins County Council of Governments (TCCOG)
meeting as worth attending, as two guests will be featured. Jay Franklin, the County Assessor,
will be speaking on the disabled veterans tax credit, an item that was raised at a previous
Board meeting and one the Assessor believes municipalities do not understand well. Hailley
Delisle from County Planning will also be speaking on the County’s Climate Action Plan. The
meeting is publicly noticed and available on Zoom.
Establishing Sewer/Water EDUs
A Anderson read the following statement regarding the establishment of sewer/water
EDUs:
This report is to let the Board know about future steps and actions that will need to be
taken over the next 9 to 12 months to establish Sewer and Water Equivalent Dwelling Units
(EDUs) for future tax assessment.
The Town representatives to the Ithaca Wastewater Treatment Facility have been
informed that there will be significant debt to be shared between the member municipalities.
Also, the Town will have its own debt through EFC for the sewer project and water project capital
improvements that have been happening to the Town-owned sewer lines.
Currently, the consolidated sewer and water districts have no debt, and all expenses
(repairs, maintenance, and supply costs) have been funded through sewer and water usage rates
that are set annually by the Town. But with the new debt, the Town will need to levy property
taxes to all parcels that are served and within the sewer and water districts to fund these capital
improvement debts.
In order for debt to be assessed in 2028, the Town will need to determine how to levy the
taxes before September 2027 for 2028 budget planning. The consolidated sewer and water study
done by TG Miller in 2017 provided a suggested method to assign EDUs for each parcel, but no
final action was taken at the time the districts were consolidated in 2019.
TB 9-17-26
Page 11 of 12
Looking at the current records, EDUs have not been assessed for the parcels in the
districts. The County assessment office has provided their current list of properties that are in the
districts. And in the 2017 study, there is a list of properties with possible EDUs assigned.
The Town needs to update the assessment roll in order to tax the properties in the
districts. The Town will need to look at the properties that are benefitted and those that could
benefit (meaning they could have sewer and water service but are not currently utilizing it).
At a future meeting, a recommendation will be provided on how to assign EDUs. Once the
Town Board approves the recommendation, there will need to be a mailing to every property
owner within the district with their individual assessment. Then, there will be a public hearing for
a local law to establish the method of assessing EDUs for each property in the district.
At this public hearing, which should be held in late spring 2027 (but as late as August
2027), property owners can make comments about the process.
The work requires a single individual to take on the process. The position would touch
legal, engineering, assessment, planning/zoning, and the Town Clerk’s office (which handles
billing). A Anderson volunteered to take it on, describing it as already within the scope of the
job and noting the advantage of holding several of the relevant threads – tax assessment, the
budget, and the relationships with the engineer and attorney.
Concepts discussed include:
∙ Full EDUs for existing served units; a fractional share – a quarter or a half – for vacant
parcels
∙ Whether the fraction should turn on acreage or on zoning-permitted density. A two-
acre parcel might carry half an EDU because only one house fits. A hundred-acre parcel
zoned for one-acre lots raises the question of whether it carries a hundred fractional
units.
∙ Mobile home parks are currently billed as a single account but would likely receive
units assigned by lot count.
∙ A pre-consolidation precedent exists – a reduced formula by acreage or percentage
applied to vacant land, associated with the parcel on Turkey Hill Road where the solar
array now sits. The documents exist somewhere and should be located before the Town
reinvents the method.
The hardest issue is how to treat land that does not receive service but could. The
working definition offered for this was land with no structure currently taking service, which
would be eligible if the mains run past it. The rationale offered to property owners is that the
availability of Town sewer and water is itself a benefit to the parcel, and that the choice is
between paying for the infrastructure now or paying to buy into the district later.
Cl Lamb’s substantive question was whether a property owner could face a higher
assessment purely because of development potential, without changing anything on the parcel.
The answer was that this is precisely the open question and there is no final answer yet.
Supv Leifer offered to be a part of future discussions on the matter, and voiced that, at
roughly 90 parcels, Yellow Barn will need a similar treatment and appears never to have been
studied. It also carries an operational problem, as pipes failed last winter and the Highway
Department had to replace a section that burst in the cold. Board members agreed that the
Highway Superintendent needs to be brought into that conversation, and that it is a separate
exercise from the consolidated district work.
There being no further business, the meeting was adjourned at 7:31 p.m.
TB 9-17-26
Page 12 of 12
Respectfully submitted,
Loren Sparling
Town Clerk
DRYDEN FIBER
MONTHLY REPORT
for August 2026
DRYDEN BROADBAND COMMITTEE MEETING on Sept 11, 2026
And
DRYDEN TOWN BOARD on Sept 17, 2026
Our Mission is to provide
reliable, affordable, high -
speed, fiber -based internet
access. We offer state-of-
the-art technology and
unmatched customer
service.
EXECUTIVE SUMMARY – 9/1/2026
▪The Good News:
Easements: The first 75 (+28) are completed (signed and filed);25 more verbally
o 593 customers are active as of Sept. 1, 2026 (Net of 10; +14 in August; -4 in August)
o 78 in-bound service requests in August (17 more than July)
o Construction is on-going all over town: Both underground and aerial
o Cabinet/Pop Grounding and DC Power Project: 100% complete
▪Next up: Calix Installations week of September 14
o Milestone #2: Mileage Goal Complete!
▪30% of MIP (44 of 147 miles)
▪$3.2M reimbursement request
▪TBD on payment (review details of miles, construction, and expenditures)
o Pre-Installation Process has started
Service Requests
Service Requests – Map Watchers
▪They installed the cable down the road this week. I know there may be time yet before
it all gets connected to the network and tested but I'd like to be put down on the list for
installation as soon as its ready.
▪I believe service is coming to our area if it is not here already. We received a postcard
in the mail advising that we could register.
▪It seems I'm in the yellow zone so let me know when and if I go green. Thanks
▪Our street is in orange right now on the map, looking forward to joining!
▪It is unclear to me if this service is provided at this location - but it seems if it is not
currently it will be in a month or so?
▪Service is coming to my area soon, and I’m signing up early
▪It looks like there is a buildout date for my residence and I want to make sure I'm in the
queue for that.
▪Sign me up for the pre-service install. Cable is already hung at my location so I would
like to be ready to go as soon as service is turned on.
Service Requests – Functionality / Service
▪I wanted to start with the 1gb but if i do not need or notice a difference I was just curious if
it is easy to switch to a lower plan?
▪Will I be contacted when you know more about the availability in my neighborhood?
▪Can I use the wifi routers I currently have? Or a new mess system.
▪If we set up an uninterrupted power supply in case there is a power outage, would we
continue to receive service or will the power outage affect the main source?
▪we have an existing router, just want to see if it will be possible to use with fiber.
▪Do you provide underground cable installation? At what cost?
▪I'm on the West side of [Road]. Can the fiber be run across/under the road if the main line
runs on the east side of the road?
▪Email or Phone, both are fine. Also wondering recommendation of packages - silver, gold
or platinum.
▪I would like an additional plume to put in my garage for mesh coverage. I also was
reached out to in the past to add service but was not ready at that time. I am ready now!
▪Want 5 Static IP addresses
Service Requests – Patient Waiters
▪can't wait no longer
▪we are waiting for you!
▪Please hurry. I’d like to reliably make phone calls, watch tv and get Ring security.
Thank you!
▪How quickly can I get service?
▪? When is earliest service can be operational ?
▪Looking forward to add service as soon as it reaches my home
▪I look forward to service!
▪How soon can we start!?
▪Patiently awaiting fiber on Sheldon Rd!
▪I think I may have filled this out before, but I am looking forward to having service
available and will sign up as soon as it is in my area.
Service Requests - Competition
▪We would like service ASAP as [Our Cable Provider] is trash! We love your residential!
▪I see my property has recently been added to the Yellow and I would very much appreciate being
aligned with Dryden Fiber (I'm sick and tired of [Our Cable Provider])
▪We are unfortunately 1 road away from the edge of your service map [in Groton]. We are sick and
tired of being monopolized by [Our Cable Provider] internet and would very much welcome some
competition in our area! I would switch over in a heartbeat if you would consider expanding your
service a little further north.
▪We have fiber ran from [Our Cable Provider]. Could this be reused without having to run new wire?
▪We're hoping this service is better than [Our Cable Provider]. The rates are considerably less than
[Our Cable Provider].
▪We’re eager and in the Oct 2026 install area! Just got my $90 Internet bill from the monopoly. I was
working on WiFi and Fiber broadband Internet products in 1980 at DEC Digital Equipment Corp. 45
years ago!
▪eagerly awaiting a better internet connection than my current DSL line from [Our Phone Provider]
▪Currently connected to [Our Fiber Provider] and ready to not be.
▪Please hurry to [My Road] - our current service is hideous and we can't take it!!!!
Service Requests – Name Dropping, unique
requests, lots of feelings, etc.
▪At one point, we had been told that this address *does* actually have service, even
though it's outside the current zone, because it is next door to Jason Leifer's house,
and there was a little "island" there. I'm not sure if that's still true, but if it is, I'd be
eager to sign up! Otherwise, please let me know when service is available at our
address.
▪Is it possible to cat-proof the setup of the modem/router? We will have 2 cats...
▪anxious to get this installed
▪No
▪We realize that service isn’t available yet, but wanted to get on the list since it should
be soon.
▪When can I expect service to start
MIP Scoreboard – August 2026
As of September 10, 2026
291
DAYS TO GO
(<11 months)
131.6 miles to build
Municipal Infrastructure Program Grant must be completed by 6/30/27
MIP Scoreboard – August 2026
As of September 1, 2026
Months to go:
5.1
----------
147
(3.4%)
MIP Miles Completed*
206
----------
2,711
(7.6%)
# of Parcels Reached**
4
----------
470
(0.9%)
# of Unserved Reached
1
----------
74
(1.4%)
# of Underserved Reached
58
----------
400
(14.5%)
# of MIP Installs
10
--------
36
(27.8%)
44.1
----------
147
(30%)
MIP Miles Built
Project Highlights
Project Name:Dryden Fiber Expansion
for Towns of Dryden and Caroline
Applicant and Partner(s):Town of
Dryden dba, Dryden Fiber and Town of
Caroline
Construction Miles (Fiber): 147
Total Locations Served:2,711
ConnectALL Grant Amount: $ 11,641,537.00
Local Contribution: $ 906,321.00
Total Project Investment: $ 12,547,858.00
Easement Map
Green = Signed:47
Yellow = Accepted: 25
Red = Declined: 6
Gray = Actively Seeking: 172
Unique Neighborhoods: 46
•1 to 11 easements each (ave. 3.34)
•We will be tracking 'completed'
neighborhoods
Support Needed:
•Method to handle people who are
declining the easement
•Location of people we can't find (i.e.
LLC owned by someone outside of
Dryden or Tompkins or NY State)
•Outreach to people who are
undecided
•Brainstorming on Messaging and
Methods to communicate to property
owners (special sub-group session)
Easement Map
Green = Signed:75
Yellow = Accepted: 25
Red = Declined: 10
Gray = Actively Seeking: 101
Unique Neighborhoods: 46
•1 to 11 easements each (ave. 3.34)
•We will be tracking 'completed'
neighborhoods
Support Needed:
•Method to handle people who are
declining the easement
•Location of people we can't find (i.e.
LLC owned by someone outside of
Dryden or Tompkins or NY State)
•Outreach to people who are
undecided
•Brainstorming on Messaging and
Methods to communicate to property
owners (special sub-group session)
#1. Emailed 7/7; 7/8 (new email); 7/13 (reply); 7/14 (reply, scheduled); 7/15 signed! Note:
This person knew Cynthia from past experience
#5. DEC Land / Yellow Barn State Forest: April 30 to August 19 (2 site visits, multiple
applications, Temporary Revocable Permit (TRP),Concurrent Use and Occupancy
Agreement (CUOA); 9/10/26 - Redesign and reapplication process started
#14. No email, no phone, mailed, no reply; in-person: house empty, for sale, spoke to
realtor, spoke to executor (brother), emailed easement, requested legal paperwork as
executor
#28. Yes! Definitely (Verbally); but didn't want to have to sign; but later did
#36. June 29 email; June 30 scheduled (no notary / holiday week); July 7 signed
#42. Work around parcel due to home sale; 30+ day deliberation; then wanted bank loan
provider permission; waiting for them to come in
#59. Prospect in rural area, six signers on trust, located in 3 states, lots of mailing
#71. No email, No phone response; in-person, in-person, vacay, truck fire, came in
#96. Happens to be 96 years old, no phone or email, package in mail, in-person, came to
town hall with spouse to sign
Easements Acquisition – First 106 Processed
August 2026 (10 declines, 96 accepted)
NYDOT Permits
We've applied for 16 NYDOT Permits
15 (+4) have been granted!
1 is in process
These cover:
Route 13 (Hanshaw to Cortland)
Route 366 (Varna to Freeville)
Route 392 (E. Main and Virgil Road)
Route 38 (Harford to Groton)
Route 79 (Slaterville Road)
Route 34B (Peruville Road)
1.Parallel Runs
2.Aerial Road Crossings
3.Underground Road Crossings
Key Items:
Traffic Control Plans and Fiber Count
2026 Construction Plan (Gantt Chart) - As of September 11, 2026
Sep.Oct.Nov.Dec.Jan.Feb.Mar.Apr.May June
Freeville Expansion PARTIAL
HOLD
PARTIAL
HOLD
PARTIAL
HOLD
PARTIAL
HOLD BUILD BUILD LIVE LIVE LIVE LIVE
Greater Dryden PARTIAL
HOLD
PARTIAL
HOLD
PARTIAL
HOLD
PARTIAL
HOLD
PARTIAL
HOLD BUILD BUILD BUILD BUILD LIVE
Caroline MIP (5)PARTIAL
HOLD
PARTIAL
HOLD
PARTIAL
HOLD
PARTIAL
HOLD
PARTIAL
HOLD BUILD BUILD BUILD LIVE LIVE
Status Definitions
PARTIAL HOLD – Pole licensing, NY State Highway Permits, POP Server Upgrades, Easements,
network design/redesign:Vantage is directing construction (aerial, underground) to limited parts of
the map where we have permits,licenses, and easements. Splicing can be carried out under specific
direction.Some installs can happen.
BUILD - "Let it rip" - Construction partner has full access to licenses, permits, weather, inventory,
materials, and POPs are ready for activating parcels in small bunches. Installations continue.
LIVE – Residents in the zone can schedule and can have service installed.
▪Static IP Addresses – Business Tier Feature
o Current:
▪1 Static IP Address provided to each business account
▪No Static IP Addresses provided to residential accounts
▪Additional static IP Addresses sold for $40 per month for 5 static IP Addresses
o Proposed:
1 Static IP Address provided to each business account
No Static IP Addresses provided to residential accounts
Additional static IP Addresses sold for $10 per month for 1 static IP Address
Reason for Change:
We pay for static IP addresses and most requests and usage is for 2-3 total addresses, not 6
We are assigning 6 when they get the additional 5 pack, but many are unneeded
Previously we limited product expansion to tiers and 5 packs of Static IP for monthly on-going billing to keep
things simple
Policy Items
▪Property Owner Declination Letter (aka Red Zone Letter):
▪We reached out to you;you have declined, or have not agreed to, the requested easement.
▪Your parcel will not be included in Dryden Fiber's construction.
▪Your parcel will not be eligible to connect to Dryden Fiber.
▪A future connection will be at the property owner's expense.
▪Your parcel's status will be reflected on Dryden Fiber's public service-availability map.
▪“This parcel is not eligible for Dryden Fiber service through the primary construction project
because the required property access was not provided. Any future connection to the Dryden
Fiber network, if technically feasible, will be at the expense of the parcel owner.”
▪This designation will inform current and future property owners that the parcel was not included in the
primary network construction, and that additional construction and expense will be required before
service can be provided.
▪Declining an easement may also affect neighboring properties.
▪If you wish to reconsider, please respond within 30 days.
Policy Items
▪Customer Base – Matthew Kinast – Dryden Fiber Accounting
▪Finance – Amanda Anderson – Dryden Fiber Accounting
▪Customer Service - Netegrity
▪Sales Operations/MDUs - Conor Hans, Account Manager
▪Installations – Clarity Connect, Netegrity, Conor Hans, Account Manager
▪Easements – Exec. Dir. Dave Makar; Cynthia Brock
▪Legal – Dave Makar
▪Government Relations and Reseach – Dave Makar, Dan Lamb
Team Reports
Customer Base
As of September 1st, 2026 (billing date is 1st of month)
Speed
Number of
Subscriptions
Billed Monthly
Revenue
Net Change
from Prior
month
Average Monthly
Revenue
Residential
Silver ($45)400 Mbps 441 19,845 +10 / -2
Gold ($75)700 Mbps 78 5,850 3
Platinum ($90)1 Gbps 46 4,140 1
Total Residential Customers 565 29,835 12 52.81
Commercial
Standard ($75)500 Mbps 22 1,650 -2
Preferred ($150)1 Gbps 5 750
Enhanced ($250)2 Gbps 1 250
Total Commercial Customers 28 2,650 -2 94.64
Total of ALL Customers 593 32,485 54.78
0
200
400
600
800
1000
1200
1400
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
2026 Dryden Fiber - Customer Count
Projected Customer Count Actual Customer Count
Financial Reporting
as of August 31, 2026
Revenue and Expenses
2026 Budget and Actual
1-1 to 8-2026 2026 Budget Remainder
Revenue
Customer Subscriptions 237,660.00 461,950.00 224,290.00
MIP Grant Revenue 1,191,525.96 2,793,968.88 1,602,442.92
Other Revenue Sources 5,135.94 69,200.00 64,064.06
Total 1,434,321.90 3,325,118.88 1,890,796.98
Expenses
Construction 6,209,598.96 11,537,893.41 5,328,294.45
Installation 187,497.78 710,000.00 522,502.22
Operations 276,877.60 505,123.01 228,245.41
Total 6,673,974.34 12,753,016.42 6,079,042.08
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
2026 Budgeted and Actual Operating
Budgeted Expenses Actual Operating Exp Budgeted Revenue Actual Revenue
-
2,000.00
4,000.00
6,000.00
8,000.00
10,000.00
12,000.00
14,000.00
16,000.00
18,000.00
20,000.00
22,000.00
24,000.00
26,000.00
28,000.00
30,000.00
32,000.00
34,000.00
36,000.00
38,000.00
40,000.00
42,000.00
44,000.00
46,000.00
48,000.00
50,000.00
52,000.00
54,000.00
Sept 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 April 2026 May 2026 June 2026 July 2026 Aug 2026
Dryden Fiber Revenue and Operating Exp. - 12 months
Series3 Series1 Series2 Trend Operational Expenses
Customer Service
As of September 1st, 2026 (billing date is 1st of month)
Helpdesk Call Report August 2026
•Bandwidth Complaint (Speed Concerns)
•1
•Billing Related Call
•6
•Downed Drop (Damaged Service Line)
•0
•Email (Calls related to email difficulties)
•0
•No Connectivity
•4
•ONT / Power Cycle (Calls related to the
ONT where unplugging or rebooting
equipment was necessary)
•1
•Other / Unrelated (Calls looking for
unrelated departments or information)
•31
•Outage
•0
•Install Orders / Create Service
•21
•Router Issue
•5
•PC / Laptop Issue
•1
•Sporadic Connection
•0
•Streaming Related Issue
•0
•User Error / Education
•17
•Wireless
•7
Total Service Call Dispatches: 2
Tickets: 94 Customers: 593 June: 68/554 July: 196/567 Aug: 94/593
Ticket / Customer Ratio: 16%June: 12% July: 35% Aug: 16%
Note:
Install Orders denote an
incoming install scheduling
request – not a completed install
One caller can generate
numerous tickets for a single
issue (i.e. calls in 5x for same
problem)
Support@drydenfiber.com
607-391-3500 (direct support
number)
User Error / Education:
User Error / Education:
Service inquiry (non-green)
Hardware Q's
Range Extenders
Account Management – MDUs – Mobile Home Parks -As of: Sept. 1, 2026
Current
Task
Owner
MDU Name
And Zone (Green,
Yellow, Orange:
Could be)
Initial
Property
Owner
Outreach
Property
Owner
Paperwork
signed
Engineering
Design
Complete
Eng. Plan
approved by
property
owner
Construction
Scheduled
Construction
Completed
Residents
Notified
Unit
Count
NEXT STEPS
Acct.
Mgr
Ithaca Estates Yes Yes Yes Yes Yes Yes Yes 9 / 74 None at this time
Acct.
Mgr
Shady Grove
MHP
(Pinckney)
Yes No Yes Yes Yes Yes Yes 0 / 17 Conor: Acquire
access agreement.
Emailed property
owner to set up a
meeting(7/9/26)
Dave /
Acct.
Mgr
Mott Road
Mobile Home
Park
Yes Yes Yes No No No No 24 Dave: Call Reggie
Dave /
Acct.
Mgr
Fall Creek
Parke (Etna)
Yes Yes Yes Yes Yes Yes Yes 4/38 Live, installs
scheduled, door
hangers left
VPS –
plan
needed
Little Creek
MHP (North
Road)
Yes Yes;
however
new
signature
needed
No No No No No 100 Conor: Setup
meeting with park
owners after Fall
Creek Parke
Acct.
Mgr
County Acres
MHP
(McLean)
Yes No No No No No No 102 Dave: Follow-up
with owner /
manager; Vista
Management (Fall
Creek Rd./Rt. 366)
Current
Task
Owner
MDU Name
And Zone (Green,
Yellow, Orange:
Could be)
Initial
Property
Owner
Outreach
Property
Owner
Paperwork
signed
Engineering
Design
Complete
Eng. Plan
approved by
property
owner
Construction
Scheduled
Construction
Completed
Residents
Notified
Unit
Count
NEXT STEPS
Acct.
Mgr
Pleasant View
(Southworth
Rd.)
Yes Yes Yes Yes No No Yes 49 Property owner
signed agreement
Dave /
Acct.
Mgr
Country Manor
Estates (Wood
Rd.)
Yes No Yes No No No No 14 Karel Westerling's
property; Yellow
zone; plan created
Acct.
Mgr
Hanshaw
Village
(Hanshaw
Road)
Yes No; needs
engineeri
ng review
first
No No No No No 149 Dave: Follow-up
with Cook
properties
VPS Cook Street
(Freeville)
Yes No No No No No No 12+Dave: Follow-up on
engineering plan to
reach park
Acct.
Mgr
Hillside Acres*Yes No No No No No No 150+*Low priority, due to
not likely to be built
to until 2027 (Poles
potentially needed);
new owner
Account Management – MDUs – Mobile Home Parks -As of: Sept. 1, 2026
Current
Task
Owner
MDU Name Initial
Property
Owner
Outreach
Property
Owner
Paperwork
signed
Engineering
Design
Complete
Eng. Plan
approved
by property
owner
Construction
Scheduled
Construction
Completed
Residents
Notified
Unit
Count
Notes
Account
Manager
1062 Dryden
Rd. Apts.
(Varna)
Yes No Yes Meeting
Scheduled
No No No 21 Conor: finishing
touches needed on
agreement
Account
Manager
12-14-16
Lake Street
Yes Yes Yes Yes Yes No No 20 Agreement signed,
construction started
VPS Willow Brook
Apartments
Yes No No No No No No 50 Service via North
Rd (Rt. 13), State
Permit (Sept. '26)
VPS Willow Brook
Office Only
Yes No Service via North
Rd (Rt. 13), State
Permit (Sept. '26)
Account
Manager
194 Lower
Creek Road
(Apartments)
Yes No No No No No No 28 Conor, Eric:
outreach and
investigate
Account
Manager
Creekwood
Apartments
at 200 Lower
Creek Rd.
Yes No No No No No No 57 Conor, Eric:
outreach and
investigate
Account Management – MDUs – Apartments -As of: Sept. 1, 2026
Account Management – MDUs – Apartments -As of: Sept. 1, 2026
Current
Task
Owner
MDU Name Initial
Property
Owner
Outreach
Property
Owner
Paperwork
signed
Engineering
Design
Complete
Eng. Plan
approved
by property
owner
Construction
Scheduled
Construction
Completed
Residents
Notified
Unit
Count
Notes / Steps /
Blockers
Account
Manager
Freeville
Cottages
Yes Yes Yes Yes Yes Yes Yes 12 Conor: Marketing /
Outreach.
Doorhangers left
and postcards sent
Dave /
Account
Manager
George
Junior
Republic
Yes N/A (no
tenants)
Yes Yes Yes Yes Yes 1 Live!
Account
Manager
1279 Dryden
Road
(Wawak)
Yes No No, TBD
N/A
No No No No 18 After 1062 (Same
owner)
Account
Manager
1 Etna Lane Yes Yes Yes Yes Yes Yes Yes 3/16 Live!
Account Management – MDUs – Apartments -As of: Sept. 1, 2026
Current
Task
Owner
MDU Name Initial
Property
Owner
Outreach
Property
Owner
Paperwork
signed
Engineering
Design
Complete
Eng. Plan
approved
by property
owner
Construction
Scheduled
Construction
Completed
Residents
Notified
Unit
Count
Notes / Steps /
Blockers
Account
Manager
9 East Main Yes Yes Yes Yes Yes Yes Yes 1 Community Center
Account
Manager
2 East Main Yes Yes Yes Yes Yes No No 3 Agreement signed,
Construction
Started
Account
Manager
6 East Main Yes Yes Yes Yes Yes No No 7 Agreement signed,
construction started
Account
Manager
1 West Main Yes No Yes No No No No 9 Blocked by NY DOT
Permit (Rt. 13)
Account
Manager
8-10 West
Main
Yes No Yes No No No No 6-8 Blocked by NY DOT
Permit (Rt. 13)
Account
Manager
12-14-16
West Main
Yes No Yes No No No No 6 Blocked by NY DOT
Permit (Rt. 13)
Account
Manager
18-20-22
West Main
Yes No Yes No No No No 6 Blocked by NY DOT
Permit (Rt. 13)
Background
▪We have over 1,000 parcels between Dryden and Caroline where we have service requests
outside of the green zone
▪The blockers: NY DOT permits to connect their street; Calix upgrade; construction
▪The good news: MPT / MST locations identified or in-place for hundreds of these locations
▪We will begin "exterior" or "pre-installations" this month
▪Yellow Zone Roads with Requests (and known MPT locations)
▪Rt. 38N from Freeville, West Dryden Road, Peruville Road, Leisure Meadow, Cricket, Palmear
▪Outreach
▪Email to confirm with these future customers
▪Forwarded lists to Clarity Connect for exterior installations
▪Clarity to conduct by neighborhoods
▪Saves us time and winter underground construction hurdles
Pre-Installations
Pre-Installations
Status
▪Outreach Zones (Pilot)
▪Roads: Ocean Drive, Ed Hill, West Dryden Road, Peruville Road, Groton Road, Meadow Drive,Leisure
Lane, Cricket Lane, Palmear Road, Hile School Road
▪Service Requests: 43
▪Confirmation: 27
▪Not interested: 1
▪Maybe(asked for details): 1
▪No response: 14
▪Timing:
▪September 14 Week – Begin Pre-Installations
▪Outreach to next batch of 56 locations
▪Tracking:
▪Online Spreadsheet
Pre-Installations
o Construction
▪Empire Access Overlash Agreement (6 miles of fiber) – Approved by Town Board (9/10/26)
▪Easements: We're processing over 100 locations on -going
Operational
▪Dryden – Caroline IMA (Intermunicipal Agreement) for project – with Dryden Town Attorney
▪INHS Varna Project – with Executive Director
Legal Update
August 2026
o Research
▪Survey Project – Delayed due to easements project
Government Relations
▪“THE MUNICIPAL BROADBAND FINANCING MODERNIZATION IMPROVEMENT ACT OF 2026”
▪We will try again in 2027
Government Relations and Research
August 2026
APPENDIX A
o Total Addressable Market: 18,000 people; 7,200 households
▪Green Zone:1,815
▪Live:560
▪Green Zone Adoption: 31%
▪TAM Adoption: 8%
▪Signed Up: 1,560 22% of households
▪Wait List: 1,000 14% of all households; 18% of non-green zones
o Goal:
▪50% or 3,600 households (9,000 people)
▪15% of the way to the goal
Goals: Total Addressable Market
Discussion Topics
New Signs - February 2025
New Sign Requirements – MIP Grant
▪"This deployment of internet service is supported by a grant awarded to [insert Grantee name] by New York
State through the ConnectALL program.”
▪Example from Livingston County / Empire Access
Meeting Schedule
▪Dryden Fiber Public Broadband Committee – Public reporting on project
o 1st and 3rd Friday morning, 10:30am-11:30am (except July and August, 2nd and 4th
Friday morning)
▪Dryden Fiber Operations Team Meeting – Construction and Install Collaboration
o Every other Wednesday, 10am-11:15am
▪Dryden Fiber MIP Status Call – Meet with Connect All Office to stay on track
o Every Tuesday, 1pm-1:45pm
▪Dryden Fiber MIP Steering Committee – Implementation of the Grant
o Monthly (Town of Dryden, Town of Caroline)
▪Dryden Fiber Policy Committee – Advise and Recommend on Policy
o Monthly
Financial Reporting
Review of Construction Costs from beginning of project
Subcontractors (Syr. Util., Lghtspd, etc.), 50%Equipment Purchases, 28%
Professional Fees (Leg.,
Eng., etc.), 13%
Permit and Pole
Applications, 5%
Loan
interest,
2%
Misc
Constru
ction
Exp, 1%
Construction Costs 1/1/21 to 12/31/24
Subcontractors (Syr. Util., Lghtspd, etc.)
Equipment Purchases
Professional Fees (Leg., Eng., etc.)
Permit and Pole Applications
Loan interest
Misc Construction Exp
Permitting Steps
1.Final Design Edits = Survey has occurred and Prelim in is design edits
2.Prelim Sent = Sent to Engineering Firm (VPS) to review/approve and then to NYSEG/Frontier to review
3.Final NYSEG Design Sent = NYSEG reviewing final design before sending the Final Make Ready Package
4.Telco Recon = Telco Review prelim design
5.Frontier Billing Outstanding = Frontier awaiting payment to proceed
6.RFB = Request for Bid sent to contractors
7.MR Construction = Make Ready Contruction - Moves are in progress
Other Statuses (from slide 8):
▪Attached – definition...
▪Elec make-ready in process – definition...
▪Telco make-ready in process – definition...
▪Final ELEC Design Input – definition...
▪Avant Grid is NYSEG
Permitting Map Colors
1.Green = Conditional license to attach
2.Yellow = non-billable quote approved, quotes back from electrician sub-
contractors (i.e. HRS, Davella), when NYSEG gives ok, this moves to Green
3.Red = Design submitted to joint pole owner
4.Orange = make ready work package approved, heading to bid
5.Pink = out for make ready construction
6.Purple = design input (LaBella)