HomeMy WebLinkAboutBC 2025-12-19 ApprovedTown of Dryden
Broadband Committee Meeting
Friday, December 19, 2025 – Via Zoom
Approved Minutes
Attendees
Graham Dobson – Broadband Committee
Tony Salerno – Broadband Committee
Joel Cisne – Broadband Committee
Arthur Sommer – Broadband Committee
Dan Lamb – Town of Dryden Deputy Supervisor
Brad Penney – Vantage Point Solutions – Project Engineer
Shawn Scorzelli – Syracuse Utilities
Scott Brennan – Netegrity
Dave Makar – Dryden Fiber Executive Director
Amanda Anderson – Director of Finance and Personnel
Cassie Byrnes – Confidential Secretary to the Town Supervisor
Matt Kinast – Accounting Assistant
Ray Burger – Planning Director
Dave Makar called the meeting to order at 10:33am.
Second of 2 Monthly Meetings – Discussion Meeting
Introductions – Dave Makar
D Lamb read the Dryden Fiber Mission Statement aloud: “Our mission is to provide reliable, affordable,
high-speed, fiber-based internet access. We offer state-of-the-art technology and unmatched
customer service.”
• D Makar explained that there have been suggestions regarding the “fiber-based” aspect of our
mission, involving bringing service to MDUs. Currently, the engineering for MDUs has been
problematic in that getting Dryden Fiber to each unit can be challenging (up to 7 other
existing utilities are already on the ground). The suggestions include putting in a tower at the
Mobile Home Park and broadcast fixed wireless to the individual units. While this is a
possibility, and would be cost-effective, it does not follow our mission of “fiber-based internet
access.” We are going to hold off on this suggestion for now.
Municipal Infrastructure Program Update – Dave Makar
The $11.64M Grant Disbursement Agreement (GDA) has now been signed and counter-signed
between New York State’s Empire State Development ConnectALL Office (ESD, CAO) and the Town of
Dryden (on behalf of the Town of Dryden and the Town of Caroline). We can now start to request
reimbursement funds for the project. Over the next 13 months, we will construct over 140 miles of
fiber (90% aerial and 10% underground) in the two towns.
• The first part of this construction was awarded to Syracuse Utilities in September, and the
second part was posted for bid on Friday, December 12 with an aim to be awarded in early
January. The third part, which covers the Town of Caroline, will be posted in early January and
awarded in February.
• We are aiming to have 100% of electrical make ready complete across both towns by May 1st.
GDA Payment Milestones
Milestone #1: The signed GDA allows Dryden Fiber to submit their first milestone, which requires us to
have network design, construction documents, pole attachment applications, and purchase orders for
procured items. It also requires all engineering across the entire 147 miles to be completed.
• We believe we have completed all the steps required to submit this milestone request. The first
reimbursement will be about $2M.
• A Anderson added that accounting documents are being prepared for submission once
engineering work is complete.
• D Makar explained that the state has allowed us to get started on the reimbursement request
details in advance of having the GDA signed, with a pencil review process already underway.
Milestone #2: Requires 30% fiber installed and spliced (44 miles).
Milestone #3: Requires 75% fiber installed and spliced (110 miles).
Milestone #4: Requires 100% fiber installed and spliced (147 miles) and before 12/31/2026.
Estimated Schedules
Project 1 – Freeville Expansion (28.53 miles)
• Awarded in September / Start date in December / End date of 3/31/26 (60 business days)
Project 2 – Greater Dryden (106.51 miles)
• Award in January / Start in February / End date of 7/31/26 (120 business days)
Project 3 – Caroline MIP
• Award in February / Start in March / End date of 8/31/26 (120 business days)
Potential Blockers
1. Electrical Make Ready (EMR)
a. Receiving provisional licenses to attach to poles (there is a gap between verbal
commitments and actual progress with NYSEG)
b. Having enough 25 KVA Transformers to complete the EMR packages (NYSEG is
requiring 10 KVA Transformers to be replaced with 25 KVA Transformers)
2. Weather
a. Long winter (cold, icy, windy)
b. Long rainy mud season
3. Issues with Acquiring Equipment / Materials
a. Fiber
b. Strand
c. Handholes
d. MSTs
e. Other material
4. Right-of-Way Resistance
a. NYSDOT permits
b. NYSEG easements
Freeville Expansion Update
S Scorzelli of Syracuse Utilities reported that underground work is complete (just waiting on
permitting for a few locations) and aerial installation of anchors and strands is ongoing.
D Makar announced the start of weekly Monday morning calls with Dryden Fiber, Syracuse Utilities,
and Vantage to monitor progress, with a commitment to hold meetings every seven days for the next
three months.
Plume Updates – Dave Makar
In 2021, the Town of Dryden signed a 10-year contract with Plume to provide cloud services for our
Wi-Fi devices. At that time, there was a very optimistic construction timeline put together for the
project, where they believed the project would already be completed and there would be 2,500-3,000
customers (we currently only have 500 customers). Every 6 months, the cost for Plume is increased, no
matter how many customers we have, per the contract. The rate has increased from the beginning
$500 per month to the now $2,250 per month. D Makar and the Town Attorney negotiated with Plume
and agreed to a new 3-year contract with a reset of the monthly rate to $744 per month beginning
January 1. The contract still has a rate increase every 6 months, but it is now more aligned with our
new construction plan. This revised contract will save Dryden Fiber around $60,000 over the first 3
years of the change.
Fiber to the Premises (FTTP) OLT / ONT Agreement – Dave Makar
At their meeting on December 18, 2025, the Town Board voted to award the FTTP bid to Calix. Calix
runs on DC power, whereas Ciena runs on AC power. The current PoPs are all AC power.
S Brennan of Netegrity explained the technical requirements and existing plans for DC power
installation and explained that each PoP and the Central Office (CO) need a DC power plant installed
(a piece of equipment that mounts in the rack) to accommodate Calix equipment.
T Salerno raised concerns that the DC power conversion costs should have been included in the
original Calix discussion. D Makar noted that the estimates were low enough not to block the switch
and S Brennan added that the Town discussed DC power at some point because it is already in some
of the inventory plans.
IP Address Needs for 2026 – Scott Brennan
We currently have 521 customers on the system, with 521 IP addresses being used. The Town
originally purchased a /22 (a little over 1,000 IP addresses) at auction, with some being sub-netted out
for the server and network equipment and others going to the customers.
S Brennan presented options for IPv4 address management, explaining that as we grow, we need to
either:
1. Leave it the way it is, set up CGNAT on the network for IPv4 only, and hand out IPv6 addresses
and private CGNAT addresses to the customers. This option would create double NAT issues
affecting services like online gaming and VPNs.
2. Purchase more public IPv4 addresses and provide IPv4 and IPv6 addresses to the customers
(this is called a dual stack).
The current cost for a /21 (2,048 addresses) is $49,152 and for a /20 (4,096 addresses) is $94,208. If
Dryden Fiber ends up not needing all these addresses, they can turn around and re-sell them.
The committee discussed purchasing additional IPv4 addresses (either a /21 or a /20) to support
Dryden Fiber’s growth. After discussing the needs for 2026, D Makar proposed moving forward with a
motion to recommend to the Town Board that they approve the purchase of additional IPv4
addresses.
Motion: T Salerno made a motion to recommend to the Town Board that they approve the
purchase of a /20 block of IPv4 addresses at auction, at an amount not to exceed $125,000.
Second: G Dobson
With no opposition or abstention, the motion was approved and will be sent to the Town
Board for consideration at their meeting on January 8, 2026.
Upcoming Topics – Dave Makar
Reporting Meeting on December 2025 Business: Friday, January 16, 2026
Organizational Meeting for Dryden Fiber: Friday, January 23, 2026
Dryden Fiber Annual Budget Meeting: Friday, February 20, 2026
MDUs: Apartment Buildings, Mobile Home Parks, Mixed-Use Buildings: March 20, 2026
Marketing: Semi-Annual Update and Assessment: April 17, 2026
Discussion Items – Dave Makar
The Caroline Hut arrived and was installed this week.
A Anderson shared that the Account Manager position was posted on the Civil Service website and
she encouraged everyone to share the link.
The meeting adjourned at 12:01pm
Respectfully submitted,
Cassie Byrnes
Confidential Secretary to the Town Supervisor