HomeMy WebLinkAboutBC 2024-08-09Town of Dryden Broadband Committee Meeting Friday, August 9, 2024 – Via Zoom Approved Minutes Attendees Graham Dobson – Broadband Committee Tony Salerno – Broadband Committee Mark Wilson – Broadband Committee Jason Leifer – Town Board Dan Lamb – Town Board Tracy Monell – Gleamon Technology Ryan Garrison – HUNT EAS Eric Beckhorn – Clarity Connect Dave Makar – Executive Director Amanda Anderson – Bookkeeper Cassie Byrnes – Confidential Secretary to the Town Supervisor Ray Burger – Planning Director Doug Schneider – Cortland Standard Dave Makar called the meeting to order at 10:32am. Executive Summary (Month of July) – Dave Makar • Construction continues to move strongly across multiple fronts across the Town (Village of Dryden, Village of Freeville, parts of Ferguson Road, and Yellow Barn neighborhoods) • Added new locations/homes/parcels including the Villages of Dryden and Freeville • By the end of summer (September 21st) we’ll end up doubling the number of parcels that we had at the beginning of summer • We are now at 565 parcels (about 748 households) • We have 66 paying customers (14 added in July) making it our biggest month since we started • We had 65 inbound requests in June and 33 green zone requests in July • We have 27 customers in the installation queue for the month of August • We are now estimating: o 100 customers by September 1st o 100+ customers by the end of summer (September 21st) o 200 customers by the end of the year (near break-even) o 500 customers by the end of 2025 ConnectALL MIP Grant Project Highlights – Dave Makar • The teams from Dryden, Caroline, Dryden Fiber, and HUNT have been working closely with the ConnectALL Office on implementation of the grant • We now have about 28 months left on the schedule and we are making progress • For the next 2 ½ years, the main thing we will be working on is the implementation of this grant, reaching the unserved and underserved across the Town of Dryden, and then into the Town of Caroline (this will make our service more sustainable in the long run by adding these 1,200 additional homes) Meeting Schedule – Dave Makar • Dryden Fiber Public Broadband Committee – 1st and 3rd Friday of each month at 10:30am • Dryden Fiber Operations Team Meeting – Every other Wednesday at 10:00am o Focus on construction and installation collaboration • Dryden Fiber MIP Status Call – Every Tuesday at 1:00pm o Teams from Town of Dryden, Dryden Fiber, Town of Caroline, and the ConnectALL Office meet to stay on top of the MIP project • Dryden Fiber MIP Steering Committee – Monthly o Internal team from Town of Dryden, Town of Caroline, and Dryden Fiber meet to make sure we are going in the right direction over the next 2 ½ years • Dryden Fiber Policy Subcommittee – Monthly o Members from the Public Broadband Committee as well as some of our vendors meet to advise and recommend on policy Team Reports • Customer Base – Amanda Anderson o Consistent in terms of this report o Residential Platinum shows a +1/-1 resulting from a customer that moved but somebody moved into that house and got service o We ended up with 14 installations, 13 new billings for the month of August o Dan Lamb asked if our revenue stream is paid electronically and if there has been any problem with it?  Amanda Anderson answered that pretty much everybody is automatically signing up for automatic payments; There are a couple that aren’t getting their first emails, but set up automatic payments once they get into the email; No customers are mailing a check at this time; We are not charging the additional percentage to cover the credit card fees to encourage our customers to sign up for automatic payments (we currently pay about $100 per month in credit card and ACH fees, and this will go up as we add more customers because it’s based on the amount of money being charged); This saves a lot of administrative time by not having to process cash or checks • Construction Permitting Updates – Ryan Garrison o NYSDOT Permits – The only one we have out there is a county permit o Pole Applications  DRY001-DRY003 are in the process of closing out with NYSEG  DRY004 got pushed back because of the storm and they are estimating completion by the end of next week (Etna area, Lower Creek Road, and Upper Creek Road)  DRY005 was completed and we are going to begin to get our cable up (Caswell Road)  DRY010 is estimated to be completed by the end of this month (North Road and State Route 13 where the Empire Overlash ends)  DRY012 is awaiting non-billable make ready approval, so we will see that getting done in September/October (State Route 366 from Freeville to Route 13, parts of Dryden Road and Turkey Hill Road)  Other applications are waiting on packages or waiting on NYSEG approval  Graham Dobson asked, “When will we have to start for the MIP Project, or when will we start submitting for those?” • Ryan Garrison answered that we have already submitted everything to LaBella for OneTouch on Phase 2 (everything in the south half of Dryden), and we’ve got the majority of Caroline complete and ready to submit (planning on doing this by the end of the month) • Construction Implementation Updates – Ryan Garrison o About 167 parcels were added this month (estimated at about 137 households) which brings us up to 10% coverage on parcels and 12.9% coverage on households o We have 15 aerial miles that happened in 60 days o We have 22.5 miles of underground work that occurred over the last year/18 months/24 months o The Village of Freeville is nearing completion with Main Street and Groton Avenue scheduled to be finished next week o The Village of Dryden is 50% activated and we are working to get this near 100% by the end of the summer (we need to work with Graybar on getting materials) o Underground work was completed at Applewood Lane, Wellsley Drive, and Tannery Circle o Underground is in progress on Penny Lane and Logans Run o Underground work will continue on Greystone Drive, Hilton Road, Goodrich Way, Scenic Way, Chelsey Circle, Bear Circle, and Hanford Drive o Amanda Anderson asked if she should be sending construction postcards to any of these locations?  Ryan Garrison answered yes for Penny, Logans, Greystone, Hilton, Goodrich, Scenic, Chelsey, Bear, and Hanford • Construction Update – Ryan Garrison o Village Buildout – The South Backbone and the Empire Overlash will be green, but we are waiting on closures o Phase 2 Expansion follows the pole applications • Installations – Eric Beckhorn o Number of installations completed this month: 14 o Number of installations pending (as of July 31st): 27 o Installation blockers: 1 (15 Main Street – Eric Beckhorn will go out there today to see what needs to be done) o Tony Salerno asked, “What is the standard timeframe, if an area is green and I request service, for the service to actually be installed?”  Dave Makar answered that it is around 2 weeks now that we’ve increased the number of installs being done per day (Clarity used to only do one per day); Clarity is very efficient and can do 4-6 installations per day; Clarity will be able to get more people to do installs if needed • Finance – Capital Project – Amanda Anderson o No new inflows of interest o We had a big subcontractor bill that came through in July • Finance – Operations – Amanda Anderson o A line was added in July for the outage credits that were taken for July invoices; Because of the outage in May, the credit was applied in June, but most of those credits were not accepted until July o Accounts payable continues to stay steady at around $14,000-$15,000 o Accounts receivable is at $180 from new customers in July o Total parcels available (7/31) was 565; Total addresses served by 7/31 (total customers) is 66 o There will be a big jump in revenue coming in next month • Finance – Operations – Dave Makar o Difference of expenses to revenue = $10,945.00 o Income per customer = $56.29 ($56 flat number) o Customer count = As we add more customers at the $56 per customer, income increases, and the break-even point is estimated at 262 customers right now; Once we pass the break-even point, the difference can go back into funding the construction costs month after month • Sales Operations – Tracy Monell o Ray Burger sent a list of all the trailer parks in the Town, and Tracy Monell is working on getting landlord agreements signed o We now have 9 signed landlord agreements and 10 more waiting to be signed o We have 36 commercial sales possibilities, and all have been contacted o We have 14 new installations and 27 pending installations o Had conversations with Dryden School District and George Junior; Both are interested but already have commitments with other providers o Contacted the owners of a new apartment complex that is under construction on Dryden Road, and they are making arrangements for our service o Some potential customers have asked about cables coming into their buildings (aerial); The Policy Committee will discuss aerial vs. underground construction • Customer Service – Dave Makar o 33 install orders (green zone orders) o 2 reports of “No Connectivity”  Dave Makar will ask Andrew Hafner to do a “Downtime Report” for the previous month as well as see if anyone reported an outage • Marketing (as of August 1st) – Dave Makar o Under contract = 66 (12 new) o Requests in July = 58  27 of these requests were available (in the green zone)  Serviceable Live = 48% (66/137) o We continue to see strong website visits (users, new users, total sessions) o June and July were heavy public relations months (11 media hits, 2 TV interviews) o Social media postings consistent throughout July o “Coming Soon / Construction” postcards (ongoing as we have new parcels go live) o Next up = signs in the new neighborhoods, email marketing, swag Reminders • Our next meeting is Friday, August 23rd at 10:30am The meeting adjourned at 11:39am. Respectfully submitted, Cassie Byrnes Confidential Secretary to the Town Supervisor DRYDEN FIBER MID-MONTH REPORT AUGUST 2024 TOWN OF DRYDEN BOARD MEETING AUGUST 15th, 2024 EXECUTIVE SUMMARY ▪Construction Updates: o Massive Expansion coming in the next 60 days: Village of Dryden; Village of Freeville; this will double the number of homes with access to Dryden Fiber (By September 21st, 2024) ▪We are now able to serve 565 parcels o We are now able to serve 748 households (apartments; mobile homes) ▪We have 66 paying customers (+14 in July);We had 65 in-bound requests in June; 33 green zone in July ▪We have 27 customers in the installation queue for this month (Aug 2024) ▪We estimate 100 total customers by Sept 1, 2024 ▪Dave is estimating 100+ customers by the "end of summer" (9/21/24) o 200 by end of year (near break-even) o 500 by end of 2025 Municipal Infrastructure Program Grant ▪Key Discussion Topics (between Dryden Fiber Steering Committee and CAO): o Finishing Phase 3 pole applications (estimated completion date 8/23/24) o Location data reporting of "Now Available" and "Subscribed" addresses o Review actions, decisions, risks, schedule, licenses, and permitting ▪Accomplishments o Survey of Caroline POP sites o Began Design Development on MIP Phase 2 routes ▪Wins: o We believe 4 of the 2,673 addresses are now live with Dryden Fiber o These are the first 4 in the entire state of New York where installation is covered by MIP  Project Highlights Project Name:Dryden Fiber Expansion for Towns of Dryden and Caroline Applicant and Partner(s):Town of Dryden dba, Dryden Fiber and Town of Caroline Construction Miles (Fiber): 124.6 Total Locations Served:2,674 ConnectALL Grant Amount:$ 8,995,979.00 Local Contribution:$ 906,321.00 Total Project Investment: $9,902,300.00  Difference Monthly Expense Income Customers Income per customer $(10,945.00)$14,660.00 $3,715.00 66 $56.29 $(10,460.00)$14,660.00 $4,200.00 75 $56.00 $(9,060.00)$14,660.00 $5,600.00 100 $56.00 $(6,260.00)$14,660.00 $8,400.00 150 $56.00 $(3,460.00)$14,660.00 $11,200.00 200 $56.00 $(660.00)$14,660.00 $14,000.00 250 $56.00 $(380.00)$14,660.00 $14,280.00 255 $56.00 $(100.00)$14,660.00 $14,560.00 260 $56.00 $12.00 $14,660.00 $14,672.00 262 $56.00 $180.00 $14,660.00 $14,840.00 265 $56.00 $2,140.00 $14,660.00 $16,800.00 300 $56.00 $4,940.00 $14,660.00 $19,600.00 350 $56.00 $7,740.00 $14,660.00 $22,400.00 400 $56.00 Finance -Operations As of July 31, 2024 Appendix A Team Reports Team Reports ▪Customer Base – Amanda, Town of Dryden Bookkeeper ▪Construction Permitting Updates – Hunt Engineering ▪Construction Implementation Updates – Hunt,Syracuse Utilities,Lightspeed ▪Installations – Clarity Connect, Netegrity, Gleamon ▪Sales Operations – Gleamon ▪Finance – Amanda,Town of Dryden Bookkeeper ▪Customer Service - Netegrity ▪Marketing – Exec. Dir. Dave Makar Customer Base As of August 1st, 2024 (billing date is 1st of month) Speed Number of subscriptions Billed Monthly Revenue Net Change from Prior Month Average Monthly Revenue Residential - Silver ($45)400 Mbps 50 $2,250 +11 - Gold ($75)700 Mbps 6 $450 +2 - Platinum ($90)1 Gbps 3 $270 +1/-1 59 $2,970 +13 $50.34 Commercial - Silver ($75)400 Mbps 5 $345 No Change - Gold ($150)700 Mbps 1 $150 No Change - Platinum ($250)1 Gbps 1 $250 No Change 7 $745 $106.43 Total 66 $3,715  Construction Permitting Updates As of August 1st, 2024 ▪NYDOT: Total Permits: 21 o 20 Issued Permits (+1 for this month) o 1 Permits under review awaiting approval o 0 Permits pending either drawings or survey ▪Utility Pole Permits Application Name Status ECD Location DRY001 Attached Complete Freeville (V) DRY002 Attached Complete Dryden (V) DRY003 Attached Complete Dryden (V) DRY004 EMR in construction 8/14/2024 Etna Area DRY005 EMR Complete 8/7/2024 Caswell Rd. DRY006 Awaiting NYSEG approval of Non-Billable EMR 11/30/2024 Bone Plain Rd. DRY007 Waiting on EMR Package 10/30/2024 SR 38 North DRY008 Awaiting NYSEG approval of Non-Billable EMR 11/30/2024 Peruville Rd DRY009 Waiting on EMR Package 10/30/2024 Fall Creek &Ed Hill Rd DRY010 EMR in construction 8/31/2024 North Rd &SR 13 North DRY011 Awaiting NYSEG approval of Non-Billable EMR 11/30/2024 Gulf Hill, Sweetland &Bradshaw Rd DRY012 Awaiting NYSEG approval of Non-Billable EMR 9/30/2024 SR 366,Dryden Rd &Turkey Hill Rd  ▪Freeville is nearing completion with Main Street and Groton Ave scheduled to be finished next week. ▪Village of Dryden is 50% activated and are working to get this near 100% activated by the end of the summer. ▪Underground was completed at Applewood,Wellsley,& Tannery Circle. ▪The underground is in progress on Penny Lane/Logan's Run, ▪Underground work will continue on Greystone Dr,Hilton, Goodrich, Scenic Way, Chelsey Cir, Bear Cir. and Hanford Dr. Construction Implementation Updates As of August 1st, 2024 Coverage Parcels Households New (June 2024)+167 +138 Total w/ coverage 590 775 (est.) Total 5,839 6,036 Coverage %7.25% (+2.84%)12.9% (+2.2%) New Fiber Aerial Underground New (June 2024)+0 miles +2.25 miles Total 15 miles 22.5 miles  Construction Update Route Name Status ECD Application#Notes Village Buildout South Backbone Complete 8/1/2024 DRY002 MR Complete, Strand complete, Cabling this week. Village of Freeville (Empire Overlash Inc.)40% Complete, Splicing 8/31/2024 DRY001 60% Live, finishing Rt 366. Village of Dryden Aerial 50% Complete, Splicing 7/14/2024 DRY002,003 25% Live, Splicing Continues Village of Dryden Underground*60% complete, Line work and splicing 9/14/2024 Underground Applewood and Wellsley complete. . Phase 2 Expansion Lower Creek Rd Electrical MR Construction in process.8/14/2024 DRY004 HRS is scheduled for electrical MR construction in July. Tompkins County Recovery Fund Electrical MR Construction complete on DRY005 and DRY006 is pending NYSEG Approval of MR Costs. 9/14/2024 DRY005, 006 HRS projects electrical MR construction in July/August. West Dryden Rd Pending NYSEG Approval of make ready costs. 10/31/2024 DRY007 App in process. Rt. 38 North Pending NYSEG Approval of make ready costs. 11/31/2024 DRY007 Bidding Peruville Rd Pending NYSEG Approval of make ready costs. 11/31/2024 DRY008 App in process. Fall Creek Rd/ Ed Hill Rd/Telco Design 12/31/2024 DRY009 App in process. West Mallory Rd/ Morris Rd Telco Design 12/31/2024 DRY009 App in process. North Rd/ Dutcher Rd Telco Design 9/31/2024 DRY010 Bidding Gulf Hill Rd./ Sweetland Rd Telco Design 12/31/2024 DRY011 App in process. Rt. 366 (Freeville to Rt. 13)Electrical MR Construction in process.10/31/2024 DRY012 HRS projects electrical MR construction in July/August. Installations As of August 1st, 2024 (billing date is 1st of month) ▪June Install Summary o Number of installations completed this month:14 o Number of installations pending (as of July 31st): 27 o Installation blockers / questions:1  Finance – Capital Project As of July 31, 2024 Balance Sheet as of 7/31/2024 2024 Year to Date Total Project to Date Project Budget Assets - Cash 764,751.40 Inflows 123,547.83 1,509,474,96 - Due from Grants 624,614.00 Expenses - Acct Receivable 197,309.19 Professional Fees 332,685.86 790,696.68 Total Assets 1,586,674.59 Incidental Const. Exp 3,764.73 70,055.83 Equipment Purchases 138,210.13 2,019,595.56 Liabilities and Equity Subcontractor Costs 566,264.38 2,988,850.64 - Bond Anticipation Note 5,840,000.00 Pole and Permit Cost 352,514.42 932,480.82 Equity -4,253,325.41 Interest Payment 146,840.97 168,641.73 Total 1,586,674.59 Total Expenses 1,540,280.49 6,961,321.26 14,535,281.00 Budget Remaining 7,573,959.74 52.1%  Finance -Operations As of July 31, 2024 July 2024 Year to Date Residential 2,415.00 11,884.50 Balances as of 7/31/24 Commercial 700.00 5,460.00 Accounts Receivable 180.00 Misc Fees 885.00 Accounts Payable 10,870.34 Outage Credit -1,242.50 -1,242.50 Total Revenue 1,872.50 16,897.00 Expenses Parcels Serviceable 6/30 425 Credit Card Fees 176.32 1,019.97 + New Parcels added in July 140 Billing Program -2,320.92 Total Parcels available 7/31 565 Utilites 6,079.67 55,861.95 *does not include MDUs Subscriptions 8,405.60 55,776.77 Total Addressed Served by 7/31 66 Insurance 303.28 303.28 Total Expenses 14,660.91 115,281.89 Profit/Deficit -12,788.41 -98,384.89 Sales Operations As of August 1, 2024 (billing date is 1st of month) ▪Multi-Use Development –working on getting agreements with Mobile home parks throughout the town ▪Renters – We now have 9 signed agreements and 9 more waiting for signature ▪Commercial Sales - 36 possibilities and all have been contacted. ▪Prospects-We have 14 new installs and 27 pending. Also 14 potentials that have signed up and contact has been made. These include 3 in the Ithaca Estates mobile home park and the 2 for the Town ▪Had conversation with Dryden School District and George Junior.Both are interested but have already made commitments to current providers ▪Made contact with owners of new apartment complex that is under construction on Dryden Rd.They are making arangements to have our service Customer Service As of August 1st, 2024 (billing date is 1st of month) Helpdesk Call Report July 2024 •Bandwidth Complaint (Speed Concerns) •1 •Billing Related Call •15 •Downed Drop (Damaged Service Line) •0 •Email (Calls related to email difficulties) •0 •No Connectivity •2 •ONT / Power Cycle (Calls related to the ONT where unplugging or rebooting equipment was necessary) •1 •Other / Unrelated (Calls looking for unrelated departments or information) •42 •Outage •1 •Install Orders / Create Service •33 •Router Issue •1 •PC / Laptop Issue •0 •Sporadic Connection •0 •Streaming Related Issue •0 •User Error / Education •6 •Wireless •2 Sum: 104 Note: Install Orders denote an incoming install scheduling request – not a completed install One caller can generate numerous tickets for a single issue (i.e. calls in 5x for same problem)  Marketing As of August 1st, 2024 (billing date is 1st of month) 8/10 9/8 10/5 11/2 12/1 1/1/24 2/1/24 3/1/2 4 4/1/2 4 5/1/2 4 6/1/24 7/2/2 4 8/1/2 4 Under Contract 8 22 26 32 28 28 29 (+3, -2) 32 (+3) 37 (+5) 40 (+3) 44 (+6,-2) 54 (+10) 66 (+12) Requests (since 1/1/23) 150 174 (+11) 230 (+21) 252 (clean - up) 274 (+9) 298 (+24) 332 (+13) 363 (+31) 389 (+26) 409 (+20) 429 (+20) 494 (+65) 552 (+58) Available 30 38 41 43 44**44 56 TBD TBD 75 87 110 (+23) 137 (+27) Not Available 120 136 189 209 226 250 276 TBD TBD 340~342 384 415 Serviceable Live 76.7 % 76.3%80.5%83.7%72%63.6%51.8%TBD TBD 40/70 51% (44/87) 49% 54/110 48% 66/137 Website Visits 8/25-9/7 9/22-10/4 10/21-11/2 11/17- 11/30 12/1- 12/31 1/1-1/31 2/1- 2/29 3/1- 3/31 4/1- 4/30 5/1- 5/31 6/1- 6/30 7/1- 7/31 Users N/A 226 193 161 140 320 484 392 403 368 516 820 935 New Users N/A 211 170 137 115 288 424 346 353 315 471 755 868 Sessions N/A 324 271 515 194 448 673 617 706 601 739 1221 1373 Engagement (secs.) N/A 0m 46s 1m 09s 1m 10s 42s 1m 7s 1m 6s 1m 30s 1m 6s 53 s 58 s 1m 14 s 1m 3 s Marketing As of August 1st, 2024 (billing date is 1st of month) ▪June and July were a heavy Public Relations month o 11 media hits (through 7/11/24) o 2 tv interviews ▪Social Media postings o Facebook, Instagram, Nextdoor ▪Postcard outreach:"Construction / Coming Soon", "Now Available", "Business Class" (coming soon) ▪Next up: o Signs in the new neighborhoods (Spring Run, Dryden Village,Village of Freeville), refreshed design o Email Marketing o Swag (Hats, Truck Magnets, stickers) Appendix B Background and Definitions Meeting Schedule ▪Dryden Fiber Public Broadband Committee – Public reporting on project o 1st and 3rd Friday morning, 10:30am-11:30am (except July and August, 2nd and 4th Friday morning) ▪Dryden Fiber Operations Team Meeting – Construction and Install Collaboration o Every other Wednesday, 10am-11:15am ▪Dryden Fiber MIP Status Call – Meet with Connect All Office to stay on track o Every Tuesday, 1pm-1:45pm ▪Dryden Fiber MIP Steering Committee – Implementation of the Grant o Monthly (Town of Dryden, Town of Caroline) ▪Dryden Fiber Policy Committee – Advise and Recommend on Policy o Monthly Permitting NYSEG ▪Permitting Steps Permitting NYSDOT ▪Permitting Steps