HomeMy WebLinkAbout2021-07-26HUNTENGINEERS I ARCHITECTS I SURVEYORS Meeting Notes Date:7/23/2021 Present: Jason Leifer (Town of Dryden), Daniel Lamb (Town of Dryden), Ryan Garrison (Hunt EAS), Mark Wilson (Broadband Committee), Jeff Smith (Municipal Solutions), Tony Salerno (Broadband Committee), Ray Burger (Town of Dryden), Sam Bouabane (Broadband Committee) Absent: Karl Kolesnikoff (Broadband Committee), Mike Perehinec (Broadband Committee) From: Adam Monell (Hunt EAS) Project: Dryden FTTH Design Phase 1 Project No.: 1122.042 Re: Broadband Committee Meeting Summary: The following items were discussed during a Broadband Committee Meeting held on 23 July 2021. 1. Financials a. Review b. Ryan is working through the business model to flesh these things out 2. Schedule Updates a. Permit review with the DPW I. the Village and Town attorneys are looking over these documents and should be able to deliver their finding in a couple of weeks b. Equipment supply chain concerns i. Graybar has been diligently working to find fiber supplies and have found enough Commscope outside plant fiber to complete P1 of our project ii. Innerduct is the other critical item for the P1 and it looks like SU has about 65% of the total needed in stock and Graybar should be able to provide the balance 3. RFP Updates a. Equipment RFP responses have been received from Nokia, Calix, and Ciena b. Interview reviews L Ryan will be sending out some collected information and an updated Rubric ii. There will be instructions for participants to add their thoughts iii. We will resolve to have a decision by our next committee meeting 4. Marketing Plan HUNT ENGINEERS, ARCHITECTS, LAND SURVEYORS & LANDSCAPE ARCHITECT, DPC AIRPORT CORPORATE PARK, 100 HUNT CENTER, HORSEHEADS, NY 14845 T. 607.358-1000 F:607-358-1800 HUNT-EAS.COM HUNTENGINEERS I ARCHITECTS I SURVEYORS a. Strategy -we really should look at what this plan is moving forward. We are much closer to beginning construction and should start talking about this plan. b. Public Outreach for Village of Dryden I. Hunt can compile 1. An email list from the survey data 2. A mailing list from the GIS data ii. We should collect our survey data email responses and utilize the Town's existing Mail Chimp service to send this out iii. Ryan proposing a GIS Map to show folks where service is available or coming iv. Ryan and team can work on some talking points to share with the community v. As the project develops we may want to consider additional scope to provide some sort of leave behind to be distributed from the Town Hall 5. Website a. Recommendations or updates from the subcommittee b. Implementation Strategy i. Logo - ii. What is the message that we want to convey to the Town iii. This should be a priority as we need to provide a place where we can get information about the project out to the community 6. Legal a. Dryden's Utility Easement review Village Roads & Rail Trail b. NYSEG Agreement c. Properties — Town Hall, Pinckney Rd, Splitter cabinet in Freeville 7. Additional Items 8. Next Committee Meeting August 6`h, 2021 @ 10:30am. HUNTENGINEERS, ARCHITECTS, LAND SURVEYORS & LANDSCAPE ARCHITECT, DPC AIRPORT CORPORATE PARK, 100 HUNT CENTER, HORSEHEADS, NY 14845 T. 607-358-1000 F: 607-358-1800 HUNT-EAS.COM