HomeMy WebLinkAbout23 05 12-1.1 Fan Submittal, CORRECTIONS NOTED, PROCEED
Taitem Engineering PC
ENERGY STAR MFHR
Submittal Review
Approved
Approved As Noted
Revise and Resubmit
Rejected
No Review Required
This review only covers the requirements
related to the ENERGY STAR Multifamily
High Rise Program and associated energy
savings.
By: Date:
Evan Hallas 10/13/2020
As requested in original submittal review, thefollowing wills till need to be provided. Seesubsequent submittal request by Vecino:-Provide wall mounted speed controller for EF-2-Provide motorized make-up air damper for EF-2 thatmeets IECC air leakage requirements, installed atexterior wall, and linked to EF-2 operation
Installation notes:-Radiation damper to be air sealed to EF-1 exhaustfan. EF-1/radiation damper to be air sealed to drywall.