Loading...
HomeMy WebLinkAbout03_RFI Question_Response Worksheet_Self-Pricing_HANS BETHEPROJECT:WEST CAMPUS DINING EXHAUST- PART 1 HANS BETHE HOUSE DATE: July 13, 2018 RFI Form RFI/ Response Index 1 The timeline of 2 weeks is condensed and some work may take longer to get than 2 weeks, such as signage. Cornell may increase the scheduled days to accomodate critical path items to facilitate the kitchen operations that require code compliance. Additionally, longer lead items that are not required for code compliance, that do not impact substantial completion and testing may occur beyond the construction window of August 3rd, however they shall be done timely (within 60 days of substantial completion). 2 3 4 5 RFI Project Team Response