HomeMy WebLinkAboutAddendum No. 2_2-2-2021CORNELL UNIVERSITY LOW RISE 9 CERTIFICATE OF OCCUPANCY FACILITIES CONTRACTS ENABLING & HEATER REPLACEMENTS 121 HUMPHREYS SERVICE BUILDING ITHACA, NEW YORK 14853-3701 ADDENDUM NO. 2 February 2, 2021 This Addendum contains changes to the requirements of the Contract Documents and Specifications. Such changes are to be incorporated into the Construction Documents and shall apply to the work with the same meaning and force as if they had been included in the original document. Wherever this Addendum modifies a portion of a paragraph of the specifications or a portion of any Drawing, the remainder of the Paragraph or Drawing shall remain in force. NOTE: Provisions of all Contract Documents apply.
INSTRUCTIONS TO BIDDERS Item 1. INS-5, Item 14.c. DELETE “…no later than 2:00PM on February 9, 2021.” REPLACE with c. Completed and responsive Bid Proposals shall be submitted through the eBuilder Bid Portal, no later than 2:00PM on February 10, 2021. BID PROPOSAL CERTIFICATION FORM Item 2. BF-2, Item 3.c.
DELETE “…Substantial Completion: August 13, 2021”
REPLACE with “…Substantial Completion: August 6, 2021”
Item 3. RFI Questions and Clarifications
See attached RFI Log (Items 1 - 8)
Attachments: Pre-Bid Sign in sheet RFI Log (Items 1-8) ****END OF ADDENDUM****
PROJECT: Low Rise 9 Certificate of Occupancy Enabling & Heater Replacements Date: February 2, 2021
RFI Form
RFI/Page/
Response Dwg./Spec./Rep.Section/Design Team
Index Number Paragraph/Topic RFI Response
1
Does the steel in the elevator shaft need spray fireproofing?The elevator does not need spray fireproofing. The
Steel can be encased with metal furring and gwb.
2
Who’s responsible for getting the elevator locked out and
going from floor to floor?
The Owner will work with the elevator contractor and
cover the cost with Otis.
3
How do you infill the pivot holes when you take doors out?Contractor to infill hole with self-leveling floor patch compound material similar to "Sakrete Gray Self-
Leveling" or equal, and provide cover material
product materail that matches adjacent to infill.
4
Are you taking out the frames as well or just the doors?Doors and frames will both be taken out.
5 01 35 29 None of the drywall is asbestos?Bid documents include testing reports which indicate
that drywall is not ACM.
6
Can the Unit Heaters be removed back to back or is there a
Phasing plan to replace them?
The unit heaters should all be removed and new ones
installed, prior to students return in August. There is
no phasing necessary.
7 ME-201 2
Are the 3/8" threaded rod hangers new, or can the existing hangers be used, specifically where the hanger is in finish
ceiling we are not removing ?
( detail 2/ME-501).
Contractor to remove portions of existing ceiling as required to install new HVAC unit and provide new
threaded rod as indicated on detail. Contractor to
patch, repair, tape, spackle, and paint (2 coats min.)
ceiling after installation of new Mech unit.
8
Is our mechanical sub. responsible to receive, store, then
deliver to job site the new owner provided unit heaters?
The unit heater will be ordered and delivered by the
Owner, and the Contractor will assist in unloading
and moving to storage designated space within Low
Rise 9 until ready for installation by Contractor.