HomeMy WebLinkAboutOlin Hall 2024 Room B40 Minor Lab-top Epoxy Abatement SOW (003)Cornell University – Asbestos Abatement Type 1
Project Scope of Work
Page 1 of 5
Project Location/Information:
Date Prepared: September 11, 2020
Building Name / Code / Address: Olin Hall / 2024 / 113 Ho Plaza, Ithaca, NY
Cornell Space ID#(s): Basement Room B40
Cornell Project Representative: Mike Swartwout (Office: 607-255-4920 / Cell: 607-327-0128)
Cornell Building Coordinator: Thom Quinn (Office: 607-255-3540, Room B-14A in Olin Hall)
Quantity and description of materials being removed:
Abatement operations shall include the removal of non-asbestos Lab-tops / Sink-top / Backsplashes and
their associated non-friable organically bound (NOB) asbestos containing joint/seam epoxy present along
the west wall in Room B40. All Lab-top/sink utilities shall be disconnected prior to abatement
operations. The ACM epoxy is applied at the various joints/seams on the lab-top/sink-top sections and
backsplashes to be removed. The total quantity of asbestos containing joint/seam epoxy to be removed is
less than 1 square foot (23 linear feet at an average 1/8” width). Reference the attached drawing for the
lab-top sections and their associated backsplashes to be removed. All lab-top bases shall be cleaned and
are to remain.
Method of Abatement:
Non-Asbestos Lab-tops and associated ACM joint/seam epoxy removal shall be performed as per the
requirements of 12 NYCRR Part 56-11.1 for In-Plant operations and Part 56-11.3 for Minor Asbestos
Projects.
Abatement Project Schedule/Dates/Manpower:
Anticipated Crew Size: 1 Supervisor 2 Worker
Project Schedule: Abatement operations including work area preparation, abatement, and final cleaning
shall be performed during a worst-case single shift on Wednesday, September 16th, 2020 starting at 7:30
am. Contact Building Coordinator Tom Quin upon arrival for Room Access.
Special Project Conditions:
Project Power: Existing Building Power to be utilized
Project Water: Source to be provided by the Owner
Negative Air Exhaust Location: Localized via HEPA-Vacuum.
Project Documentation / Requirements:
Work Order No. Reference Task Authorization for Work Order No.
Prevailing Wage Rate Project: Yes No X
Cornell University – Asbestos Abatement Type 1
Project Scope of Work
Page 2 of 5
Building Permits:
State Permit Required: Yes No X ; Contractor to Procure: Yes No
Local City Permit Required: Yes X No ; Contractor to Procure: Yes X No
Project Notifications:
NYS DOL 10-Day Notification Required: Yes No X
EPA 10-Day Notification Required: Yes No X
Building Occupant Posting, Date of Posting: As necessary for 9/16/2020 project date
Prepared By:
DELTA ENGINEERS, ARCHITECTS, & LAND SURVEYORS, DPC
Stephen Prislupsky
Director of Environmental Services
NYS DOL Asbestos Project Designer Certificate No. 90-10891
Cornell University – Asbestos Abatement Type 1
Project Scope of Work
Page 3 of 5
Attachment A
Drawings
Cornell University – Asbestos Abatement Type 1
Project Scope of Work
Page 4 of 5
Attachment B
Photos
Cornell University – Asbestos Abatement Type 1
Project Scope of Work
Page 5 of 5
Non-Asbestos Lab-top / Sink-top / Backsplash with ACM Joint/Seam Epoxy to be removed
(sections present on blue base cabinets in photos)