HomeMy WebLinkAbout150304_RFI Question_Response WorksheetCLARA DICKSON HALL WASTE & STORM LINE REPLACEMENT - YEAR 1 Pre-Bid RFI Form Date: March 4, 2015 RFI/Page/ Response Dwg./Spec./Rep.Section/Design Team Index Number Paragraph/Topic RFI Response 1 Specification Section 09 68 00 - Carpeting F.E. Jones 03/02/15 9:41 a.m. "Please provide the basis of design carpet manufacturer and the "Quality Name" as these cannot be found either in the specifications or on the drawings." See Addendum No. 1, Item 5. 2 Specification Section 31 23 16.13 - Trenching L.C. Ames 02/27/15 1:57 p.m. "Please confirm that the Owner will not provide a dump site as suggested by Spec 312316."See Addendum No. 1, Item 7. 3 Specification Section 31 23 16.13 - Trenching Disposal of Materials L.C. Ames 02/27/15 1:57 p.m. "Are there any special disposal requirements for the existing pipe that is removed (hazardous or contaminated waste requirements)?"See Addendum No. 1, Item 8. 4 Specification Section 31 23 23.13 - Backfill Offsite Materials L.C. Ames 02/27/15 1:57 p.m. "Do the stone aggregate products have to be limestone (imported from Syracuse area) or can they be made by the local pits from crushed cobbles?"See Addendum No. 1, Item 8 and Item 9. 5 Drawing P001 - Title Sheet, Symbols, Schedules, Notes & Details Detail 1/P001 L.C. Ames 03/02/15 9:20:05 a.m. "Can flowable fill be used in lieu of the specified bedding and backfill? Any shrinkage could be addressed with a leveling top layer below the slab."See Addendum No. 1, Item 10. 6 Drawing P001 - Title Sheet, Symbols, Schedules, Notes & Details Detail 1/P001 L.C. Ames 02/27/15 1:57 p.m. "Please clarify your trench sections to indicate width." See Addendum No. 1, Item 10 and Item 11. 7 Drawing P100 - Underfloor Piping Removal Plan - North L.C. Ames 02/27/15 3:19:22 p.m. "Would you please provide invert for storm line."See Addendum No. 1, Item 12. 8 Drawing P100 - Underfloor Piping Removal Plan - North L.C. Ames 03/02/15 11:28 a.m. "We see some locations where it appears that piping connections are made close to columns. Is any excavation/coring, etc. into the structural concrete (footers, etc.) required to make the required piping connections to existing? If so, please advise the locations where this is required and also provide the structural details so we can assess what is required." See Addendum No. 1, Item 13 and Item 14. RFI/Page/ Response Dwg./Spec./Rep.Section/Design Team Index Number Paragraph/Topic RFI Response