Loading...
HomeMy WebLinkAbout14060 Tech SpecificationChi Phi Fraternity August 4, 2014 Interior Finishes Restoration SELECTIVE DEMOLITION Bero Architecture PLLC 024119 - 1 14060.024119.21614 SECTION 024119 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. The work to be done under this section includes administrative and procedural requirements for selective demolition shown on the Drawings or called for in the Project manual. 1. Demolition and removal of selected portions of building or structure. 2. Salvage of existing items to be reused or recycled. 1.2 MATERIALS OWNERSHIP A. Unless otherwise indicated, demolition waste becomes property of Contractor. B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner. 1. Carefully salvage in a manner to prevent damage and promptly return to Owner. 1.3 PREINSTALLATION MEETINGS A. Predemolition Conference: Conduct conference at Project site. 1.4 INFORMATIONAL SUBMITTALS A. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for dust control. Indicate proposed locations and construction of barriers. B. Schedule of selective demolition activities with starting and ending dates for each activity. C. Predemolition photographs or video. 1.5 FIELD CONDITIONS A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration SELECTIVE DEMOLITION Bero Architecture PLLC 024119 - 2 14060.024119.21614 1. Before selective demolition, Owner will remove the following items: a. Furniture, furnishings, and equipment in work areas. C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition. D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work. 1. Hazardous materials will be removed by Owner before start of the Work. 2. If suspected hazardous materials are encountered, do not disturb; immediately notify Architect and Owner. Hazardous materials will be removed by Owner under a separate contract. E. Storage or sale of removed items or materials on-site is not permitted. F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations. 1. Maintain fire-protection facilities in service during selective demolition operations. G. Arrange selective demolition schedule so as not to interfere with Owner's operations. PART 2 - PRODUCTS 2.1 PERFORMANCE REQUIREMENTS A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction. B. Standards: Comply with ASSE A10.6 and NFPA 241. PART 3 - EXECUTION 3.1 EXAMINATION A. Verify that utilities have been disconnected and capped before starting selective demolition operations. B. Inventory and record the condition of items to be removed and salvaged. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration SELECTIVE DEMOLITION Bero Architecture PLLC 024119 - 3 14060.024119.21614 3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage. B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished. 1. Owner will arrange to shut off indicated services/systems when requested by Contractor. 2. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building. 3. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed. a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material. b. Equipment to Be Removed: Disconnect and cap services and remove equipment. 3.3 PROTECTION A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain. B. Remove temporary barricades and protections where hazards no longer exist. 3.4 SELECTIVE DEMOLITION A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows: 1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain. 2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces. 3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations. 4. Maintain fire watch during and for at least one hour after flame-cutting operations. 5. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing. 6. Dispose of demolished items and materials promptly. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration SELECTIVE DEMOLITION Bero Architecture PLLC 024119 - 4 14060.024119.21614 B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities. C. Removed and Salvaged Items: 1. Clean salvaged items. 2. Pack or crate items after cleaning. Identify contents of containers. 3. Store items in a secure area until delivery to Owner. 4. Transport items to Owner's storage area on-site. 5. Protect items from damage during transport and storage. D. Removed and Reinstalled Items: 1. Clean and repair items to functional condition adequate for intended reuse. 2. Pack or crate items after cleaning and repairing. Identify contents of containers. 3. Protect items from damage during transport and storage. 4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated. E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete. 3.5 CLEANING A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction. 1. Do not allow demolished materials to accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. 3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent. B. Burning: Do not burn demolished materials. C. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began. END OF SECTION 024119 CORNELL SECTION 051200 Ithaca, New York STRUCTURAL STEEL CHI PHI FRATERNITY STRUCTURAL STEEL 051200-1 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of contract, including general and supplementary conditions and Division 1 specification sections, apply to this section. 1.2 DESCRIPTION OF WORK A. This section includes structural steel. 1.3 QUALITY ASSURANCE A. Comply with latest editions of: 1. American Institute of Steel Construction (AISC), "Manual of Steel Construction," including: - ANSI/AISC 360, "Specification for Structural Steel Buildings.” - AISC 303, "Code of Standard Practice for Steel Buildings and Bridges.” - Research Council on Structural Connections (RCSC), “Specification for Structural Joints Using ASTM A 325 or A 490 Bolts.” 2. American Welding Society, Inc. (AWS) a. AWS D1.1 “Structural Welding Code - Steel.” b. AWS C5.4 “Recommended Practices for Stud Welding.” 3. Research Council on Structural Connections (RCSC), Educational Bulletin No. 4, "Recommended Erection and Field Inspection Procedures for High-Strength Bolts in Structural Steel Assemblies." B. Qualifications for Welding Work: 1. Qualify welding processes and welding operators in accordance with AWS standards. 2. Provide one of the following certifications for welders to be employed in work. a. Certification of satisfactorily passing AWS qualification tests within previous 12 months to perform type of welding in work. b. Work record signed by supervisor showing regular employment within previous 12 months to perform type of welding in work. C. Qualifications for Fabricator, Detailer, and Erector: 1. Fabricator, Detailer, and Erector of structural steel shall have minimum 3 years experience in fabricating, detailing, and erecting structural steel. CHI PHI FRATERNITY STRUCTURAL STEEL 051200-2 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 a. Erector Qualifications: Erector shall be AISC Certified Erector, Category CSE. b. Fabricator Qualifications: Fabricator shall be AISC Certified Fabricator, Category STD. c. AISC Certification for Fabricators and Erectors may be waived at the discretion of Owner, Architect, and Engineer provided acceptable written quality assurance and quality control plan is submitted. 2. Submit written description of ability. 3. At completion of fabrication, Fabricator shall submit Certificate of Compliance to Special Inspector and Code Enforcement Official stating work was performed in accordance with approved Construction Documents. 1.4 MATERIAL EVALUATION/QUALITY CONTROL A. Contractor shall employ testing laboratory acceptable to Engineer and Architect to perform material evaluation tests. B. Submit testing service qualifications demonstrating experience with similar types of projects. C. The Registered Design Professionals (RDPs) for Structural Engineering and Architecture will visit construction site at appropriate intervals to determine if work is in general conformance with Contract Documents and specifications. Notify RDPs 48 hours before anticipated time of completion for a given section of work so they may determine if site observations are required. If site observations are required, do not conceal framing until RDPs have had opportunity to make observations. 1.5 SUBMITTALS A. General: Review of submittals will be for general conformance only. Compliance with requirements for materials, fabrication, erection, and dimensioning of structural steel shall be Contractor's responsibility. Resubmitted shop drawings shall have revisions identified and dated. B. Connections: Submit proposed connection types and calculations for review before preparing detailed shop drawings. C. Shop Drawings: Submit detailed drawings showing: 1. Reference Contract Drawing number and addendum number in each shop drawing. 2. Shop erection details including cuts, copes, camber, connections, holes, bolts, and other pertinent information. 3. Material, including ASTM designations and grades or manufacturer’s data as appropriate. 4. Welds with size, length, and type. 5. Anchor rod locations. 6. Shop drawings have been checked by detailer and noted as checked in drawings before submitting. Failure to submit checked shop drawings will be cause for their return without review. If drawings are not prepared by detailer under direct control of Fabricator, Fabricator shall stamp each drawing and initial or sign stamp to certify review CHI PHI FRATERNITY STRUCTURAL STEEL 051200-3 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 and approval of drawings and conformance with Fabricator’s shop practice and capability. D. Material Data: Submit to Special Inspector and Engineer laboratory test reports and other data as required to show compliance with specifications. Submit producer’s or manufacturer’s specifications and installation instructions for the following products: 1. Structural steel, including certified copies of mill reports covering chemical and physical properties. 2. High-strength bolts, including nuts and washers. 3. Unfinished bolts and nuts. 4. Structural steel primer paint if used. 5. Welding electrodes. 6. Post-installed anchors (expansion, sleeve, or chemical adhesive) if used. E. Bolt Certification: Submit to Special Inspector and Engineer certifications that bolts, nuts, and washers furnished comply with specifications. Submit manufacturer's inspection certificates for mill tests. For fasteners to be accepted, lot numbers on kegs, boxes, or bags must correlate with lot numbers shown in accepted test certificates and identification numbers in mill test reports. Manufacturer's symbol and grade markings must appear on bolts and nuts. F. Field Modifications: Submit drawings showing field modifications required to conform to actual field conditions or as required to correct errors in shop drawings, fabrication, or erection. G. Erector’s Welding Procedure Specifications: Submit welding procedure specifications for joint types detailed for field welding. 1.6 PRODUCT HANDLING A. Store material in horizontal position on supports above ground. B. Protect from weather, and keep free of dirt and debris. C. Handle material carefully so it is not bent or marred. D. Repair or replace damaged materials. Do not incorporate in work fastener components that accumulate rust or dirt. 1.7 WORKMANSHIP A. Contractor shall be responsible for correction of work not conforming to specified requirements. Correct deficient work as directed by Architect. B. Remove work found to be defective. Replace with new acceptable work.   PART 2 - PRODUCTS CHI PHI FRATERNITY STRUCTURAL STEEL 051200-4 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 2.1 MATERIALS A. Materials shall be new and free from rust. B. Rolled-Steel Plates, Bars, and Angles: ASTM A 36. C. Rolled-Steel C and MC Shapes: ASTM A 36 unless indicated in drawings as Grade 50 (ASTM A 572). D. Hollow Structural Sections (HSS): ASTM A 500, Grade B or C. E. High-Strength Bolts: ASTM A 325 or A 490, Type 1, plain. F. Anchor Rods: ASTM A 36. G. Nuts: ASTM A 563. Grade and finish to match bolt or rod type. H. Washers: ASTM F 436 (ASTM F 844 for ASTM A 307 bolts, A 36 rods and F 1554 Grade 36 anchor rods). Finish to match bolt or rod type. I. Electrodes: E70 and in accordance with AWS. J. Nonshrink Grout: Corp of Engineers CRD-C 621. “Conspec 100” by Conspec Manufacturing Co.; “NS Grout” by Euclid Chemical Co.; “SikaGrout 212” by Sika Corp.; “Masterflow 928” or “Set Grout” by Master Builders, Inc.; “Sonogrout” by Sonneborn Building Products; or accepted equivalent. K. Steel Primer Paint: For steel scheduled to receive finish paint, use primer compatible with finish paint specified in Division 9. L. Chemical Adhesive Anchors: 1. Anchors to solid concrete, grouted CMU, solid brick, or stone: a. Anchors for use when base material temperature is 0°F or greater: “HIT-Ice” by Hilti; “Epcon A7” by ITW Ramset/Red Head; “AC 100 Plus” by Powers Fasteners; “AT Acrylic-Tie” by Simpson/Strong-Tie; or accepted equivalent. b. Anchors for use when base material temperature is 40°F or greater; “HIT HY 150” or “HIT HY 150 MAX” by Hilti; “Epcon C6” by ITW Ramset/Red Head; “T308 Plus” by Powers Fasteners; “ET Epoxy-Tie” by Simpson/Strong-Tie; or accepted equivalent. 2.2 FABRICATION A. Fabricate structural steel in strict accordance with reviewed shop drawings and referenced standards. B. Fabricate and assemble structural material in shop to greatest extent possible. C. Provide holes for securing other work to structural steel framing. Cut, drill, or punch holes CHI PHI FRATERNITY STRUCTURAL STEEL 051200-5 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 perpendicular to metal surfaces. Do not flame-cut holes or enlarge holes by burning. Drill holes in base and bearing plates more than 3/4 inch thick. D. Finish bottom of column and weld to base plate. Use flat base plates. 2.3 CONNECTIONS A. Comply with requirements of this section unless indicated otherwise in drawings. B. Use connection dimensions and sizes complying with AISC-published recommendations and limitations shown in drawings. C. Bolt field connections wherever possible. D. Use AISC Single-Plate Shear Connection for beam connections to faces of tubes and column flanges that have a width of 6 inches or less. E. Use AISC Framed Beam Connection for beam connections to faces of tubes and F. Provide snug-tightened joints using bearing bolts with thread condition N for bolted connections unless indicated otherwise. Provide pretensioned or slip-critical joints where shown or noted in drawings. For slip-critical joints, provide AISC Class A faying surface condition. G. Remove burrs that prevent solid seating of connected parts. PART 3 - EXECUTION 3.1 JOB CONDITIONS A. Examine conditions under which work shall be erected. Do not proceed until unsatisfactory conditions are corrected. 3.2 ERECTION A. Set structural frames accurately to lines and elevations indicated. Align and adjust various members forming part of a complete frame or structure before permanently fastening. B. Fit up connections to be field welded in compliance with AWS standard tolerances for review by the Special Inspector or Testing Agency prior to field welding. C. Before assembly, clean bearing surfaces and other surfaces that will be in permanent contact after assembly. D. Perform necessary adjustments to compensate for discrepancies in elevations and alignment. Level and plumb individual members of structure within specified tolerances. E. Splice members only where shown or specified. CHI PHI FRATERNITY STRUCTURAL STEEL 051200-6 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 F. Maintain work in stable condition during erection. G. Install field connections and framing as detailed in Contract Documents and accepted shop drawings. If Contractor finds field modifications are necessary, submit documentation of proposed field modifications to Architect and Engineer for review and acceptance before beginning. 1. Use of thermal cutting for field modifications is prohibited unless documented and accepted by Engineer before beginning. 2. Use of thermal cutting for enlarging or cutting bolt holes in field is prohibited. 3.3 TOLERANCES A. Tolerances shall be within limits in AISC "Code of Standard Practice.” B. Fabrication and mill tolerance shall be within limits in AISC “Standard Mill Practice.” 3.4 TEMPORARY SHORING AND BRACING A. Provide temporary shoring and bracing members as required with connections of sufficient strength to bear imposed loads. B. Remove temporary members and connections when permanent members are in place and final connections are made. 3.5 PROTECTION A. Do not use members for storage or work platforms until permanently secured. B. Do not exceed load capacity of members with construction loads. ***END OF SECTION 051200*** Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration DECORATIVE METAL Bero Architecture PLLC 057000 - 1 14060.057000.21614 SECTION 057000 - DECORATIVE METAL PART 1 - GENERAL 1.1 SUMMARY A. The work to be done under this section includes all equipment, labor, materials, and accessories required for the furnishing, setting in place, and completion of decorative metal shown on the Drawings or called for in the Project Manual including but not limited to: 1. Cleaning decorative metal drawer pulls. 2. Fabrication of decorative metal drawer pulls. 3. Cleaning foot rail at bar. 4. Decorative mechanical grilles. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product, including finishing materials. B. Samples: For each type of exposed finish. 1. Cleaning methods and results. PART 2 - PRODUCTS 2.1 COPPER AND COPPER ALLOYS A. Custom fabricate new elements from materials to match existing. 2.2 DECORATIVE MECHANICAL GRILLES A. Basis-of-Design Product: Subject to compliance with requirements, provide Reggio Register® Metal Grille – Square Design – G616 B. Fabricate decorative grilles from perforated steel sheet or plate of thickness, size, and pattern to match existing. Form perforations by punching, cutting, or drilling to produce openings of sizes and shapes indicated. Roll, press, and grind perforated metal to flatten and to remove burrs and deformations. 1. Drawings indicate perforated metal patterns required and are based on products of one manufacturer. Perforated metal patterns produced by other manufacturers may be considered, provided deviations are minor and do not change design concept as judged solely by Architect. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration DECORATIVE METAL Bero Architecture PLLC 057000 - 2 14060.057000.21614 2. Color: Black. 2.3 FASTENERS A. Fastener Materials: Unless otherwise indicated, provide the following: 1. Match existing. 2.4 MISCELLANEOUS MATERIALS A. Cleaning materials. 1. HEPA filtered vacuum. 2. Soft natural bristle brush. 3. Mineral spirits. 4. Dish detergent. 5. Distilled water. 6. Denatured alcohol. 7. Clean, soft cotton cloth. 2.5 FABRICATION, GENERAL A. Form decorative metal to match existing shapes and sizes, true to line and level with true curves and accurate angles and surfaces. Finish exposed surfaces to smooth, sharp, well-defined lines and arris. B. Provide castings that are sound and free of warp, cracks, blowholes, or other defects that impair strength or appearance. Grind, wire brush, sandblast, and buff castings to remove seams, gate marks, casting flash, and other casting marks. 2.6 CUSTOM DRAWER PULLS A. Fabricate custom drawer pulls from metals to match existing. Cast or form curves by bending to produce uniform curvature; maintain profile of member throughout entire bend without buckling, twisting, or otherwise deforming exposed surfaces. Where radii of bends are too small to avoid buckling, grind bars after bending to restore original profile. Drill and tap door pulls to receive through bolts for attachment to doors. B. Fabricate backing plates for custom drawer pulls from material to match existing. Cut to shape to match existing. Drill and countersink holes where required for screws and bolts. C. Provide units with oval-head through bolts for mounting pulls and with oval-head wood screws for mounting backing plates. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration DECORATIVE METAL Bero Architecture PLLC 057000 - 3 14060.057000.21614 2.7 FINISHES, GENERAL A. Match existing. B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping. 2.8 COPPER-ALLOY FINISHES A. Finish for new elements to match existing, after cleaning. PART 3 - EXECUTION 3.1 CLEANING EXISTING DECORATIVE METAL A. It is not the intent of this project to clean decorative metal to the extent that existing patina is removed. Care must be taken to clean using the most gentle methods possible. Elements should be clean only at completion, not polished or look “like new”. B. Remove loose dirt and dust using a soft brush and HEPA filtered vacuum. Do not use dust cloths which will not remove particles from small crevices. C. Remove waxy or oily residue with mineral spirits applied with loose cotton balls or cotton swabs. Use care to avoid scratching metal surfaces with accumulated grime. Change cotton balls or swabs often. D. Remaining residue may be removed with very dilute solution of detergent in distilled water. Gently agitate using soft brush, taking care not to scratch metal. Rinse thoroughly in clean distilled water and dry with soft cotton cloths. E. Light tarnish may be removed by wiping with color balls moistened with denatured alcohol. 3.2 INSTALLATION A. Provide anchorage devices and fasteners where needed to secure decorative metal to in-place construction. B. Set products locations identified. C. Fit exposed connections accurately together to form tight, hairline joints or uniform reveals. D. Do not cut or abrade finishes that cannot be completely restored in the field. Return items with such finishes to the shop for required alterations, followed by complete refinishing, or provide new units as required. E. Restore protective coverings that have been damaged during shipment or installation. Remove protective coverings only when there is no possibility of damage from other work. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration DECORATIVE METAL Bero Architecture PLLC 057000 - 4 14060.057000.21614 END OF SECTION 057000 Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration MISCELLANEOUS ROUGH Bero Architecture PLLC 061053 - 1 CARPENTRY 14060.061053.21614 SECTION 061053 - MISCELLANEOUS ROUGH CARPENTRY PART 1 - GENERAL 1.1 SUMMARY A. The work to be done under this section includes all equipment, labor, materials and accessories required for the furnishing, setting in place, and completion of miscellanous rough carpentry shown on the Drawings or called for in the Project Manual including but not limited to: 1. Framing with dimension lumber. 2. Wood blocking, cants, and nailers. 1.2 ACTION SUBMITTALS A. Product Data: For each type of process and factory-fabricated product. PART 2 - PRODUCTS 2.1 WOOD PRODUCTS, GENERAL A. Certified Wood: Lumber shall be certified as "FSC Pure" or "FSC Mixed Credit" according to FSC STD-01-001, "FSC Principles and Criteria for Forest Stewardship," and to FSC STD-40- 004, "FSC Standard for Chain of Custody Certification." B. Lumber: DOC PS 20 and applicable rules of grading agencies indicated. If no grading agency is indicated, provide lumber that complies with the applicable rules of any rules-writing agency certified by the ALSC Board of Review. Provide lumber graded by an agency certified by the ALSC Board of Review to inspect and grade lumber under the rules indicated. 1. Factory mark each piece of lumber with grade stamp of grading agency. 2. Dress lumber, S4S, unless otherwise indicated. C. Maximum Moisture Content of Lumber: 15 percent unless otherwise indicated. 2.2 DIMENSION LUMBER FRAMING A. Non-Load-Bearing Interior Partitions: Construction or No. 2 grade of any species. B. Other Framing: Construction or No. 2 grade of any of the following species: 1. Hem-fir (north); NLGA. 2. Southern pine; SPIB. 3. Douglas fir-larch; WCLIB or WWPA. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration MISCELLANEOUS ROUGH Bero Architecture PLLC 061053 - 2 CARPENTRY 14060.061053.21614 4. Southern pine or mixed southern pine; SPIB. 5. Spruce-pine-fir; NLGA. 6. Douglas fir-south; WWPA. 7. Hem-fir; WCLIB or WWPA. 8. Douglas fir-larch (north); NLGA. 9. Spruce-pine-fir (south); NeLMA, WCLIB, or WWPA. 2.3 FASTENERS A. General: Provide fasteners of size and type indicated that comply with requirements specified in this article for material and manufacture. B. Power-Driven Fasteners: Fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC70. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Framing Standard: Comply with AF&PA's WCD 1, "Details for Conventional Wood Frame Construction," unless otherwise indicated. B. Set carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit carpentry accurately to other construction. Locate nailers, blocking, and similar supports to comply with requirements for attaching other construction. C. Securely attach carpentry work to substrate by anchoring and fastening as indicated, complying with the following: 1. Table 2304.9.1, "Fastening Schedule," in ICC's International Building Code. 2. Table R602.3(1), "Fastener Schedule for Structural Members," and Table R602.3(2), "Alternate Attachments," in ICC's International Residential Code for One- and Two- Family Dwellings. 3. ICC-ES evaluation report for fastener. END OF SECTION 061053 Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR FINISH CARPENTRY Bero Architecture PLLC 062023 - 1 14060.062023.21614 SECTION 062023 - INTERIOR FINISH CARPENTRY PART 1 - GENERAL 1.1 SUMMARY A. The work to be done under this section includes all equipment, labor, materials, and accessories required for the furnishing, setting in place, and completion of interior finish carpentry shown on the Drawings or called for in the Project manual including but not limited to: 1. Interior historic wood elements. 2. Replacement wood elements. 3. Restoration of existing clear finishes. 4. Finishing of new wood. 1.2 ACTION SUBMITTALS A. Product Data: For each type of process and factory-fabricated product. B. Samples: For each type of profiled trim. 1.3 MOCKUPS A. Mockups of wood cleaning are required. Prepare mockups for review by Restoration Architect and Owner for approval before continuing. Provide a sample of each cleaning technique on a 12” length of each wood item or species. B. Mockups of modifications to wood trim are required. PART 2 - PRODUCTS 2.1 MATERIALS, GENERAL A. Certified Wood: The following wood products shall be produced from wood obtained from forests certified by an FSC-accredited certification body to comply with FSC STD-01-001, "FSC Principles and Criteria for Forest Stewardship": 1. Interior trim. B. Lumber: DOC PS 20. 1. Factory mark each piece of lumber with grade stamp of inspection agency indicating grade, species, moisture content at time of surfacing, and mill. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR FINISH CARPENTRY Bero Architecture PLLC 062023 - 2 14060.062023.21614 a. For exposed lumber, mark grade stamp on end or back of each piece, or omit grade stamp and provide certificates of grade compliance issued by inspection agency. 2.2 INTERIOR TRIM A. Hardwood Lumber Trim: 1. Species and Grade: Match existing for each type of trim. 2. Maximum Moisture Content: 10 percent. B. Hardwood Moldings for Transparent Finish (Stain or Clear Finish): WMMPA HWM 2, N-grade wood moldings made to patterns included in WMMPA HWM 1. 1. Species: Match existing for each type or trim. 2. Maximum Moisture Content: 9 percent. 2.3 PANELING A. Hardwood Veneer Plywood Paneling: Manufacturer's stock hardwood plywood panels complying with HPVA HP-1, made without urea-formaldehyde adhesive. 1. Face Veneer Species and Cut: Match existing at each area. 2. Thickness: Match existing. 3. Finish: Match existing. B. Board Paneling: 1. Species and Grade: Match existing. 2. Maximum Moisture Content: 15 percent. 2.4 CLEANING MATERIALS A. Cleaning Materials. 1. Water Cleaning: a. Clean with water and bristle brush. 2. Job-Mixed Detergent Solution: a. Mix 2 cups of tetrasodium polyphosphate, 1/2 cup of laundry detergent and 15 quarts of warm water for each 5 gallon of solution required. If mildew stains are encountered notify Owner for instructions. 3. Mineral spirits. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR FINISH CARPENTRY Bero Architecture PLLC 062023 - 3 14060.062023.21614 2.5 FINISH MATERIALS A. Wood fillers: Wood Filler Paste: MPI #91. B. Stains: Semi-Transparent, for Interior Wood: Benwood Stains, or approved equal. C. Polyurethane Varnishes: Interior, Polyurethane, Oil-Modified, Satin (Gloss Level 4): Benwood Polyurethane Varnish, or approved equal. 2.6 MISCELLANEOUS MATERIALS A. Low-Emitting Materials: Adhesives shall comply with the testing and product requirements of the California Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers." B. Glue: Aliphatic-resin, polyurethane, or resorcinol wood glue recommended by manufacturer for general carpentry use. 1. Wood glue shall have a VOC content of 30 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). C. Paneling Adhesive: Comply with paneling manufacturer's written recommendations for adhesives. 1. Adhesive shall have a VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). PART 3 - EXECUTION 3.1 GENERAL A. Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay. 1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition. 3.2 CUTTING A. Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations. 1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR FINISH CARPENTRY Bero Architecture PLLC 062023 - 4 14060.062023.21614 required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use. 2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces. 3.3 REMOVALS A. Photograph areas where removals will occur to show original configuration. Each item scheduled for removal is to be identified in the photograph using non-bleeding permanent marker on painter’s tape, or similar tape proven not to remove existing finish when removed, with item numbered to show location in two planes. As each item is removed mark the back side with the same identification as that on the front. 1. Store items in a safe location to prevent breakage, scratching, or theft. Stack neatly in layers on untreated 4x4 blocking not more than 24” oc. Leave 2” between each item in a layer. Provide cross blocking, aligned with base blocking, between layers to allow free flow of air around all items. Cross blocking are to be straight, uniformly thick, thoroughly dry and the same width as the stack. Do not stack more than head high. 2. Profiled or unevenly carved items are to supported as specified above but do not stack. Store in a single layer only. 3. Items of similar lengths are to be stacked together. For each layer, stack longer pieces at the edges for greater stability. Do not allow ends to overhang the stack without support. Put thicker items at the bottom of the stack. 4. Provide environmental conditions similar to those in the areas from which items are removed. Do not allow excessive heat, cold, dampness, or dryness. Provide sufficient blocking that no item is allowed to deformation from lack of support. Reinstall all items in the exact location from which they were removed. 3.4 PATCHING A. Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections. B. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation. C. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing. 3.5 PREPARATION FOR CLEANING A. Removing original finish or patina is not desirable. Cleaning is intended to remove loose dirt, dust, and superficial buildup. Some evidence of age of the items being cleaned should remain after cleaning. In all cases the most gentle cleaning methods will be used. Methods below are listed gentlest to most aggressive. Do not proceed to next method without written authorization from Owner. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR FINISH CARPENTRY Bero Architecture PLLC 062023 - 5 14060.062023.21614 B. Test items to be cleaned prior to cleaning to determine if finish is shellac: Dampen a clean a cotton cloth with denatured alcohol. Rub surface to be cleaned in a concealed location. If the finish becomes “gummy” the finish is shellac. Notify Owner for instructions for proceeding with cleaning. 3.6 CLEANING METHODS A. First method: 1. Remove loose surface soil or dust using a clean, soft cotton cloth or vacuum with a clean soft brush attachment. Wipe surface with cotton cloth dampened with mineral spirits. Soft bristle brush dipped in mineral spirits shall be used to clean hard to reach areas not accessible with cotton cloth such as carvings and intricate parts of the items being cleaned. 2. Wipe surface with clean cloth again and let dry for several hours. Where second cleaning is required, wipe lightly with clean cotton cloth dampened in cleaning detergent. Wipe with cloth slightly dampened in clear water. Wipe dry with clean cloth. B. Second method: 1. Remove dust, dirt, oil, grease, and sticky residue with job-mixed detergent solution; rinse thoroughly and allow to dry. Protect adjacent surfaces from cleaning process by masking surfaces. Detergent can damage metal, painted surfaces, stained wood, and glass. C. Third method: 1. For heavy-duty cleaning where job-mixed detergent solution does not adequately remove residue, mix 1 cup tetrasodium polyphosphate with 3 quarts water. Apply in a limited amount to substrate and protect adjacent construction. D. Other. 1. Mineral spirits only may be used if other methods are unsuccessful. Follow manufacturer’s written instruction regarding ventilation or breathing device requirements when using mineral spirits. 2. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection. a. After completing reinstallation, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection if any. 3.7 PREPARATION A. Before installing interior finish carpentry, condition materials to average prevailing humidity in installation areas for a minimum of 24 hours unless longer conditioning is recommended by manufacturer. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR FINISH CARPENTRY Bero Architecture PLLC 062023 - 6 14060.062023.21614 3.8 INSTALLATION, GENERAL A. Install interior finish carpentry level, plumb, true, and aligned with adjacent materials. Use concealed shims where necessary for alignment. 1. Scribe and cut interior finish carpentry to fit adjoining work. Refinish and seal cuts as recommended by manufacturer. 2. Countersink fasteners, fill surface flush, and sand unless otherwise indicated. 3. Install to tolerance of 1/8 inch in 96 inches for level and plumb. Install adjoining interior finish carpentry with 1/32-inch maximum offset for flush installation and 1/16-inch maximum offset for reveal installation. 3.9 REINSTALLATION A. Rotary sanders, pressurized water or aggregate blasting, or propriety machines will not be used. B. All loose boards and missing or loose fasteners will be repaired or replaced in kind. Replacement fasteners shall be stainless steel or bronze. C. Weathered gray (punky) or deteriorated wood shall be sanded to a bright, sound substrate prior to priming. This can be accomplished with hand sanding, pad (finish) sanders, or random orbit sanders. D. Where sanding is not possible, weathered gray or deteriorated wood shall be treated with a mixture of one-part boiled linseed oil and one-part mineral spirits as a consolidant for the wood surface. Treatment shall dry prior to priming. E. Treat mildew with a solution of one-part chlorine bleach and four-parts water and then thoroughly rinse. F. Caulking and filling procedures shall be completed not over bare wood. G. Apply finish to match existing exactly only where minor repairs are made. Do not apply finish to entire item. 3.10 STANDING AND RUNNING TRIM INSTALLATION A. Install with minimum number of joints practical, using full-length pieces from maximum lengths of lumber available. Miter at returns, miter at outside corners, and cope at inside corners to produce tight-fitting joints with full-surface contact throughout length of joint. Use scarf joints for end-to-end joints. 3.11 PANELING INSTALLATION A. Board Paneling: 1. Install in full lengths without end joints. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR FINISH CARPENTRY Bero Architecture PLLC 062023 - 7 14060.062023.21614 2. Stagger end joints in random pattern to uniformly distribute joints on each wall. 3. Select and arrange boards on each wall to minimize noticeable variations in grain character and color between adjacent boards. Install with uniform tight joints between boards. 4. Fasten paneling by face nailing, setting nails, and filling over nail heads. 5. Fasten paneling with trim screws, set below face and filled. 6. Fasten paneling by blind nailing through tongues. 7. Interior Wood Finish System Schedule 8. Wood substrates, including wood trim, architectural woodwork, doors, wood flooring, and wood panels. 3.12 FINISH APPLICATON A. Apply finishes according to manufacturer's written instructions and recommendations in "MPI Manual." 1. Testing: Test product system in an inconspicuous location for adhesion and compatibility prior to full-scale application. Apply finishes to produce surface films without cloudiness, holidays, lap marks, brush marks, runs, ropiness, or other surface imperfections. Apply coatings at spreading rate required to achieve the manufacturer’s recommended dry film thickness. a. Hand sand surface between coats with 220-grit sandpaper and wipe clean with damp cloth. B. Regardless of number of coats specified, apply as many coats as necessary for complete hide and uniform appearance. 3.13 INTERIOR WOOD FINISH SYSTEM SCHEDULE A. Polyurethane Varnish over Stain System: 1. Stain Coat: Stain, semi-transparent, for interior wood, MPI #90. 2. First Intermediate Coat: Polyurethane varnish matching topcoat. 3. Second Intermediate Coat: Polyurethane varnish matching topcoat. 4. Topcoat: Varnish, interior, polyurethane, oil-modified, satin (Gloss Level 4), MPI #57. B. Polyurethane Varnish System: 1. Prime Coat: Polyurethane varnish matching topcoat. 2. Intermediate Coat: Polyurethane varnish matching topcoat. 3. Topcoat: Varnish, interior, polyurethane, oil-modified, satin (Gloss Level 4), MPI #57. C. Finish restoration. Thin stain and varnish 1:3 with solvent or water. Mix well. Wipe on clean surfaces and remove excess. Repeat as required to provide continuous appearance to match existing. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR FINISH CARPENTRY Bero Architecture PLLC 062023 - 8 14060.062023.21614 END OF SECTION 062023 CORNELL SECTION 078413 Ithaca, New York PENETRATION FIRESTOPPING CHI PHI FRATERNITY PENETRATION FIRESTOPPING 078413-1 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Penetrations in horizontal assemblies. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Product Schedule: For each penetration firestopping system. Include location and design designation of qualified testing and inspecting agency. 1. Where Project conditions require modification to a qualified testing and inspecting agency's illustration for a particular penetration firestopping condition, submit illustration, with modifications marked, approved by penetration firestopping manufacturer's fire-protection engineer as an engineering judgment or equivalent fire- resistance-rated assembly. 1.3 INFORMATIONAL SUBMITTALS A. Installer Certificates: From Installer indicating penetration firestopping has been installed in compliance with requirements and manufacturer's written recommendations. B. Product test reports. 1.4 QUALITY ASSURANCE A. Fire-Test-Response Characteristics: Penetration firestopping shall comply with the following requirements: 1. Penetration firestopping tests are performed by UL. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. A/D Fire Protection Systems Inc. 2. Hilti, Inc. CHI PHI FRATERNITY PENETRATION FIRESTOPPING 078413-2 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 3. Specified Technologies Inc. 4. 3M Fire Protection Products. 5. Tremco, Inc.; Tremco Fire Protection Systems Group. 6. USG Corporation. 2.2 PENETRATION FIRESTOPPING A. Provide penetration firestopping that is produced and installed to resist spread of fire according to requirements indicated, resist passage of smoke and other gases, and maintain original fire- resistance rating of construction penetrated. Penetration firestopping systems shall be compatible with one another, with the substrates forming openings, and with penetrating items if any. B. Penetrations in Horizontal Assemblies: Ratings determined per ASTM E 814 or UL 1479, based on testing at a positive pressure differential of 0.01-inch wg (2.49 Pa). 1. F-Rating: At least 1 hour, but not less than the fire-resistance rating of constructions penetrated. 2. T-Rating: At least 1 hour, but not less than the fire-resistance rating of constructions penetrated except for floor penetrations within the cavity of a wall. C. Exposed Penetration Firestopping: Provide products with flame-spread and smoke-developed indexes of less than 25 and 450, respectively, as determined per ASTM E 84. D. VOC Content: Penetration firestopping sealants and sealant primers shall comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24): 1. Sealants: 250 g/L. 2. Sealant Primers for Nonporous Substrates: 250 g/L. 3. Sealant Primers for Porous Substrates: 775 g/L. E. Accessories: Provide components for each penetration firestopping system that are needed to install fill materials and to maintain ratings required. Use only those components specified by penetration firestopping manufacturer and approved by qualified testing and inspecting agency for firestopping indicated. PART 3 - EXECUTION 3.1 INSTALLATION A. Examine substrates and conditions, with Installer present, for compliance with requirements for opening configurations, penetrating items, substrates, and other conditions affecting performance of the Work. B. Install penetration firestopping to comply with manufacturer's written installation instructions and published drawings for products and applications indicated. CHI PHI FRATERNITY PENETRATION FIRESTOPPING 078413-3 INTERIOR FINISHES RESTORATION AUGUST 4, 2014 C. Install forming materials and other accessories of types required to support fill materials during their application and in the position needed to produce cross-sectional shapes and depths required to achieve fire ratings indicated. 1. After installing fill materials and allowing them to fully cure, remove combustible forming materials and other accessories not indicated as permanent components of firestopping. D. Install fill materials for firestopping by proven techniques to produce the following results: 1. Fill voids and cavities formed by openings, forming materials, accessories, and penetrating items as required to achieve fire-resistance ratings indicated. 2. Apply materials so they contact and adhere to substrates formed by openings and penetrating items. 3. For fill materials that will remain exposed after completing the Work, finish to produce smooth, uniform surfaces that are flush with adjoining finishes. 3.2 IDENTIFICATION A. Identify penetration firestopping with preprinted metal or plastic labels. Attach labels permanently to surfaces adjacent to and within 6 inches (150 mm) of firestopping edge so labels will be visible to anyone seeking to remove penetrating items or firestopping. Use mechanical fasteners or self-adhering-type labels with adhesives capable of permanently bonding labels to surfaces on which labels are placed. Include the following information on labels: 1. The words "Warning - Penetration Firestopping - Do Not Disturb. Notify Building Management of Any Damage." 2. Contractor's name, address, and phone number. 3. Designation of applicable testing and inspecting agency. 4. Date of installation. 5. Manufacturer's name. 6. Installer's name. 3.3 FIELD QUALITY CONTROL A. Owner may engage a qualified testing agency to perform tests and inspections. B. Where deficiencies are found or penetration firestopping is damaged or removed because of testing, repair or replace penetration firestopping to comply with requirements. C. Proceed with enclosing penetration firestopping with other construction only after inspection reports are issued and installations comply with requirements. ***END OF SECTION 078413*** Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration NON-STRUCTURAL METAL Bero Architecture PLLC 09 22 16-1 FRAMING 14060.092216.21614 SECTION 09 22 16 - NON-STRUCTURAL METAL FRAMING PART 1 - GENERAL 1.1 SUMMARY A. The work to be done under this section includes all equipment, labor, materials, and accessories required for the furnishing, setting in place, and completion of non-structural metal framing shown on the Drawings or called for in the Project Manual including but not limited to: 1. Non-load-bearing steel framing systems for interior gypsum board assemblies. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product. PART 2 - PRODUCTS 2.1 PERFORMANCE REQUIREMENTS 2.2 PERFORMANCE REQUIREMENTS A. Fire-Test-Response Characteristics: For fire-resistance-rated assemblies that incorporate non- load-bearing steel framing, provide materials and construction identical to those tested in assembly indicated, according to ASTM E 119 by an independent testing agency. 2.3 FRAMING SYSTEMS A. Framing Members, General: Comply with ASTM C 754 for conditions indicated. 1. Steel Sheet Components: Comply with ASTM C 645 requirements for metal unless otherwise indicated. 2. Protective Coating: Coating with equivalent corrosion resistance of ASTM A 653/A 653M, G40, hot-dip galvanized unless otherwise indicated. B. Studs and Runners: ASTM C 645. Use either steel studs and runners or dimpled steel studs and runners of equivalent minimum base-metal thickness. 1. Steel Studs and Runners: a. Subject to compliance with requirements, provide systems from Clark Dietrich Building Systems or approved equivalent. b. Minimum Base-Metal Thickness: As indicated on Drawings. c. Depth: As indicated on Drawings. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration NON-STRUCTURAL METAL Bero Architecture PLLC 09 22 16-2 FRAMING 14060.092216.21614 C. Slip-Type Head Joints: Where indicated, provide one of the following in thickness not less than indicated for studs and in width to accommodate depth of studs: 1. Single Long-Leg Runner System: ASTM C 645 top runner with 2-inch- deep flanges, installed with studs friction fit into top runner and with continuous bridging located within 12 inches of the top of studs to provide lateral bracing. D. Cold-Rolled Channel Bridging: Steel, 0.053-inch minimum base-metal thickness, with minimum 1/2-inch- wide flanges. 1. Depth: 1-1/2 inches. 2. Clip Angle: Not less than 1-1/2 by 1-1/2 inches, 0.068-inch- thick, galvanized steel. 2.4 AUXILIARY MATERIALS A. Fasteners for Metal Framing: Of type, material, size, corrosion resistance, holding power, and other properties required to fasten steel members to substrates. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Installation Standard: ASTM C 754. 1. Gypsum Board Assemblies: Also comply with requirements in ASTM C 840 that apply to framing installation. B. Install supplementary framing, and blocking to support fixtures, equipment services, heavy trim, grab bars, toilet accessories, furnishings, or similar construction. C. Install bracing at terminations in assemblies. D. Do not bridge building control and expansion joints with non-load-bearing steel framing members. Frame both sides of joints independently. 3.2 INSTALLING FRAMED ASSEMBLIES A. Install framing system components according to spacings indicated, but not greater than spacings required by referenced installation standards for assembly types. B. Where studs are installed directly against exterior masonry walls or dissimilar metals at exterior walls, install isolation strip between studs and exterior wall. C. Install studs so flanges within framing system point in same direction. D. Install tracks (runners) at floors and overhead supports. Extend framing full height to structural supports or substrates above suspended ceilings, except where partitions are indicated to Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration NON-STRUCTURAL METAL Bero Architecture PLLC 09 22 16-3 FRAMING 14060.092216.21614 terminate at suspended ceilings. Continue framing around ducts penetrating partitions above ceiling. 1. Slip-Type Head Joints: Where framing extends to overhead structural supports, install to produce joints at tops of framing systems that prevent axial loading of finished assemblies. 2. Fire-Resistance-Rated Partitions: Install framing to comply with fire-resistance-rated assembly indicated and support closures and to make partitions continuous from floor to underside of solid structure. E. Direct Furring: 1. Screw to wood framing. F. Installation Tolerance: Install each framing member so fastening surfaces vary not more than 1/8 inch from the plane formed by faces of adjacent framing. END OF SECTION 09 22 16   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GYPSUM PLASTERING Bero Architecture PLLC 14060.092300.21614 092300 - 1 SECTION 092300 - GYPSUM PLASTERING PART 1 - GENERAL 1.1 SUMMARY A. The work to be done under this section includes all equipment, labor, materials, and accessories required for furnishing, setting in place, and completion of gypsum plastering shown on the Drawings or called for in the Project Manual including but not limited to: 1. Alternate No. 1: Provide Decorative Plaster Ceiling. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product. B. Samples for verification: Provide one 6 inch sample for verification of cross section. C. Shop Drawings: Provide full size shop drawing for each large decorative element. 1.3 QUALITY ASSURANCE A. Mockups: Before installing plaster ornaments provide one sample of each piece to demonstrate aesthetic effects and set quality standards for materials and execution. 1. Approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion. PART 2 - PRODUCTS 2.1 MISCELLANEOUS MATERIALS A. Water for Mixing and Finishing Plaster: Potable and free of substances capable of affecting plaster set or of damaging plaster, lath, or accessories. B. Bonding Compound: ASTM C 631. 2.2 FINISH-COAT PLASTER MATERIALS A. Gypsum Gauging Plaster: ASTM C 28/C 28M. 1. Products: Subject to compliance with requirements, provide one of the following: a. National Gypsum Company; Gauging Plaster (Super-White). Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GYPSUM PLASTERING Bero Architecture PLLC 14060.092300.21614 092300 - 2 b. USG Corporation; Red Top Gauging Gypsum Plaster. B. Lime: ASTM C 206, Type N, normal finishing hydrated lime. 2.3 MOULDING PLASTER A. Plaster for molded decorative elements: 1. Basis of Design: USG Moulding Plaster or approved equal complying with ASTM C28. 2. HYDROCAL White Gypsum Cement or approved equal. 2.4 PLASTER MIXES 1. Mixing: Comply with ASTM C 842 and manufacturer's written instructions for applications indicated. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Protect adjacent work for soiling, spattering, moisture deterioration, and other harmful effects called by plastering. 3.2 INSTALLING EXPANDED-METAL LATH A. Expanded-Metal Lath: Install according to ASTM C 841. 3.3 PLASTER APPLICATION A. General: Comply with ASTM C 842. B. Bonding Compound: Apply on substrates for direct application of plaster. C. Plaster Finishes: 1. Provide troweled finish. END OF SECTION 092300 Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GYPSUM BOARD Bero Architecture PLLC 092900 - 1 14060.092900.21614 SECTION 092900 - GYPSUM BOARD PART 1 - GENERAL 1.1 SUMMARY A. The work to be done under his section includes all equipment, labor, materials, and accessories required for the furnishing, setting in place, and completion of gypsum board shown on the Drawings or called for in the Project Manual including but not limited to: 1. Interior gypsum board. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product. PART 2 - PRODUCTS 2.1 GYPSUM BOARD, GENERAL A. Regional Materials: Gypsum panel products shall be manufactured within 500 miles of Project site. B. Size: Provide maximum lengths and widths available that will minimize joints in each area and that correspond with support system indicated. 2.2 INTERIOR GYPSUM BOARD A. Gypsum Board, Type X: ASTM C 1396/C 1396M. 1. Thickness: 5/8 inch. 2. Long Edges: Tapered. 2.3 TRIM ACCESSORIES A. Interior Trim: ASTM C 1047. 1. Material: Galvanized or aluminum-coated steel sheet or rolled zinc, paper-faced galvanized-steel sheet. 2. Shapes: a. Cornerbead. b. Bullnose bead. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GYPSUM BOARD Bero Architecture PLLC 092900 - 2 14060.092900.21614 c. LC-Bead: J-shaped; exposed long flange receives joint compound. d. L-Bead: L-shaped; exposed long flange receives joint compound. e. U-Bead: J-shaped; exposed short flange does not receive joint compound. 2.4 JOINT TREATMENT MATERIALS A. General: Comply with ASTM C 475/C 475M. B. Joint Tape: 1. Interior Gypsum Board: Paper. C. Joint Compound for Interior Gypsum Board: For each coat, use formulation that is compatible with other compounds applied on previous or for successive coats. 1. Prefilling: At open joints and damaged surface areas, use setting-type taping compound. 2. Embedding and First Coat: For embedding tape and first coat on joints, fasteners, and trim flanges, use setting-type taping compound. a. Use setting-type compound for installing paper-faced metal trim accessories. 3. Fill Coat: For second coat, use setting-type, sandable topping compound. 4. Finish Coat: For third coat, use setting-type, sandable topping compound. 5. Skim Coat: For final coat of Level 5 finish, use setting-type, sandable topping compound. 2.5 AUXILIARY MATERIALS A. General: Provide auxiliary materials that comply with referenced installation standards and manufacturer's written instructions. B. Steel Drill Screws: ASTM C 1002 unless otherwise indicated. 1. Use screws complying with ASTM C 954 for fastening panels to steel members from 0.033 to 0.112 inch thick. 2. For fastening cementitious backer units, use screws of type and size recommended by panel manufacturer. PART 3 - EXECUTION 3.1 APPLYING AND FINISHING PANELS A. Examine panels before installation. Reject panels that are wet, moisture damaged, and mold damaged. B. Comply with ASTM C 840. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GYPSUM BOARD Bero Architecture PLLC 092900 - 3 14060.092900.21614 C. Isolate perimeter of gypsum board applied to non-load-bearing partitions at structural abutments. Provide 1/4- to 1/2-inch-wide spaces at these locations and trim edges with edge trim where edges of panels are exposed. Seal joints between edges and abutting structural surfaces with acoustical sealant. D. For trim with back flanges intended for fasteners, attach to framing with same fasteners used for panels. Otherwise, attach trim according to manufacturer's written instructions. E. Prefill open joints and damaged surface areas. F. Apply joint tape over gypsum board joints, except for trim products specifically indicated as not intended to receive tape. G. Gypsum Board Finish Levels: Finish panels to levels indicated below and according to ASTM C 840: 1. Level 5: At ceilings. a. Primer and its application to surfaces are specified in Section 099123 "Interior Painting." 3.2 PROTECTION A. Protect installed products from damage from weather, condensation, direct sunlight, construction, and other causes during remainder of the construction period. B. Remove and replace panels that are wet, moisture damaged, and mold damaged. END OF SECTION 092900   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WOOD FLOORING Bero Architecture PLLC 14060.096400.21614 096400 - 1 SECTION 096400 - WOOD FLOORING PART 1 - GENERAL 1.1 SUMMARY A. The work to be done under this section includes all equipment, labor, materials, and accessories required for the furnishing, setting in place, and completion of wood flooring shown on the Drawings or called for in the Project Manual including but not limited to: 1. Field-finished wood flooring. B. Related Requirements: 1. 1. Section 099300 “Staining and Transparent Finishing” for field finishing. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product. B. Samples: For each type of wood flooring and accessory. 1.3 QUALITY ASSURANCE A. Hardwood Flooring: Comply with NOFMA's "Official Flooring Grading Rules" for species, grade, and cut. B. Oak Flooring: Comply with applicable MFMA grading rules for species, grade, and cut. 1.4 PROJECT CONDITIONS A. Conditioning period begins not less than seven days before wood flooring installation, is continuous through installation, and continues not less than seven days after wood flooring installation. 1. Environmental Conditioning: Maintain an ambient temperature between 65 and 75 deg F and relative humidity planned for building occupants in spaces to receive wood flooring during the conditioning period. 2. Wood Flooring Conditioning: Move wood flooring into spaces where it will be installed, no later than the beginning of the conditioning period. a. Do not install flooring until it adjusts to relative humidity of, and is at same temperature as, space where it is to be installed. b. Open sealed packages to allow wood flooring to acclimatize immediately on moving flooring into spaces in which it will be installed. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WOOD FLOORING Bero Architecture PLLC 14060.096400.21614 096400 - 2 B. After conditioning period, maintain relative humidity and ambient temperature planned for building occupants. PART 2 - PRODUCTS 2.1 FIELD-FINISHED WOOD FLOORING A. Solid-Wood Flooring: Kiln dried to 6 to 9 percent maximum moisture content; tongue and groove and end matched; with backs channeled. 1. Grade and Species: Match existing original wood flooring. 2. Cut: Vertical grain. 3. Thickness: 3/4 inch. 4. Face Width: Match existing. 5. Lengths: Random-length strips complying with applicable grading rules. B. Urethane Finish System: Complete solvent-based, oil-modified system of compatible components that is recommended by finish manufacturer for application indicated and as specified in Section 099300 “Staining and Transparent Finishing.”. 1. Stain: Penetrating and nonfading type. a. Color: As selected by Architect from manufacturer's full range. 2. Finish Coats: Formulated for multicoat application on wood flooring. C. Wood Filler: Compatible with finish system components and recommended by filler and finish manufacturers for use indicated. 2.2 ACCESSORY MATERIALS A. Fasteners: As recommended by manufacturer, but not less than that recommended in NWFA's "Installation Guidelines." B. Thresholds and Saddles: To match wood flooring. Tapered on each side. PART 3 - EXECUTION 3.1 PREPARATION A. Broom or vacuum clean substrates to be covered immediately before product installation. After cleaning, examine substrates for moisture, alkaline salts, carbonation, or dust. Proceed with installation only after unsatisfactory conditions have been corrected. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WOOD FLOORING Bero Architecture PLLC 14060.096400.21614 096400 - 3 3.2 INSTALLATION A. Comply with flooring manufacturer's written installation instructions, but not less than applicable recommendations in NWFA's "Installation Guidelines." B. Provide expansion space at walls and other obstructions and terminations of flooring of not less than 3/4 inch. C. Solid-Wood Flooring: Blind nail or staple flooring to substrate. 3.3 FIELD FINISHING A. Finishing of new wood flooring. 1. Machine-sand flooring to remove offsets, ridges, cups, and sanding-machine marks that are noticeable after finishing. Vacuum and tack with a clean cloth immediately before applying finish. 2. Comply with applicable recommendations in NWFA's "Installation Guidelines: Wood Flooring". 3. Fill open-grained hardwood. 4. Fill and repair wood flooring seams and defects and fill all nail holes with manufacturer’s recommended wood filler compound. 5. Apply final finish as soon as possible after final sanding is complete. 6. Apply floor-finish materials in number of coats recommended by finish manufacturer for application indicated, but not less than three finish coats. a. Apply stains to achieve an even color distribution matching approved Samples. b. For water-based finishes, use finishing methods recommended by finish manufacturer to minimize grain raise. 3.4 PROTECTION A. Do not cover wood flooring after finishing until finish reaches full cure, and not before seven days after applying last finish coat. B. Protect installed wood flooring during remainder of construction period with covering of heavy kraft paper or other suitable material. Do not use plastic sheet or film that might cause condensation. C. Repair or replace any damaged or deflective work, including but not limited to chipping or scratching of flooring. END OF SECTION 096400   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR PAINTING Bero Architecture PLLC 099123 - 1 14060.099123.21614 SECTION 099123 - INTERIOR PAINTING. PART 1 - GENERAL 1.1 SUMMARY A. The work to be don’t under this section includes all equipment, labor, materials, and accessories required for interior painting shown on the Drawings or called for in the Project Manual including but not limited to: 1. Gypsum board. 2. Plaster. 1.2 DEFINITIONS A. MPI Gloss Level 1: Not more than five units at 60 degrees and 10 units at 85 degrees, according to ASTM D 523. B. MPI Gloss Level 4: 20 to 35 units at 60 degrees and not less than 35 units at 85 degrees, according to ASTM D 523. C. MPI Gloss Level 5: 35 to 70 units at 60 degrees, according to ASTM D 523. 1.3 ACTION SUBMITTALS A. Product Data: For each type of product. Include preparation requirements and application instructions. 1. Include Printout of current "MPI Approved Products List" for each product category specified, with the proposed product highlighted. B. MSDS: For each type of product. C. Samples: For each type of paint system and in each color and gloss of topcoat. 1.4 MAINTENANCE MATERIAL SUBMITTALS A. Furnish extra materials, from the same product run, that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Paint: 5 percent, but not less than 1 gal. of each material and color applied. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR PAINTING Bero Architecture PLLC 099123 - 2 14060.099123.21614 PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Products: Subject to compliance with requirements, provide one of the products listed in the Interior Painting Schedule for the paint category indicated. B. Basis of Design: Subject to compliance with requirements, provide paint products APPROVED BY CORNELL UNIVERSITY. Design based on products Benjamin Moore & Co or comparable products by one of the following manufacturer’s: 1. Pratt& Lambert 2. Sherwin Williams. 3. ICI Paint Stores, Inc. (Akzo Nobel Paints: ICI Paints/Glidden Professional/Devoe). 4. PPG Industries, Inc. (Pittsburgh Paints). 2.2 PAINT, GENERAL A. Material Compatibility: 1. Materials for use within each paint system shall be compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience. 2. For each coat in a paint system, products shall be recommended in writing by topcoat manufacturers for use in paint system and on substrate indicated. B. VOC Content: Products shall comply with VOC limits of authorities having jurisdiction. 1. Flat Paints and Coatings: 50 g/L. 2. Nonflat Paints and Coatings: 150 g/L. 3. Primers, Sealers, and Undercoaters: 200 g/L. C. Colors: As selected by Architect from manufacturer's full range. 2.3 PRIMERS/SEALERS A. Primer, Latex, Water Based: 1. Benjamin Moore & Co.; Fresh Start High-Hiding All Purpose Primer (046). 2.4 WATER-BASED PAINTS A. Latex, Interior, Flat, (Gloss Level 1): 1. Benjamin Moore & Co.; Waterborne Ceiling Paint (508). B. Latex, Interior, Institutional Low Odor/VOC, (Gloss Level 4). Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR PAINTING Bero Architecture PLLC 099123 - 3 14060.099123.21614 1. Benjamin Moore & Co.; Super Spec Interior Latex (Eggshell) (C274). 2.5 CLEANING MATERIALS A. Water Cleaning: Clean with water and bristle brush. B. Job-Mixed Detergent Solution: Mix 2 cups of tetrasodium polyphosphate, 1/2 cup of laundry detergent, 5 quarts of 5-percent sodium hypochlorite bleach, and 15 quarts of warm water for each 5 gallon of solution required. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work. B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows: 1. Gypsum Board: 12 percent. 2. Plaster: 12 percent. C. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers. D. Proceed with coating application only after unsatisfactory conditions have been corrected. 1. Application of coating indicates acceptance of surfaces and conditions. 3.2 CLEANING A. Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease, and incompatible paints and encapsulants. 1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce paint systems indicated. 2. Remove dust, dirt, oil, grease, and sticky residue with job-mixed detergent solution; rinse thoroughly and allow to dry. Protect adjacent surfaces from cleaning process by masking surfaces. Detergent can damage metal, painted surfaces, stained wood, and glass. 3. For heavy-duty cleaning where job-mixed detergent solution does not adequately remove residue, mix 1 cup tetrasodium polyphosphate with 3 quarts water. Apply in a limited amount to substrate and protect adjacent construction. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR PAINTING Bero Architecture PLLC 099123 - 4 14060.099123.21614 3.3 PREPARATION A. Comply with manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual" applicable to substrates and paint systems indicated. B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting. 1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection if any. C. Surface Preparation: Clean and prepare surfaces to be painted according to manufacturer’s written instructions for each particular substrate condition and as specified. 1. Provide barrier coats over incompatible primers or remove and re-prime. D. Material Preparation: 1. Maintain containers used in mixing and applying paint in a clean condition, free of foreign materials and residue. 2. Stir material before application to produce a mixture of uniform density. Stir as required during application. Do not stir surface film into material. If necessary, remove surface film and strain material before using. E. Scheduled Painting: Apply first coat to surfaces that have been cleaned, pretreated, or otherwise prepared for painting as soon as practical after preparation and before subsequent surface deterioration. 1. If undercoats, stains, or other conditions show through final coat of paint, apply additional coats until paint film is of uniform finish, color, and appearance. 3.4 APPLICATION A. Application Procedures: Apply paints and coatings by brush, roller, spray, or other applicators according to manufacturer’s written instructions. All spray work must be back-brushed or rolled, and all unpainted surfaces protected from overspray. B. Minimum Coating Thickness: Apply paint materials no thinner than manufacturer’s recommended spreading rate. Provide total dry film thickness of the entire system as recommended by manufacturer. C. Prime Coats: Before applying finish coats, apply a prime coat, as recommended by manufacturer, to material that is required to be painted or finished and that has not been prime coated by others. Re-coat primed and sealed surfaces where evidence of suction spots or unsealed areas in first coat appears, to ensure a finish coat with no burn-through or other defects due to insufficient sealing. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration INTERIOR PAINTING Bero Architecture PLLC 099123 - 5 14060.099123.21614 D. Pigmented (Opaque) Finishes: Completely cover surfaces as necessary to provide a smooth, opaque surface of uniform finish, color, appearance, and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections will not be acceptable. 3.5 CLEANING AND PROTECTION A. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by Architect, and leave in an undamaged condition. B. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces. C. At the end of each workday, remove empty cans, rags, rubbish, and other discarded paint materials from Project site. D. Provide “Wet Paint” signs to protect newly painted finishes. After completing painting operations, remove temporary protective wrappings provided by others to protect their work. 1. After work of other trades is complete, touch up and restore damaged or defaced painted surfaces. Comply with procedures specified in PDCA P1. 3.6 INTERIOR PAINTING SCHEDULE A. Gypsum Board and Plaster Substrates: 1. Institutional Low-Odor/VOC Latex System: a. Prime Coat: Primer, Latex, Water-based; Fresh Start High-Hiding All Purpose Primer. b. Intermediate Coat: Latex, interior, institutional low odor/VOC, matching topcoat. c. Topcoat: Latex, interior, institutional low odor/VOC, Super Spec Interior Latex (Eggshell). B. Ceilings, Gypsum Board and Plaster: 1. Institutional Low-Odor/VOC Latex System: a. Prime Coat: Primer, Latex, Water-based; Fresh Start High-Hiding All Purpose Primer. b. Intermediate Coat: Latex, flat, matching topcoat. c. Topcoat: Latex, interior, flat; Waterborne Ceiling Paint (Flat). END OF SECTION 099123   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRE PROTECTION Bero Architecture PLLC 211000 - 1 14060.211000.21614 SECTION 211000 – FIRE PROTECTION PART 1 GENERAL 1.01 SUMMARY: A. Inside piping, including sprinkler heads, valves, hangers and supports, sleeves, and accessories. B. This Contractor shall include all piping, valves and devices necessary to provide protection system as shown in accordance with the requirements of NFPA Standard 13, Installation of Sprinkler Systems. 1.02 CODES AND REGULATIONS A. Comply with all applicable rules and regulations of the municipal laws and ordinances and latest revisions thereof. All work shall be done in full conformity with the requirements of all authorities having jurisdiction. Modifications required by the above authorities will be made without additional charges to the Owner. Where alterations to and/or deviations from the Contract Documents are required by the authorities, report the requirements to the Architect and secure approval before work is started. B. Work shall comply with codes and laws of New York State. These include but are not limited to: Building Code of New York State Fire Code of New York State C. The design, materials, and installation shall where applicable comply minimally with the following standards: NFPA 13 National Electric Code (NFPA 70) New York State Division of Housing and Community Renewal Design Handbook New York State Department of Heath Cross Connection Control D. Organizations that have applicable standards include: ANSI American National Standards Institute ASME American Society of Mechanical Engineers ASTM American Society for Testing Materials FM FM Global/FM Approved OSHA Occupational Safety and Health Act NEMA National Electrical Manufacturers Association NFPA National Fire Protection Association UL Underwriters Laboratories, Inc. 1.03 QUALITY ASSURANCE Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRE PROTECTION Bero Architecture PLLC 211000 - 2 14060.211000.21614 A. Sprinkler equipment and installations shall be in accordance with recommendations of Owner's Underwriters and approved by local Fire Commissioner. All components to be FM and U.L. Listed. B. Equipment and installation to meet requirements of NFPA No. 13 - Standard for the Installation of Sprinkler Systems. 1.04 SUBMITTALS A. Submit shop drawings and product data. B. Produce complete working drawings as defined by NFPA Standard 13 for review by local code officials and the owners insurance company if required. PART 2 PRODUCTS 2.01 ACCEPTABLE MANUFACTURES A. Manufacturer and Type: Tyco or equal. 2.02 SPRINKLER HEADS A. Temperature rating on fusible links shall suit specific hazard areas. Provide temperature rating, response, coverage and K-factor appropriate for the location. Unless otherwise required or noted – Ordinary temperature, ½”, 5.6 K Factor. B. Standard Coverage Concealed –Tyco RFII or similar D. Standard Coverage Sidewall – Horizontal semi-recessed with escutcheon. E. Sprinkler Finish: Finished Spaces – as specified by owner 2.03 PIPING A. Black Steel, UL listed, ASTM A-153, schedule 40, schedule 10 (2” and larger only). 2-1/2” – 3” – Schedule 40 1” – 2” - Schedule 40 B. Threaded fittings – Cast Iron Class 125, ANSI 16.4. Malleable Iron Class 300, ANSI B16.3. C. Grooved Piping - 2-1/2” minimum. Victaulic FireLock or equal. 1. Couplings – 300 PSI, rigid coupling, UL listed. Victaulic Style 005 2. Fittings – Ductile Iron. D. Do not use bushings or reducing couplings. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRE PROTECTION Bero Architecture PLLC 211000 - 3 14060.211000.21614 PART 3 EXECUTION 3.01 INSTALLATION A. Run piping concealed above furred ceilings and in joists to minimize obstructions. Expose only heads. B. Provide on wall near sprinkler valve, cabinet containing extra sprinkler heads of various styles, quantities as required, and wrench suitable to each head type. C. Install system in accordance with NFPA 13. Provide all accessories required (drains, test connections, etc.)   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GENERAL PROVISIONS FOR Bero Architecture PLLC 230000 - 1 HVAC WORK (MECHANICAL) 14060.230000.21614 SECTION 230000 - GENERAL PROVISIONS FOR HVAC WORK (MECHANICAL) PART 1 GENERAL 1.01 GENERAL PROVISIONS A. Mechanical work can encompasses HVAC and others as defined elsewhere in the contract documents. Provide materials and labor required for complete working systems as shown on drawings and/or specified. B. Coordinate with other trades. The contractor shall coordinate work with other trades to insure the coordination of the installation of their work. Coordination includes review of other trade drawings that may affect the work and meetings with other trades. C. The contractor shall be experienced in the work to be performed and knowledgeable of applicable codes and standards. The contractor is expected to provide complete work in accordance with the drawings, specifications and generally accepted methods of construction. 1.02 DRAWINGS AND SPECIFICATIONS A. The plans are diagrammatic and indicate only the sizes and general arrangement of piping and equipment; exact locations of all elements shall be determined as work progresses, in cooperation with the work of other trades. It is not intended to show every item of work or minor piece of equipment, but every item shall be furnished and installed without additional remuneration as necessary to complete the system in accordance with the best practice of the trade. 1.03 MATERIALS AND EQUIPMENT A. Manufacturers and model numbers specified on the drawings are the standard of design with regard to performance, capacity and physical properties. B. Submit specific product data for equipment whether the specified manufacturer is used or a substitute is used. Submit installation data and wiring diagrams (if applicable). C. Unless specifically noted, the equipment specification is not intended to preclude the substitution of material and equipment by other manufacturers. The contractor is responsible for changes due to substitutions (electrical, capacity, support, etc.) D. If other manufacturers are named, it does not relieve the contractor from supplying equipment or materials that meet the design intent and from the capacity, electrical, and physical requirements of the installation. A named alternate manufacturer does not mean that the alternate manufacturer’s standard equipment meets the specific criteria for the project. Named alternate manufacturers does not preclude the consideration of other manufacturers. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GENERAL PROVISIONS FOR Bero Architecture PLLC 230000 - 2 HVAC WORK (MECHANICAL) 14060.230000.21614 E. Unless modified by the drawings and specifications, install equipment as required by the manufacturer’s instructions. 1.03 CODES AND REGULATIONS A. Comply with all applicable rules and regulations of the municipal laws and ordinances and latest revisions thereof. All work shall be done in full conformity with the requirements of all authorities having jurisdiction. Modifications required by the above authorities will be made without additional charges to the Owner. Where alterations to and/or deviations from the Contract Documents are required by the authorities, report the requirements to the Architect and secure approval before work is started. B. Work shall comply with codes and laws of New York State. These include but are not limited to: Building Code of New York State Mechanical Code of New York State Energy Conservation Construction Code of New York State Fire Code of New York State C. The materials, and installation shall where applicable comply minimally with the following standards: ANSI A117.1 ASHRAE Handbooks National Electric Code (NFPA 70) NFPA 90A SMACNA HVAC Metal Duct Standards D. Organizations that have applicable standards include: AGA American Gas Association ANSI American National Standards Institute ASHRAE American Society of Heating, Refrigerating and Air-Conditioning Engineers ASME American Society of Mechanical Engineers ASTM American Society for Testing Materials NEMA National Electrical Manufacturers Association NFPA National Fire Protection Association OSHA Occupational Safety and Health Act SMACNA Sheet Metal and Air-Conditioning Contractors National Association UL Underwriters Laboratories, Inc. 1.04 RECORD DRAWINGS Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GENERAL PROVISIONS FOR Bero Architecture PLLC 230000 - 3 HVAC WORK (MECHANICAL) 14060.230000.21614 A. The Contractor shall keep an accurate location record of all underground and concealed piping, and of all changes from the original design. He is required to furnish this information to the Owner prior to his application for final payment. B. At completion of the project, all changes and deviations from the Contract Documents shall be recorded by the Contractor. 1.05 RENOVATIONS A. Contractors shall verify exact existing conditions in the field and coordinate new work with these conditions. B. Contractors shall work with utilities and/or the building owners to find shut-off valves. Finding these valves or providing alternative means of shut-off remains the contractors responsibility. C. When removing materials or accessing hidden materials the contractor is responsible for restoring surfaces to match the existing adjacent surfaces. 1.06 BALANCING A. The environmental systems including all equipment, apparatus and distribution systems shall be tested and balanced in accordance with the National Environmental Balancing Bureau (NEBB) Procedural Standards for Testing Adjusting and Balancing of Environmental Systems published by NEBB, current edition. B. Submit balancing report. Report shall be on NEBB reporting forms. 1.07 SUPPORTS AND SEALANT A. Provide all required support for piping, duct and equipment. Provide appropriate vibration isolation for equipment. B. Provide sleeves for piping through walls and floor. Provide sealant for the space between the sleeve and the pipe for fire and smoke walls/partitions/floors, exterior walls and floors, waterproof walls and floors. C. Provide sealant and fire stopping for duct and piping. Sealant and fire stopping for fire rated walls/partitions/floors shall be listed for the use. D. Unless otherwise noted, run piping and duct as neatly and unobtrusively as possible. Where applicable run as high as possible. Coordinate with other trades. END OF SECTION 230000   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration VALVES Bero Architecture PLLC 230523 - 1 14060.230523.21614 SECTION 230523 - VALVES PART 1 GENERAL 1.01 SUMMARY A. Provide valves. 1.02 SUBMITTALS A. Submit product information. If product to be used is listed by manufacturer and Model No. specified herein, catalog cut is not required. B. Submit valve schedule which includes valve type for each use. 1.03 QUALITY ASSURANCE A. Valves, pressure reducing and pressure relief devices shall conform to the specification, regulations and requirements of all Agencies (Federal, State, and Local), codes, and associations having jurisdiction governing construction, sizing and application and location. B. All materials and dimensions shall conform to applicable ANSI and ASTM standards. PART 2 PRODUCTS 2.01 GENERAL A. Provide valves as shown on drawings. B. Provide valves of temperature and pressure ratings exceeding conditions under which they will operate. (WOG - Water, Oil, Gas; SWP Steam Working Pressure). 2.02 SERVICE VALVES A. Ball Valves 1. 1/2"- 2-1/2"; 150 psi SWP, 400 psi WOG. Bronze, two piece body, TFE seats, brass ball, screwed or solder end, balancing stop plate. Hammond Fig. 8901 or Fig. 8911, Jamesbury Series 3000, Apollo 70-100, or 70- 200, Watts B-6000. PART 3 EXECUTION 3.01 INSTALLATION Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration VALVES Bero Architecture PLLC 230523 - 2 14060.230523.21614 A. General 1. Install valves at locations as shown on drawings or specified. Provide line size valves unless otherwise noted. 2. Install valves as per manufacturer's recommendation. END OF SECTION 230523 Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 230580 - 1 MECHANICAL SYSTEMS 14060.230580.21614 SECTION 230580 - FIRESTOPPING FOR MECHANICAL SYSTEMS PART 1 - GENERAL 1.01 SUMMARY A. Provide listed firestop at penetrations of rated walls, partitions, ceilings, floors and assemblies. 1.02 DEFINITIONS A. Firestopping: Material or combination of materials used to retain integrity of fire-rated construction by maintaining an effective barrier against the spread of flame, smoke, and hot gases through penetrations in fire rated wall and floor assemblies. 1.03 REFERENCES A. Test Requirements: ASTM E 814, "Standard Method of Fire Tests of Through Penetration Fire Stops" B. Test Requirements: UL 1479, “Fire Tests of Through-Penetration Firestops” C. Underwriters Laboratories (UL) of Northbrook, IL publishes tested systems in their "FIRE RESISTANCE DIRECTORY" that is updated annually. 1. UL Fire Resistance Directory: a. Firestop Devices (XHJI) b. Fire Resistance Ratings (BXRH) c. Through-Penetration Firestop Systems (XHEZ) d. Fill, Voids, or Cavity Material (XHHW) e. Forming Materials (XHKU) D. International Firestop Council Guidelines for Evaluating Firestop Systems Engineering Judgments E. Inspection Requirements: ASTM E 2174, “Standard Practice for On-site Inspection of Installed Fire Stops.” F. ASTM E 84, “Standard Test Method for Surface Burning Characteristics of Building Materials.” 1.04 QUALITY ASSURANCE A. A manufacturer's direct representative to be on-site during initial installation of firestop systems to train appropriate contractor personnel in proper selection and installation procedures. This will be done per manufacturer's written recommendations published in their literature and drawing details. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 230580 - 2 MECHANICAL SYSTEMS 14060.230580.21614 B. Firestop System installation must meet requirements of ASTM E 814 or UL 1479 tested assemblies that provide a fire rating equal to that of construction being penetrated. C. Proposed firestop materials and methods shall conform to applicable governing codes having local jurisdiction. 1.05 SUBMITTALS A. Submit Product Data: Manufacturer’s specifications and technical data for each material including the composition and limitations, documentation of UL firestop systems to be used and manufacturer's installation instructions. B. Submit material safety data sheets provided with product delivered to job-site. PART 2 - PRODUCTS 2.01 FIRESTOPPING, GENERAL A. Provide firestopping composed of components that are compatible with each other, the substrates forming openings, and the items, if any, penetrating the firestopping under conditions of service and application, as demonstrated by the firestopping manufacturer based on testing and field experience. B. Provide components for each firestopping system that are needed to install fill material. Use only components specified by the firestopping manufacturer and approved by the qualified testing agency for the designated fire-resistance-rated systems. 2.02 ACCEPTABLE MANUFACTURERS A. Subject to compliance with through penetration firestop systems (XHEZ) listed in Volume II of the UL Fire Resistance Directory, provide products of the following manufacturers as identified below: 1. Hilti, Inc., Tulsa, Oklahoma 800-879-8000/www.us.hilti.com 2. Approved equal. 2.03 MATERIALS A. Use only firestop products that have been UL 1479 or ASTM E 814 tested for specific fire- rated construction conditions conforming to construction assembly type, penetrating item type, annular space requirements, and fire-rating involved for each separate instance. B. Cast-in place firestop devices are installed prior to concrete placement for use with noncombustible and combustible pipes (closed and open systems), and conduit penetrating concrete floors, the following products are acceptable: Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 230580 - 3 MECHANICAL SYSTEMS 14060.230580.21614 1. Hilti CP 680 Cast-In Place Firestop Device a. Add Aerator adaptor when used in conjunction with aerator (“sovent”) system. 2. Hilti CP 681 Tub Box Kit for use with tub installations. 3. Hilti CP 682 Cast-In Place Firestop Device for use with noncombustible penetrants C. Sealants, caulking materials, or foams for use with non-combustible items including steel pipe, copper pipe, rigid steel conduit and electrical metallic tubing (EMT), the following products are acceptable: 1. Hilti FS-ONE Intumescent Firestop Sealant 2. Hilti CP 604 Self-leveling Firestop Sealant 3. Hilti CP 620 Fire Foam 4. Hilti CP 606 Flexible Firestop Sealant 5. Hilti CP 601s Elastomeric Firestop Sealant D. Intumescent sealants, caulking materials for use with combustible items (penetrants consumed by high heat and flame) including insulated metal pipe, PVC jacketed, flexible cable or cable bundles and plastic pipe, the following products are acceptable: 1. Hilti FS-ONE Intumescent Firestop Sealant PART 3 - EXECUTION 3.01 PREPARATION A. Verification of Conditions: Examine areas and conditions under which work is to be performed and identify conditions detrimental to proper or timely completion. 1. Verify penetrations are properly sized and in suitable condition for application of materials. 2. Surfaces to which firestop materials will be applied shall be free of dirt, grease, oil, rust, laitance, release agents, water repellents, and any other substances that may affect proper adhesion. 3. Provide masking and temporary covering to prevent soiling of adjacent surfaces by firestopping materials. 4. Comply with manufacturer's recommendations for temperature and humidity conditions before, during and after installation of firestopping. 5. Do not proceed until unsatisfactory conditions have been corrected. 3.02 COORDINATION Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 230580 - 4 MECHANICAL SYSTEMS 14060.230580.21614 A. Coordinate location and proper selection of cast-in-place Firestop Devices with trade responsible for the work. Ensure device is installed before placement of concrete. B. Responsible trade to provide adequate spacing of field run pipes to allow for installation of cast-in-place firestop devices without interferences. 3.03 INSTALLATION A. Regulatory Requirements: Install firestop materials in accordance with UL Fire Resistance Directory. B. Manufacturer's Instructions: Comply with manufacturer's instructions for installation of through-penetration joint materials. 1. Seal all holes or voids made by penetrations to ensure an air and water resistant seal. 2. Consult with mechanical engineer, project manager, and damper manufacturer prior to installation of UL firestop systems that might hamper the performance of fire dampers as it pertains to duct work. 3. Protect materials from damage on surfaces subjected to traffic. 3.04 FIELD QUALITY CONTROL A. Examine sealed penetration areas to ensure proper installation before concealing or enclosing areas. B. Keep areas of work accessible until inspection by applicable code authorities. C. Inspection of through-penetration firestopping shall be performed in accordance with ASTM E 2174, “Standard Practice for On-Site Inspection of Installed Fire Stops” or other recognized standard. D. Perform under this section patching and repairing of firestopping caused by cutting or penetrating of existing firestop systems already installed by other trades. END OF SECTION Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPING AND EQUIPMENT Bero Architecture PLLC 230719 - 1 INSULATION 14060.230719.21614 SECTION 230719 - PIPING AND EQUIPMENT INSULATION PART 1 GENERAL 1.01 SUMMARY: A. The work covered by this specification consists of furnishing all labor, equipment, materials and accessories, and performing all operations required, for the correct installation of insulation on all piping, fittings, valves, controls and all other necessary items connected into the system subject to condensation or loss of heat. 1.02 QUALITY ASSURANCE A. Insulation Materials: Insulation materials must be manufactured at facilities certified and registered with an approved registrar to conform to ISO 9001 Quality Standard. 1. Pipe insulation shall be preformed and furnished in standard lengths with ends cut square, conforming with the dimensional requirements of ASTM C 585. 2. All insulating products shall have a 25/50 flame spread/smoke developed rating as tested in accordance with ASTM E 84. B. Insulation Requirements: All materials, products, thicknesses and installation shall conform with ASHRAE Standards and Energy Conservation Construction Code of New York State. C. Workmanship: All insulation to be installed by a licensed applicator and applied in accordance with the manufacturer’s recommendations. 1. All work shall comply with all applicable federal, state and local codes and laws. This shall include, but shall not be limited to, the Occupational Safety and Health Act. 2. All work shall conform with accepted industry and trade standards for commercial and industrial insulations. 3. Surfaces to be insulated shall be clean and free of dirt, scale, moisture, oil and grease. 1.03 SUBMITTALS A. Submit shop drawings which indicate complete material data, a list of materials proposed for this project and indicate thickness of material for individual services. 1.04 JOB CONDITIONS A. Deliver material to job site in original non-broken factory packaging, labeled with manufacturer's Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPING AND EQUIPMENT Bero Architecture PLLC 230719 - 2 INSULATION 14060.230719.21614 density and thickness. B. Perform work at ambient and equipment temperatures as recommended by the adhesive manufacturer. PART 2 PRODUCTS 2.01 ACCEPTABLE MANUFACTURERS A. Fiberglass Insulation 1. Owens-Corning 2. Johns Manville Corp. 3. Knauf B. PVC Fitting Covers 1. Zeston or equal 2.02 GENERAL A. All "K" factors are expressed in BTU/in./hr./sq.ft. 2.03 MATERIALS AND COMPONENTS A. Piping: All piping shall be insulated with a preformed fiber glass pipe insulation, complying with ASTM C 547, Class 3 (to 850°F [454°C]), rigid, molded pipe insulation, noncombustible. "K" value at 75o, maximum 0.23. All-Service (ASJ) Vapor-Retarder Jacket: A white, kraft paper, reinforced with a glass fiber yarn and bonded to an aluminum foil, with self sealing longitudinal closure laps (SSL) and butt strips. B. Fittings Covers: Fitting cover system shall be a complete factory-supplied system consisting of premolded PVC covers and fiberglass inserts precut to specific size, shape and thickness, complete with accessories to mechanically fasten system to adjacent pipe covering. Zeston 2000 PVC insulated fitting cover. PART 3 EXECUTION 3.01 GENERAL A. Insulation shall be installed in a workmanlike manner by workmen regularly engaged in this type of work. B. Hot - Insulate all hot piping and equipment (heat exchangers, etc.). Insulation may be broken at support. Pumps, flanges, expansion tanks, valves may be excluded. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPING AND EQUIPMENT Bero Architecture PLLC 230719 - 3 INSULATION 14060.230719.21614 Cold - Insulate all cold piping and equipment. Insulation/vapor barrier shall be continuous at support, flanges, wall penetrations, etc. Insulate pumps, valves, air separators, etc. Expansion tanks, meters, backflow preventers may be excluded. C. A complete moisture and vapor seal shall be provided on cold surfaces where vapor barrier jackets or coatings are required. Anchors, hangers, and other projections shall be insulated and vapor sealed to prevent condensation. D. Pipe insulation shall be continuous through walls and floor openings except where walls or floors are required to be firestopped or required to have a fire resistance rating. E. All insulated piping shall be supported by hangers with metal shields to be installed with the piping. Inserts shall be provided and installed between the pipe and the shields. Inserts shall consist of rigid pipe insulation equal in thickness to the adjoining insulation and shall be vapor sealed into the adjoining insulation. Where hangers are in direct contact with low temperature piping the hanger and supporting rod shall be wrapped with foil-faced blanket insulation and vapor sealed. Hanger rod insulation and vapor barrier shall extend up the rod a minimum distance equal to the diameter of the pipe. Galvanized metal shields shall be applied between hangers or supports and the pipe insulation. Shields shall be formed to fit the insulation and shall extend up to the centerline of the pipe and the length specified for the insulation hanger inserts less 4" (102 mm) to allow for vapor retarding butt joints on each side of the shields. F. The word "concealed" as used in this specification refers to insulation in furred spaces, pipe and duct shafts, unheated spaces immediately below roof, unexcavated space, crawlspaces, ceiling spaces, and tunnels. The word "exposed" refers to insulation in all other areas. G. Insulate fittings and valves. Do not insulate unions, flanges, flexible connections and expansion joints, except on chilled water and cold water lines or lines subject to condensation which shall also be furnished with removable plastic jackets. Terminate insulation neatly with molded PVC insulated end caps. H. Finish insulation neatly at hangers, supports, and other protrusions. All raw or cut ends of insulation shall be finished with a mastic suitable for the purpose. I. Locate insulation or cover seams in least visible locations. J. Adhesives, mastics and coatings shall be applied at the manufacturer’s recommended minimum coverage per gallon. K. At all points of connection, of new piping to existing, repair insulation on existing piping at new joints. 3.02 COLD PIPING/EQUIPMENT APPLICATION Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPING AND EQUIPMENT Bero Architecture PLLC 230719 - 4 INSULATION 14060.230719.21614 A. Piping: Butt all joints firmly together and smoothly secure all jacket laps and joint strips with lap adhesive or manufacturers recommended contact adhesive for elastomeric foams. Self-Seal Lap: Apply according to manufacturer's published recommendations. Ends of pipe insulation shall be sealed off with a vapor barrier coating at all fittings and valves and at intervals of 21 feet on continuous runs of pipe. B. Fittings & Valves: Insulate with molded fiberglass fittings; segments of pipe covering; or with firmly compressed foil-faced fiberglass blanket. Secure in place with 20 gauge corrosion- resistant wire and apply a smoothing coat of insulating cement. Cover with PVC covers shall overlap the adjoining pipe insulation and jackets and shall be sealed at all edges with vapor barrier adhesive. The tape shall overlap the jacket and the cover at least one inch. 3.03 HOT PIPING APPLICATION (UP TO 500oF) A. Piping: Butt all joints firmly together and smoothly secure all jacket laps and joint strips with lap adhesive. Flare-type staples at 4" spacings may be used for concealed work. Self-Seal Lap: Apply according to manufacturer's published recommendations. B. Fittings: Insulate with molded fiberglass fittings; segments of pipe covering; or with firmly compressed foil-faced fiberglass blanket. Secure in place with 20 gauge corrosion-resistant wire and apply a smoothing coat of insulating cement. Cover with PVC covers shall overlap the adjoining pipe insulation and jackets and shall be sealed at all edges with vapor barrier adhesive. The tape shall overlap the jacket and the cover at least one inch. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPING AND EQUIPMENT Bero Architecture PLLC 230719 - 5 INSULATION 14060.230719.21614 3.09 INSULATION THICKNESS SCHEDULE Piping Pipe Sizes (in.) Insulation Thickness(in.) Domestic Cold Water Up to 1" 0.5 1-1/4" and larger 1 Hot Water Up to 1-1/2" 1.5 Steam Up to 1-1/2" 1.5 END OF SECTION 230719   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPE AND PIPE FITTINGS Bero Architecture PLLC 232100 - 1 14060.232100.21614 SECTION 232100 - PIPE AND PIPE FITTINGS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish and install all piping systems indicated on drawings, and as specified hereinafter. The piping runs indicated are diagrammatic and intended to show the runs, risers, etc., which are required. It is not the intent of the plans to show each offset, which may be required due to job conditions. Install the piping in as close conformance to the plans as possible, furnishing any additional offsets, drops, risers, etc., which may be required. B. This Contractor shall carefully coordinate his work with the work of other contractors so as to avoid unnecessary changes. C. Should Architect/Engineer's details, field conditions, change of equipment or shop drawing information necessitate an important rearrangement, report same to Engineer before proceeding with work and obtain written approval or revised print. 1.02 SUBMITTALS A. Piping installations shall be approved as required by the municipality having jurisdiction over the site of the installation. 1.03 QUALITY ASSURANCE A. All pipe and tubing shall be new, first quality, full weight, free from defects, straight, true and round. Each length of pipe and each fitting shall be marked or stamped with manufacturer's name. Bundled pipe shall be properly tabbed. B. All pipe and fittings shall conform to the latest standards of A.S.A. Code for pressure piping. C. All products shall comply with standards for low volatile organic compound emissions. PART 2 - PRODUCTS 2.01 STEEL PIPE AND FITTINGS A. Steel pipe 1. 1/2"- 1-1/2" ASTM A53 Grade B Type F. 2. 2"- 12" ASTM A53 Grade B Type E or Type S. B. Welding Fittings 1. Steel, butt weld; ASTM A234 Grade WPB, ANSI B 16.9. All elbows shall be long radius unless otherwise noted. C. Screwed End Fittings Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPE AND PIPE FITTINGS Bero Architecture PLLC 232100 - 2 14060.232100.21614 2. Standard wt. malleable iron, black, banded; standard wt. 150 WSP, ANSI B16.3. 3. Extra heavy weight, malleable iron, 300lb. Class D. Unions 1. 1/2"- 3" malleable iron, black, 250 lb., screwed, brass to iron or brass to brass seats. E. Flanges 1. 2-1/2"- 12"; steel, ASTM A105, 150 lb., ANSI B16.5 slip-on (preferred) or welding neck type, raised face (when mating with 125lb. C1 flange, a flat face flange is required). 2.02 COPPER TUBING AND FITTINGS A. Copper water tube, Types K, L and ASTM B88 (hard Temper unless otherwise specified). B. Copper tube, Type DWV, ASTM B306. C. 1/8"- 7/8" OD copper tubing; ASTM B75, seamless, annealed. D. Fittings: 1. Wrought copper tube fitting, solder type ANSI B16.22. 2. Cast brass water tube fitting, solder type, ANSI B16.18. 3. Wrought copper SWV fittings, solder type, ANSI B16.29. E. Unions, 1/2"- 2"; brass water tube fitting, ground joint, screwed. F. Flanges; brass water tube fitting, solder, flat face, ANSI B16-5 Class 150. 2.03 JOINING AND SEALANT MATERIALS A. Thread Sealant 1. Teflon thread sealer B. Solder: Solid wire type - 95% tin - 5% antimony; ASTM B32-95TA or approved equal. C. Solder flux: Harris Co. Stay-Clean D. Flange Gasket Material 1. Waterproofed non-asbestos designed for the temperatures and pressures of the piping system in which installed. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPE AND PIPE FITTINGS Bero Architecture PLLC 232100 - 3 14060.232100.21614 E. Modular Mechanical Seal; Watertight Mechanical Seal. Thunderline Corp. Link-Seal. 2.06 PIPE SLEEVES A. Pipe sleeves except where otherwise specified for a particular herein or in individual work sections, shall be of 20 gauge galvanized sheet steel with a lock seam joint. B. Sleeves shall be of schedule 40 galvanized steel pipe in the following locations: waterproof walls and floors, outside walls, foundation walls, floors having a floor drain, floors over mechanical equipment, and floors on grade. C. Exceptions to the above are core drilled holes in foundation walls and non-waterproof interior walls and floors where no sleeves are required. D. Sleeves in fire rated partitions and floors shall be packed with a UL listed fire stop. PART 3 - EXECUTION 3.01 PIPING INSTALLATION A. General 1. Work of this section shall start as soon as building construction permits and furnish and insert all pipe and other hangers supports, including planning of work, purchasing materials for prompt delivery and supply sufficient labor to complete the work as rapidly as the progress of the building allows. 2. All measurements, distances, levels shall be verified at the building. 3. Open ends of pipes and equipment shall be properly capped during installation to keep dirt and other foreign materials out of the system. 4. Install piping properly while allowing maximum head room and allowance for the swing of doors and equipment. 5. Install piping with approved cold strain. Make allowance for the expansion and contraction of piping. 6. Where furred spaces are indicated, keep pipes as close to structural members as possible so as to require minimum furring. In the case of an exterior wall, piping shall be installed interior to the insulation so as not to break the continuity of the insulation membrane. 7. Unless otherwise indicated, conceal piping in building construction, i.e., above suspended ceiling. Install and test piping so as not to cause delay to work of other trades. 8. Provide easy and safe access to valves and other apparatus requiring operation. Provide access panels as required. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPE AND PIPE FITTINGS Bero Architecture PLLC 232100 - 4 14060.232100.21614 9. Do not install any bullheaded tees. 10. Cut all pipe accurately to measurements established at building and work into place without springing or forcing. Install all pipe so that it may expand and contract freely without change to any other work or to itself. All pipes, after having been cut, shall be reamed to remove burrs. All threads shall be clean cut and tapered. All piping shall be cleaned free of pipe cutting oil prior to erection. All change in direction shall be made with fittings, not with bent pipe, and equipment shall be properly capped and plugged during installation to keep dirt or other foreign materials out of the system. Install piping parallel with building surfaces and other piping, maintaining maximum head room, properly spaced, so as to provide clearance for covering. 11. All water connections to equipment and control valves shall have brass-ground joint unions or flanges. 12. Close nipples will not be accepted. Use shoulder nipples with minimum unthreaded portion not less than 1/2". Use extra heavy pipe where shoulder portion is less than 1-1/2". 13. Couplings will be permitted only where full lengths of pipe do not reach objective. Use only extra heavy couplings of same material as pipe where required. 14. Furnish and install pipe anchors where indicated on drawings and where required. The anchors shall be constructed of heavy steel shapes, welded to pipe and secured to concrete and/or structural steel. 15. Provide die-electric unions between all copper (brass) to steel connections. Watts Series 3000 or equal. B. Pipe Joints 1. Square cut and ream ends of pipe, nipples, and tubing. 2. Install a gasket for each flanged joint. 3. Use an approved teflon pipe thread tape on all screwed joints. 4. Provide the appropriate die-electric connector between dissimilar pipe joints. 5. Use grooved mechanical couplings only in accessible locations. C. Domestic Water Piping 1. Cold and hot water piping shall be installed with a pitch to be completely drainable. Provide a valved hose connection at all low points. Provide a manual air vent at all high points. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPE AND PIPE FITTINGS Bero Architecture PLLC 232100 - 5 14060.232100.21614 2. Provide a gate or ball valve on each branch to each set of fixtures, units or equipment. 3. Provide complete cold and hot domestic water system from building entrance to each fixture. 4. Flush entire system prior to connection of fixtures. See Section 3.03. D. Drainage Piping 1. Install horizontal piping at a pitch as required by the National Plumbing Code or as required by state and local codes. 2. Vents through the roof shall be full vent riser size with a minimum pipe size of 3". Extended vent 12" above roof. F. Water and Ethylene Glycol Piping 1. Install all piping to allow complete drainage. 2. Install a valved drain with a hose bib connection at low points, sections separated by valves, and the low point of down feed convectors and radiators. 3. Install manual air vents at all high points. 4. Make final connections to equipment with unions otherwise noted. Exceptions- Fintube. 5. Install valves at al branches unless otherwise noted or specified. 3.02 PIPE SLEEVE INSTALLATION A. General 1. Set sleeves, obtain review of their locations in ample time to permit pouring of concrete or progressing of other construction work as scheduled. 2. Sleeve Size a. Inside diameter of sleeve or core drilled holes to be 1/2 inch bigger than outside diameter of the pipe, or insulation if the pipe is to be insulated. Coordinate sleeve size with space required by modular mechanical type seal if used. b. The length of the sleeve in walls and partitions is to be equal to the finished thickness of the wall or partition. c. For floors the sleeve should be 1/2 inch longer than the thickness of the floor. Extend the sleeve 1/2 inch above finished floor. 3. Packing of Sleeves and Core Drilled Holes Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration PIPE AND PIPE FITTINGS Bero Architecture PLLC 232100 - 6 14060.232100.21614 a. Pack sleeves in exterior masonry walls and waterproof walls with modular mechanical type seal. b. Fill space around pipes through floors and fire rated walls and partitions with a UL listed fire sealant. 3.03 FLOOR, WALL AND CEILING ESCUTCHEONS A. Provide a solid, polished chrome plated, cast brass escutcheon with set screw for all un- insulated piping passing through floors, walls and ceilings of finished areas. B. Provide a solid cast iron escutcheon with set screw for un-insulated piping passing through floors, walls, and ceilings of unfinished areas. 3.04 PIPE SCHEDULE A. Cold Water (above ground), 125 psig and less 1. 4" and less; Type L copper tubing with solder fittings. B. Domestic Hot Water Supply and Recirculation, 125 psig and less. 1. 4" and less; Type L, copper tubing with solder fittings. C. Heating Hot Water Supply, Return - 75 psig and less. 1. ½” – 3”; Type L copper with solder fittings. 3.05 TESTING A. Test all piping as specified below before installation of insulation and connection to equipment. Perform test in a timely manner to allow building construction to continue. 1. Water piping; provide hydrostatic test at 100 psi for one hour. END OF SECTION 232100 Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GENERAL PROVISIONS Bero Architecture PLLC 260000 - 1 FOR ELECTRICAL WORK 14060.260000.21614 SECTION 260000 - GENERAL PROVISIONS FOR ELECTRICAL WORK PART 1 GENERAL 1.01 GENERAL PROVISIONS A. Provide materials and labor required for complete working systems as shown on drawings and/or specified. B. Coordinate with other trades. The contractor shall coordinate work with other trades to insure the coordination of the installation of their work. Coordination includes review of other trade drawings that may affect the work and meetings with other trades. Do not provide wiring to equipment supplied by other contractors or subcontractors until the actual location and electric requirements of the equipment has been verified. The electrical contractor shall be responsible for actively pursuing this information. 1.02 INSTALLATION AND WORKMANSHIP A. The plans are diagrammatic and indicate only the sizes and general arrangement of piping and equipment; exact locations of all elements shall be determined as work progresses, in cooperation with the work of other trades. It is not intended to show every item of work or minor piece of equipment, but every item shall be furnished and installed without additional remuneration as necessary to complete the system in accordance with the best practice of the trade. B. Provide installation minimally in accordance with NECA NEIS standards. Provide installation beyond the standards if required by the project drawings and specifications. C. Provide wiring and equipment installation in accordance with the latest edition of NFPA 70, National Electric Code. D. The contractor shall be experienced in the work to be performed and familiar with applicable codes, standards and local requirements. 1.03 CODES AND REGULATIONS A. This Contractor shall have the electrical work inspected by an approved inspection agency and shall pay all expenses incurred by same. At the completion of the work, the Contractor shall furnish a certificate of inspection indicating full approval of the work furnished and installed in this Contract. B. Work shall comply with codes and laws of New York State. These include but are not limited to: Building Code of New York State Fire Code of New York State Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GENERAL PROVISIONS Bero Architecture PLLC 260000 - 2 FOR ELECTRICAL WORK 14060.260000.21614 C. The materials, and installation shall where applicable comply minimally with the following standards: ANSI A117.1 ANSI A17.1 – Safety Code for Elevators and Escalators Power company standards and regulations. National Fire Alarm Code (NFPA 72) National Electric Code (NFPA 70) D. Organizations that have applicable standards include: ANSI American National Standards Institute ASME American Society of Mechanical Engineers ASTM American Society for Testing Materials FM FM Global/FM Approvals ICEA Insulated Cable Engineers Association IEEE Institute of Electrical and Electronic Engineers OSHA Occupational Safety and Health Act NECA National Electrical Contractors association NEMA National Electrical Manufacturers Association NESC National Electrical Safety Code NFPA National Fire Protection Association UL Underwriters Laboratories, Inc. E. Comply with all applicable rules and regulations of the municipal laws and ordinances and latest revisions thereof. All work shall be done in full conformity with the requirements of all authorities having jurisdiction. Modifications required by the above authorities will be made without additional charges to the Owner. Where alterations to and/or deviations from the Contract Documents are required by the authorities, report the requirements to the Architect and secure approval before work is started. F. Furnish and file with the proper authorities, all drawings required by them in connection with the work. Obtain all permits, licenses, and inspections and pay all legal and proper fees and charges in this connection. G. Should any work shown or specified be of lighter or smaller material than Code requires, same shall be executed in strict accordance with the regulations. H. Heavier or larger size material than Code requires shall be furnished and installed, if required by the Plans and Specifications. I. Equipment and components parts thereof shall bear manufacturer's name- plate, giving manufacturer's name, size, type and model number or serial number, electrical characteristic to facilitate maintenance and replacements. Name plates of distributors or contractors are not acceptable. J. Owner will stop any work or use of any material that is not being properly installed and each Contractor shall remove all materials delivered, or work erected, which does not comply with Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GENERAL PROVISIONS Bero Architecture PLLC 260000 - 3 FOR ELECTRICAL WORK 14060.260000.21614 Contract Drawings and Specifications, and replace with proper materials, or correct such work as directed by the Owner, at no additional cost to Owner. K. If equipment or materials are installed before proper approvals have been obtained, each Contractor shall be liable for their removal and replacement including work of other trades affected by such work, at no additional cost to Owner, if such items do not meet intent of the Drawings and Specifications. 1.04 MATERIALS AND EQUIPMENT A. Manufacturers and model numbers specified on the drawings are the standard of design with regard to performance, capacity and physical properties. B. Submit specific product data for equipment whether the specified manufacturer is used or a substitute is used. Submit installation data and wiring diagrams (if applicable). C. Unless specifically noted, the equipment specification is not intended to preclude the substitution of material and equipment by other manufacturers. The contractor is responsible for changes due to substitutions (capacity, support, etc.) D. If other manufacturers are named, it does not relieve the contractor from supplying equipment or materials that meet the design intent and from the capacity, and physical requirements of the installation. 1.05 AS-BUILT DRAWINGS A. The Electrical Contractor shall keep an accurate location record of all underground and concealed piping, and of all changes from the original design. He is required to furnish this information to the Owner prior to his application for final payment. B. At completion of the project, all changes and deviations from the Contract Documents shall be recorded by the Contractor. C. Three (3) corrected sets of all operating and maintenance instructions and complete parts lists bound in hard covers shall be furnished to the Owner. 1.06 FOUNDATIONS AND SUPPORTS A. Provide necessary foundations, supports, pads, bases, required for equipment, conduit, lighting fixtures, panels, racks, etc. If not specified provide support in accordance with generally excepted construction practice. B. For equipment where foundations are indicated or required, provide 4 inch high concrete pads, extending 6 inches beyond equipment base in all directions, with top edge chamfered. B. Where equipment is indicated or required to be floor-mounted on stands or legs, construct of structural steel members or steel pipe, fittings; brace, fasten with flanges bolted to floor. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GENERAL PROVISIONS Bero Architecture PLLC 260000 - 4 FOR ELECTRICAL WORK 14060.260000.21614 C. Where ceilings or wall mounting is indicated or required, use suspended platform, brackets or shelf, whichever is most suitable for equipment, its location. Construct of structural steel members, steel plates, rods, as required; brace, fasten to building structure or to inserts as reviewed. A. Design, construct supporting structures of strength to safely withstand stress to which the may be subjected, to distribute load, impact properly over building areas. Conform to applicable technical societies' standards, also to codes, regulations of agencies having jurisdiction. D. Paint steel work with one (1) prime coat for interior locations (exception – galvanized steel or steel with factory finish, threaded rods in unfinished locations). 1.07 CLEANING CONDUIT, EQUIPMENT A. Conduit, equipment: thoroughly cleaned of dirt, cuttings, other foreign substances. Should any conduit, other part of systems be stopped by any foreign matter, disconnect, clean wherever necessary for purpose of locating, removing obstructions. Repair work damaged in course of removing obstructions. 1.08 GROUNDING A. All electrical systems must be grounded in accordance with provisions of the National Electric Code. Provide all required accessories. 1.09 IDENTIFICATION A. Update existing panelboard directories if new connections are made. 1.10 RENOVATIONS A. Contractors shall verify exact existing conditions in the field and coordinate new work with these conditions. B. Contractors shall work with utilities and/or the building owners to find circuits. Finding these circuits remains the contractor’s responsibility. C. Contractor responsible for proper disposal of all materials removed (ballasts, etc.). 1.11 SUPPORTS AND SEALANT A. Provide all required support for wiring, conduit and equipment. B. Provide sleeves for penetrations of walls and floors. Provide sealant for the space between the sleeve and the pipe for fire and smoke walls/partitions/floors, exterior walls and floors, waterproof walls and floors. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration GENERAL PROVISIONS Bero Architecture PLLC 260000 - 5 FOR ELECTRICAL WORK 14060.260000.21614 C. Provide sealant and fire stopping. Sealant and fire stopping for fire rated walls/partitions/floors shall be listed for the use. D. Unless otherwise noted, run conduit as neatly and unobtrusively as possible. Where applicable run as high as possible. Coordinate with other trades. END OF SECTION 260000   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WIRE AND CABLE Bero Architecture PLLC 260519 - 1 14060.260519.21614 SECTION 260519 - WIRE AND CABLE PART 1 GENERAL 1.01 SUMMARY A. Section includes wiring, cables and connectors for power, lighting, signal, control and related systems rated 600 volts and less. 1.02 QUALITY ASSURANCE A. Comply with NEC requirements as to installation, materials and color coding. B. Provide products which are UL listed and labeled. PART 2 PRODUCTS 2.01 INSULATED CONDUCTORS A. Conductors: Annealed uncoated copper or annealed coated copper in conformance with the applicable standards for the type of insulation to be applied on the conductor. Conductor sizes No. 16 and larger shall be stranded. ASTM B-3, ASTM B-174, ASTM B-8, UL-62. B. Acceptable Manufacturers: American Insulated Wire Corp.; Southwire Co C. Types: 1. XHHW: Moisture and heat resistant cross-linked polyethylene insulation rated 600V conforming to U.L. requirements for type XHHW insulation (75 degrees C wet and 90 degrees C dry). 2. THWN-2: Polyvinylchloride insulation rated 600V with nylon jacket conforming to U.L. requirements for type THWN-2 insulation (90 degrees C). 3. THHN: Polyvinylchloride insulation rated 600V with nylon jacket conforming to U.L. requirements for type THHN insulation (90 degrees C). 4. MC: Insulated conductors, type XHHW with flexible metal armor conforming to U.L. requirements for type MC metal-clad cables. Connectors: Malleable iron set screw or 2 screw clamp type, and anti-short bushings. 2.02 CONNECTORS A. General: Provide UL type factory fabricated, metal connectors of sizes, capacity ratings, materials, types and classes as required for application as determined by the wire or cable manufacturer. B. Cable Terminations Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WIRE AND CABLE Bero Architecture PLLC 260519 - 2 14060.260519.21614 1. Provide cable manufacturer terminations or termination specifically manfufactured for cable type of same or greater rating. 2.03 TAPES A. Insulation Tapes: 1. Vinyl Tape: ASTM D-3005 Type 2, UL 510, CSA C22.2, 3M Co. Scotch No. 88. 2. Rubber Tape: HHI-553C, MIL-I-3825B, ASTM D-4388, Type 3, 3M Co. Scotch No. 23. B. Moisture Sealing Tape: 600V UV resistant. C. Electrical Filler Tape: UL listed, 3M Co. Scotchfil. D Color Coding Tape: UL 510, CSA C22.2, 3M Co. Scotch No. 35;. E. Arc Proofing: Fire and arc proofing. 2.04 PULLING COMPOUNDS A. UL listed. PART 3 EXECUTION 3.01 INSTALLATION A. Install conductors in interior raceways after the raceway system is completed and finishes in specific work areas of the building are finished. B. Install conductors in exterior raceways after the raceway system is completed, except where indicated on drawings to be direct burial in earth. C. No grease, oil, or lubricant other than pulling compound specified for each type insulation may be used to facilitate the pulling-in of conductors. D. Use nylon line, polyethylene line, or manila rope as pull wires when installing conductors in aluminum or rigid non-metallic conduits. 3.02 CIRCUITING A. Do not change, group or combine circuits other than as indicated on the drawings. 3.03 COMMON NEUTRAL CONDUCTOR A. A common neutral may not be used. 3.04 CONDUCTOR SIZE Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WIRE AND CABLE Bero Architecture PLLC 260519 - 3 14060.260519.21614 A. Install conductors of size shown on drawings. Where size is not indicated for branch circuit wiring, the minimum size allowed is No. 12 AWG. Where size is not indicated for control wiring, the minimum size allowed is No. 14 AWG. 1. Minimum size No. 12 for general use. At 120 volts and over 100 feet total circuit length, minimum size No. 10. At 277 volts and over 220 feet total circuit length, minimum size No. 10. Increase wire size as required on excessively long circuits to maintain a maximum voltage drop of 2% in branch circuits. 2. Control and alarm wire: Minimum size No. 14. At 120 volts and over 200 feet total circuit length, minimum size No. 12. Increase wire size voltage drop of 2%. 3. Increase raceway sizes as required where wire sizes have been increased for voltage drop. 3.05 CONNECTORS A. Splices: 1. Dry Locations: a. For conductors No. 8 or smaller, use spring type pressure connectors or indent type pressure connectors with insulating jackets. b. For conductors No. 6 AWG or larger, use uninsulated indent type pressure connectors. Fill indentions with electrical filler tape and apply insulation tape to provide insulation equivalent to that of the conductor. 2. Damp Locations: As specified for dry locations, except apply moisture sealing tape over the entire insulated connection. 3. Wet Locations: Use uninsulated indent type pressure connectors and insulate with resin splice kits or heat shrinkable splices. B. Gutter Taps in Panelboards: Install gutter tap, fill indentions with electrical filler tape and apply insulation tape to provide insulation equipment to that of the conductors, or insulate with gutter tap cover. C. Terminations: 1. For conductors No. 10 AWG or smaller, use terminals for: a. Connecting control and signal wiring to terminal strips. b. Connecting wiring to equipment designed for use with terminals. 2. For conductors No. 8 AWG or larger, use lugs for: a. Connecting cables to flat bus bars. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WIRE AND CABLE Bero Architecture PLLC 260519 - 4 14060.260519.21614 b. Connecting cables to equipment designed for use with lugs. 3. For conductor sizes larger than terminal capacity on equipment, reduce the larger conductor to the maximum conductor size that terminal can accommodate. Reduce section shall not be longer than 1'. Use bolted clamp type or pressure connections suitable for reducing connection. 3.06 COLOR CODING A. Color Code and Identification of feeders and branch circuits: 1. Install color coding tapes on feeders at terminations and at 1'0" intervals in gutters, pullboxes and manholes. Color code as follows: 120/208 Volt Phase A - black Phase B - red Phase C - blue Neutral - white Ground - green 2. Identify interior feeders by feeder number and size in pullboxes and gutters with premarked self-adhesive tags. 3. Identify exterior feeders by feeder number and size in manholes with embossed aluminum tags and attach tags to cables with non-ferrous metal wire. 4. Identify street and grounds lighting conductors by circuit number and size in manholes, also in lighting standard bases if not connected to luminaire. Use embossed aluminum tags and attach tags to conductors with non-ferrous metal wire. 5. Install tags so that they are easily read without moving adjacent conductor or requiring removal of arc proofing tapes. 3.07 EQUIPMENT GROUNDING CONDUCTOR A. Install equipment grounding conductor where specified in other sections or indicated on the drawings. B. Equipment grounding conductor may be bare or identified with a continuous green color insulation. This conductor is not intended as a current carrying conductor under normal operating circumstances. 3.08 3.09 INSULATED CONDUCTOR SCHEDULE - TYPES AND USE A. XHHW, THWN or THHN: All wiring in dry locations (except where special type insulation is required). Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WIRE AND CABLE Bero Architecture PLLC 260519 - 5 14060.260519.21614 B. XHHW, or THWN: All wiring in damp locations (except where special type insulation is required). C. THWN: Wiring installed in existing raceway systems (except where special type insulation is required). D. THHN: Wiring when using fluorescent fixture body as a raceway system. E. MC: 1. Branch circuit wiring in drywall partitions and above suspended ceilings. For surface mount panelboards provide wiring in conduit to the first junction box. END OF SECTION 260519   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration RACEWAYS, FITTINGS Bero Architecture PLLC 260533 - 1 AND ACCESSORIES 14060.260533.21614 SECTION 260533 - RACEWAYS, FITTINGS AND ACCESSORIES PART 1 GENERAL 1.01 QUALITY ASSURANCE A. Reference Standards: Raceways shall meet the requirements of NEMA, ANSI and Underwriters' Laboratories, Inc. B. Applies to exterior raceways (unless superseded by another section). 1.02 SUBMITTALS A. Waiver of Submittals: Submittals of product data for approval are not required for products specified by brand name if the specifically named product is provided for the Work. PART 2 PRODUCTS 2.01 RACEWAYS A. Rigid Steel Conduit: Galvanized on the outside and enameled on the inside or hot dipped galvanized on the outside and inside. ANSI C80.1. Threaded type. B. Intermediate Metal Conduit: Steel, galvanized on the outside and enameled on the inside or hot dipped galvanized on the outside and inside. FSWW-C-581. C. Steel Electrical Metallic Tubing: Galvanized on the outside and coated on the inside. ANSI C80.3.. D. Flexible Steel Conduit: Zinc coated steel continuous strip spiral wound into interlocking convolutions. UL 1. E. Liquid-tight Flexible Metal Conduit: Conduit constructed of galvanized steel strip, continuous interlocked double wrapped coat with jacket of flexible PVC. UL 360. 2.02 FITTINGS AND ACCESSORIES A. Connectors and Couplings: 1. Rigid and IMC Conduit: Galvanized steel threaded couplings as provided by the conduit manufacturer or threaded three piece steel/malleable iron coupling. 2. EMT: Zinc plated steel compression type or set screw type. 3. Flexible Metal Conduit: Zinc plated and chromate coated terminal connector with set screw connection. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration RACEWAYS, FITTINGS Bero Architecture PLLC 260533 - 2 AND ACCESSORIES 14060.260533.21614 4. Liquid-tight Flexible Metal Conduit: Provide zinc plated and chromate coated steel, compression type terminal connector with gasket sealing rings. 5. ½” – 1” connectors for termination at device boxes and j-boxes shall be have nylon insulated throat. B. Conduit Bodies: Galvanized cast-metal conduit bodies is required to meet job and NEC requirements. PART 3 EXECUTION 3.01 RACEWAY INSTALLATION A. Number of Circuits in Raceway: Each raceway shall enclose one circuit unless otherwise indicated on the drawings. Homerun conduits may contain three single pole circuits from separate phases, however the neutrals may not be combined. B. Conduit Size: Not smaller than 1/2" electrical trade size. Conduits size to be based on the National Electric Code. C. Conduit in Waterproofed Floors: Install conduit runs in waterproof floors to avoid penetrating the waterproofing. Avoid penetration of waterproofing with conduit risers so far as practicable. 1. Where it is necessary to puncture the waterproofing for a conduit riser, install a standard weight steel pipe sleeve extending 1/2" above the finished floor level. Flash the steel pipe sleeve to the waterproofing with 16 ounce copper. Construct the flashing with a copper tube extending the full height of the sleeve, soldered to a copper base extending 6" in all directions from the sleeve. 2. The flashing will be integrated into the waterproofing by the Construction Contractor. Provide solid cast brass floor plates with chromium finish where pipe sleeves are exposed in rooms. D. Install Conduit Concealed: Install conduit for all circuit work concealed in the floors, ceilings, walls, or partitions of the building unless otherwise indicated on the drawings. If any portions of the conduit system cannot be installed concealed due to conditions encountered in the building, report such conditions and await approval before proceeding. 1. Run conduit in partitions vertically. 2. Conduits installed under or in floors below grade or underground shall have conduit threads painted with sealant before couplings are assembled. Coupling and conduit shall then be drawn up tight to ensure water tightness. E. Conduit Installed Exposed (areas without ceilings, to exposed panelboards, mechanical rooms, or as noted): 1. Install vertical runs perpendicular to the floor. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration RACEWAYS, FITTINGS Bero Architecture PLLC 260533 - 3 AND ACCESSORIES 14060.260533.21614 2. Install runs on the ceiling perpendicular or parallel to the walls. 3. Install horizontal runs parallel to the floor. 4. Conduits installed on flat surfaces in finished spaces shall be installed directly on the surface with straps.. 5. Installation of conduit directly on the floor will not be permitted. F. Materials in Conduit Runs: All conduits in a conduit run shall be of the same material. A combination of steel and aluminum conduit or fittings will not be permitted. G. Conduit Ends: 1. Arrange conduit terminations in cabinet with ends at the same level. 2. Plug ends of conduits with caps to exclude foreign material until wiring is installed. 3. Use 2 locknuts and insulated bushing on end of each conduit entering cabinet or galvanized box (plastic bushing may be used on 1/2" & 3/4" conduit). 4. Use insulated grounding bushings on the ends of conduits which are not directly connected to the enclosure (such as stub-ups under equipment, etc.) and bond between bushings and enclosure with equipment grounding conductor. 5. Use insulated groundings bushings or grounding wedges on ends of conduit for terminating and bonding equipment grounding conductors (when required) if cabinets or boxes are not equipped with grounding/bonding screws or lugs. H. Conduit Bends: For 1/2" and 3/4" conduits, bends may be made with manual benders. For all conduit sizes larger than 3/4", manufactured or field fabricated offsets or bends may be used. Make field fabricated offsets or bends with an approved hydraulic bender. 3.02 MAINTENANCE FIRE RESISTANCE A. Conduit and equipment shall be firestopped to prevent the passage of flame, smoke, fumes and hot gases. 3.03 RACEWAY SCHEDULE - TYPES & USE A. Rigid Steel Conduit: Install in all locations unless otherwise specified or indicated on the drawings. B. Intermediate Metal Conduit: May be installed in all locations except hazardous areas. C. Steel Electrical Metallic Tubing: 1. May be installed concealed as branch circuit conduits above suspended ceilings. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration RACEWAYS, FITTINGS Bero Architecture PLLC 260533 - 4 AND ACCESSORIES 14060.260533.21614 2. May be installed concealed as branch circuit conduits in hollow areas in dry locations. 3. Exposed in mechanical rooms. Do not install exposed in garages. D. Flexible Steel Conduit: Install equipment grounding conductor in the flexible steel conduit and bond at each box or equipment to which conduit is connected: 1. Use for final conduit connection to recessed lighting fixtures in accessible suspended ceilings. Use 4 to 6 feet of flexible steel conduit (minimum size 1/2") between junction box and fixture. Locate junction box at least 1' from fixture and accessible if the fixture is removed. 2. Use 1 to 2 feet of flexible steel conduit for final conduit connection to: Emergency lighting units Dry type transformers Motors with open, drip-proof or splash-proof housings Equipment subject to vibration (dry locations) Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration DEVICE AND JUNCTION BOXES Bero Architecture PLLC 260534 - 1 14060.260534.21614 SECTION 260534 - DEVICE AND JUNCTION BOXES PART 1 GENERAL 1.01 SUMMARY: A. Pull and Junction Boxes. B. Device and Outlet Boxes. PART 2 PRODUCTS 2.01 MATERIALS A. Interior Dry Locations: Pressed steel, galvanized, conforming to UL Standard for outlet boxes and fittings with galvanized steel cover or extension ring as required to comply with NEC. 2.02 SWITCH AND RECEPTACLE BOXES - CONCEALED A. Nominal 2” x 3”, 2-3/4” deep (or as required by the number of conductors). Knockouts. Mounting accessories and ganged as required. 2.03 LIGHTING FIXTURE BOXES A. 4 inch octagon. B. For lay-in type ceilings provide box hanger which mounts to two T-bars. Knockouts. C. For drywall ceilings provide support from two joists. 2.04 PULL AND SPLICE BOXES - 600 VOLTS AND BELOW A. Galvanized steel, reinforced, with removable covers secured by brass machine screws and constructed in accordance with Requirements of UL. B. 4” steel with knockouts and cover. 2.05 BOXES IN MASONRY A. Pressed steel masonry box, 2-1/2” deep (or as required by the number of conductors). Knockouts. 2.06 SWITCH AND RECEPTACLE BOXES - EXPOSED A. 4” X 2-1/8” pressed steel box, 2-1/8” deep (or as required by the number of conductors). Knockouts. 2.07 TELEPHONE/DATA OUTLET BOXES Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration DEVICE AND JUNCTION BOXES Bero Architecture PLLC 260534 - 2 14060.260534.21614 A. Same as receptacle. PART 3 EXECUTION 3.01 GENERAL A. Mount outlet boxes as shown on drawings and specified. B. Coordinate outlets with construction and built-in cabinets and equipment. C. Close unused openings in outlet boxes with knockout closers. D. Provide blank plates on outlet boxes in which no device is installed. END OF SECTION 260534 Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 260580 - 1 ELECTRICAL SYSTEMS 14060.260580.21614 SECTION 260580 - FIRESTOPPING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.01 SUMMARY A. Provide listed firestop at penetrations of rated walls, partitions, ceilings, floors and assemblies. 1.02 DEFINITIONS A. Firestopping: Material or combination of materials used to retain integrity of fire-rated construction by maintaining an effective barrier against the spread of flame, smoke, and hot gases through penetrations in fire rated wall and floor assemblies. 1.03 REFERENCES A. Test Requirements: ASTM E 814, "Standard Method of Fire Tests of Through Penetration Fire Stops" B. Test Requirements: UL 1479, “Fire Tests of Through-Penetration Firestops” C. Underwriters Laboratories (UL) of Northbrook, IL publishes tested systems in their "FIRE RESISTANCE DIRECTORY" that is updated annually. 1. UL Fire Resistance Directory: a. Firestop Devices (XHJI) b. Fire Resistance Ratings (BXRH) c. Through-Penetration Firestop Systems (XHEZ) d. Fill, Voids, or Cavity Material (XHHW) e. Forming Materials (XHKU) D. International Firestop Council Guidelines for Evaluating Firestop Systems Engineering Judgments E. Inspection Requirements: ASTM E 2174, “Standard Practice for On-site Inspection of Installed Fire Stops.” F. ASTM E 84, “Standard Test Method for Surface Burning Characteristics of Building Materials.” 1.04 QUALITY ASSURANCE A. A manufacturer's direct representative to be on-site during initial installation of firestop systems to train appropriate contractor personnel in proper selection and installation procedures. This will be done per manufacturer's written recommendations published in their literature and drawing details. B. Firestop System installation must meet requirements of ASTM E 814 or UL 1479 tested assemblies that provide a fire rating equal to that of construction being penetrated. Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 260580 - 2 ELECTRICAL SYSTEMS 14060.260580.21614 1.05 SUBMITTALS A. Submit Product Data: Manufacturer’s specifications and technical data for each material including the composition and limitations, documentation of UL firestop systems to be used and manufacturer's installation instructions. B. Submit material safety data sheets provided with product delivered to job-site. PART 2 - PRODUCTS 2.01 FIRESTOPPING, GENERAL A. Provide firestopping composed of components that are compatible with each other, the substrates forming openings, and the items, if any, penetrating the firestopping under conditions of service and application, as demonstrated by the firestopping manufacturer based on testing and field experience. B. Provide components for each firestopping system that are needed to install fill material. Use only components specified by the firestopping manufacturer and approved by the qualified testing agency for the designated fire-resistance-rated systems. 2.02 ACCEPTABLE MANUFACTURERS A. Subject to compliance with through penetration firestop systems (XHEZ) listed in Volume II of the UL Fire Resistance Directory, provide products of the following manufacturers as identified below: 1. Hilti, Inc., Tulsa, Oklahoma 800-879-8000/www.us.hilti.com 2. Accepted equal. 2.03 MATERIALS A. Use only firestop products that have been UL 1479 or ASTM E 814 tested for specific fire- rated construction conditions conforming to construction assembly type, penetrating item type, annular space requirements, and fire-rating involved for each separate instance. B. Cast-in place firestop devices are installed prior to concrete placement for use with non- combustible and combustible plastic pipe (closed and open systems), conduit, or electrical cable bundles penetrating concrete floors, the following products are acceptable: 1. Hilti CP 680 Cast-In Place Firestop Device 2. Hilti CP 682 Cast-In Place Firestop Device for use with noncombustible penetrants Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 260580 - 3 ELECTRICAL SYSTEMS 14060.260580.21614 C. Sealants, foams or caulking materials for use with non-combustible items including rigid steel conduit and electrical metallic tubing (EMT), the following products are acceptable: 1. Hilti FS-ONE Intumescent Firestop Sealant 2. Hilti CP 620 Fire Foam 3. Hilti CP 606 Flexible Firestop Sealant 4. Hilti CP 601s Elastomeric Firestop Sealant D. Intumescent sealants, caulking materials for use with combustible items (penetrants consumed by high heat and flame) including PVC jacketed, flexible cable or cable bundles, and plastic pipe, the following products are acceptable: 1. Hilti FS-ONE Intumescent Firestop Sealant E. Foams, intumescent sealants, or caulking materials for use with flexible cable or cable bundles, the following products are acceptable: 1. Hilti FS-ONE Intumescent Firestop Sealant 2. Hilti CP 620 Fire Foam 3. Hilti CP 606 Flexible Firestop Sealant 4. Hilti CP 601s Elastomeric Firestop Sealant F. Non curing, re-penetrable intumescent putty or foam materials for use with flexible cable or cable bundles, the following products are acceptable: 1. Hilti CP 618 Firestop Putty Stick 2. Hilti CP 658T Firestop Plug G. Wall opening protective materials for use with U.L. listed metallic and specified nonmetallic outlet boxes, the following products are acceptable: 1. Hilti CP 617 Firestop Putty Pad H. Materials used for large openings and complex penetrations made to accommodate cable trays and bundles, multiple steel and copper pipes, electrical busways in raceways, the following products are acceptable: 1. Hilti CP 637 Firestop Mortar 2. Hilti FS 657 FIRE BLOCK 3. Hilti CP 620 Fire Foam 4. Hilti CP 675T Firestop Board I. Non curing, re-penetrable materials used for large openings and complex penetrations made to accommodate cable trays and bundles, multiple steel and copper pipes, electrical busways in raceways, the following products are acceptable: 1. Hilti FS 657 FIRE BLOCK Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 260580 - 4 ELECTRICAL SYSTEMS 14060.260580.21614 2. Hilti CP 675T Firestop Board J. Provide a firestop system with a "F" Rating as determined by UL 1479 or ASTM E 814 which is equal to the time rating of construction being penetrated. PART 3 - EXECUTION 3.01 PREPARATION A. Verification of Conditions: Examine areas and conditions under which work is to be performed and identify conditions detrimental to proper or timely completion. 1. Verify penetrations are properly sized and in suitable condition for application of materials. 2. Surfaces to which firestop materials will be applied shall be free of dirt, grease, oil, rust, laitance, release agents, water repellents, and any other substances that may affect proper adhesion. 3. Provide masking and temporary covering to prevent soiling of adjacent surfaces by firestopping materials. 4. Comply with manufacturer's recommendations for temperature and humidity conditions before, during and after installation of firestopping. 5. Do not proceed until unsatisfactory conditions have been corrected. 3.02 COORDINATION A. Coordinate location and proper selection of cast-in-place Firestop Devices with trade responsible for the work. Ensure device is installed before placement of concrete. 3.03 INSTALLATION A. Regulatory Requirements: Install firestop materials in accordance with UL Fire Resistance Directory. B. Manufacturer's Instructions: Comply with manufacturer's instructions for installation of through-penetration materials. 1. Seal all holes or voids made by penetrations to ensure an air and water resistant seal. 2. Protect materials from damage on surfaces subjected to traffic. 3.04 FIELD QUALITY CONTROL Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration FIRESTOPPING FOR Bero Architecture PLLC 260580 - 5 ELECTRICAL SYSTEMS 14060.260580.21614 A. Examine sealed penetration areas to ensure proper installation before concealing or enclosing areas. B. Keep areas of work accessible until inspection by applicable code authorities. C. Inspection of through-penetration firestopping shall be performed in accordance with ASTM E 2174, “Standard Practice for On-Site Inspection of Installed Fire Stops” or other recognized standard. D. Perform under this section patching and repairing of firestopping caused by cutting or penetrating of existing firestop systems already installed by other trades. END OF SECTION   Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WIRING DEVICES Bero Architecture PLLC 262726 - 1 14060.262726.21614 SECTION 262726 - WIRING DEVICES PART 1 GENERAL 1.01 SUMMARY: A. Wall switches. B. Receptacles. C. Plate covers. D. Occupancy Sensors. 1.02 REQUIREMENTS OF REGULATORY AGENCIES A. Provide UL approved devices. 1.03 SUBMITTALS A. Submit product data. PART 2 PRODUCTS 2.01 ACCEPTABLE MANUFACTURERS A. Acceptable Manufacturers: 1. Hubbell 2. Arrow Hart 3. General Electric 4. Wattstopper 5. Prescolite 2.02 WALL SWITCHES A. 120/277 Volt Switches: Quiet slow make, slow break design, toggle handle, with totally enclosed case, rated 20 ampere, specification grade. Provide matching two pole, 3 way, and 4 way switches. B. Switch and Pilot Light: Push action type with red handle, integral long-life neon pilot light, rated at 15 ampere, 120 volts. C. Color: Provide ivory switches except where wall finish is wood or dark, use brown switches or as otherwise requested by the architect/owner. 2.04 RECEPTACLES Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WIRING DEVICES Bero Architecture PLLC 262726 - 2 14060.262726.21614 A. Standard Duplex Receptacles: Full gang size, polarized, duplex, parallel blade, U-grounding slot, specification grade, rated at 20 amperes, 125 volts, designed for split feed service. B. Color: Provide ivory receptacles in areas with light wall finish. Provide brown receptacles in areas with wood or dark wall finish. 2.05 PLATE COVERS A. Flush Mounting Plates: 302/304 stainless steel satin finish beveled type with smooth rolled outer edge. Smooth nylon with color matching the device. Or as otherwise specified. 2.06 OCCUPANCY SENSORS/LIGHTING CONTROL A. Ceiling Sensors 1. Ultrasonic motion-sensing. 2. Adjustable time delay from 15 seconds to 15 minutes. 3. Adjustable sensitivity setting. 4. Manual override switch in sensor for maintenance use. 5. Provide required switchpack and wiring. 6. Watt Stopper W. C. General 1. All wiring and conduit between switchpacks and room sensors has been omitted from the drawings. Verify with the manufacturer all wiring requirements. Provide all necessary wiring and conduits, switchpacks, room sensors, lighting fixtures and wall switches. 2. The system has been designed based on the above indicated equipment. Any equipment substitutions shall be provided with drawings and specifications confirming the substituted system functions as the designed system. Provide all additional components (at no additional cost) to accommodate original design. 3. Adjust each sensor to assure proper lighting control of all fixtures. Each sensor sensitivity should be set to assure corridor movement does not effect individual room control. Sensor operation shall be acceptable to the Owner and Engineer before final acceptance. 4. Mount sensors a minimum of 4' from air distribution equipment and in accordance with the manufacturer's recommendations. PART 3 EXECUTION Chi Phi Fraternity August 4, 2014 Interior Finishes Restoration WIRING DEVICES Bero Architecture PLLC 262726 - 3 14060.262726.21614 3.01 INSTALLATION A. Mount switches 44 inches above floor, unless otherwise noted. Coordinate switch mounting location with architectural detail. B. Mount receptacles vertically at 18 inches above finished floor, unless otherwise noted, with grounding pole at top. C. Coordinate receptacles with counters, built-in desks and other architectural details. Mount receptacles over counters and at rest room lavatories at 44” AFF unless otherwise required by the situation. END OF SECTION 262726