HomeMy WebLinkAbout23 01 01 HVAC General ProvisionsBEARDSLEY DESIGN ASSOCIATES
CORNELL – NCP HVAC GENERAL PROVISIONS
STANDARD SPECIFICATIONS 23 01 01 – PAGE 1 OF 4
MARCH 29, 2013
SECTION 230101 -- HVAC GENERAL PROVISIONS
PART 1 GENERAL
1.1 SUMMARY:
This Section includes general administrative and procedural requirements for
Division 23, Heating and Ventilation work.
1.2 DIVISION 23 - DESCRIPTION:
The technical specifications of this Contract are arranged for the convenience of
the Owner and Contractor into Divisions of work. The work of Division 23,
HVAC, is further described in Specification Sections of the 23 01 00 Series and
on contract drawings of the "M series.
The organization of this work into Divisions shall not relieve the prime Contractor
from providing all of the work shown on the complete set of drawings or specified
in the complete set of Specifications, whether or not the individual subcontractors
correctly identify their respective responsibilities.
1.3 OTHER DIVISION SPECIFICATIONS APPLICABLE TO THIS WORK:
To the extent that the work of this Division or Contract includes the work of other
trades, the Contractor for this Division shall adhere to the requirements of other
specification sections. All General Construction work shall be performed in
accordance with the provisions of the appropriate Division 02 through Division 09
Sections. All electrical work shall be performed in accordance with appropriate
Division 26 Sections.
1.4 WORK INCLUDED:
The work of this Division shall include providing all materials, labor, services,
permits and related work to furnish a complete, operating, tested, functioning,
documented HVAC System including all work shown, specified or required for
proper system operation including but not limited to the following:
A. Provide Basic Materials and Methods.
B. Provide Mechanical Coordination Drawings.
C. Provide Exhaust Fans where shown.
D. Provide Ductwork where shown.
E. Provide Fire Dampers and Fire/Smoke Dampers where shown.
F. Provide demolition and removal of existing equipment, ductwork and
piping where shown, removal of all debris from site and proper disposal of
same.
BEARDSLEY DESIGN ASSOCIATES
CORNELL – NCP HVAC GENERAL PROVISIONS
STANDARD SPECIFICATIONS 23 01 01 – PAGE 2 OF 4
MARCH 29, 2013
G, Provide revision of ductwork piping and provide new ductwork and piping
as shown on mechanical drawings. Provide liner and flexible ductwork as
shown.
H. Provide and install duct access panels in duct as shown.
I. Provide and install new diffusers, registers and grilles.
J. Provide insulation.
K. Provide air balance at completion of project, provide final report.
L. Provide maintenance of system in good condition until final acceptance.
M. Provide openings in existing and new construction as required for the
work of this division.
N. Provide fan coil units where shown.
O. Provide split-system air conditioning units where shown.
P. Provide piping where shown.
1.5 SUBMITTALS
A. Provide Shop Drawings for the following:
1. Ductwork, supply, return and flexible
2. Registers, diffusers and grilles (air devices)
3. Volume, Fire dampers, fire/smoke dampers
4. Motorized dampers
5. Access Panels
6. Insulation
7. Ductwork Coordination drawings,
8. Mechanical Coordination drawings
9. Exhaust Fans.
10. Controls, as required
11. Piping
12. Fan coil units
13. Split-system air conditioning units
14. Pre-construction & final construction testing and balancing report.
B. Provide Owner's Operation Instruction
C. Provide Operation and Maintenance Manuals - four (4) copies
D. Provide Warranty Documents
1.6 RELATED WORK NOT INCLUDED:
A. Asbestos removal is not included in the work of this contract. See
Section 013529.
BEARDSLEY DESIGN ASSOCIATES
CORNELL – NCP HVAC GENERAL PROVISIONS
STANDARD SPECIFICATIONS 23 01 01 – PAGE 3 OF 4
MARCH 29, 2013
PART 2 PRODUCTS
2.1 GENERAL:
A. Provide products as specified in Division 23.
PART 3 EXECUTION
3.1 GENERAL:
A. Conform to Division 23 Specifications for installation and execution of
work.
END OF SECTION 230101
BEARDSLEY DESIGN ASSOCIATES
CORNELL – NCP HVAC GENERAL PROVISIONS
STANDARD SPECIFICATIONS 23 01 01 – PAGE 4 OF 4
MARCH 29, 2013
[ PAGE LEFT INTENTIONALLY BLANK ]