HomeMy WebLinkAboutMN-IURA-2019-07-25
108 E. Green St. Approved: 8/29/19
Ithaca, NY 14850
(607) 274-6565
MINUTES
ITHACA URBAN RENEWAL AGENCY
Common Council Chambers, City Hall
8:30 A.M., Thursday, July 25, 2019
(following IURA Audit Committee Meeting)
Members: Svante Myrick, Chair; Tracy Farrell, Vice‐Chair; Karl Graham; Chris Proulx; Eric Rosario;
Laura Lewis (Common Council Liaison)
Excused: None
Staff: Nels Bohn; Anisa Mendizabal; Charles Pyott
Guests: Molly Chiang, Vecino Group of New York, LLC
I. Call to Order
Chair Myrick called the meeting to order at 8:47 A.M.
II. Agenda Additions/Deletions
Mendizabal noted a proposed contract modification for the Urban Bus Stop project should also
have been included on the agenda. No objections were raised.
III. Public Comments (3‐min. maximum per person)
DUCSON NGUYEN, Common Council Member, spoke regarding the proposed Green Street Garage
Redevelopment Project, noting he strongly supports VERSION 2.2, if the conference center is
determined to be infeasible. The city needs to maximize its number of affordable housing units,
especially if it is to succeed in its goal of becoming a more sustainable community.
THERESA ALT spoke regarding the proposed Green Street Garage Redevelopment Project, noting she
also supports maximizing the number of affordable housing units.
MIKE E. MORITZ, Hub Coordinator, Sunrise Movement, spoke regarding the proposed Green Street
Garage Redevelopment Project, noting the Sunrise Movement supports approving a version of the
project that includes as much affordable housing as possible, like VERSION 2.2, which represents the
most sustainable option for the city ― and would also be most consistent with the recently
enacted Ithaca Green New Deal.
IV. Agency Member Response to Public Comments
None.
V. Review of Meeting Minutes: June 27, 2019
Graham moved, seconded by Farrell, to approve the June 27, 2019 minutes with no modifications.
Carried Unanimously: 5‐0
IURA Minutes
July 25, 2019
Page 2 of 18
VI. Economic Development Committee (EDC)
A. Green Street Garage Redevelopment Project: Western Section
VERSION 1 ― ORIGINAL CONCEPT: 11 stories, 218 affordable units, 2‐story 49,000 SF conference
center, 350 parking spaces (excludes east section of garage)
VERSION 2.1 ― EXCLUDES CONFERENCE CENTER: 8 stories, 173 affordable units, 1‐story 9,000 SF
commercial (light‐gauge steel construction like City Centre)
VERSION 2.2 ― EXCLUDES CONFERENCE CENTER: 12 stories, 273 affordable units, 1‐story 9,000 SF
commercial (structural steel construction like Harold’s Square)
1. Extension of Exclusive Negotiation Agreement Schedule
Bohn explained he has been working with the developers on several significant, but as‐yet‐unresolved,
issues associated with the project, so he recommends extending the ENA deadline. No objections were
raised.
Moved by Rosario, seconded by Farrell:
Amendment #2 to Exclusive Negotiation Agreement (ENA):
Green Street Garage Redevelopment Urban Renewal Project
WHEREAS, on December 13, 2018, the IURA designated Vecino Group of New York, LLC as the
preferred developer for the urban renewal project to redevelop the Green Street Garage, and
WHEREAS, on April 11, 2019, the IURA executed an Exclusive Negotiation Agreement (ENA) with
Vecino Group of New York, LLC (Vecino), and
WHEREAS, the ENA is intended to translate Vecino’s conceptual mixed‐use development project to
finalize a term sheet to define the project and developer’s responsibilities, define seller and buyer
contingencies, resolve feasibility issues, and address pre‐identified negotiation issues, and
WHEREAS, on May 23, 2019, the IURA approved an amendment to approve a 30‐day extension of
the ENA schedule, and
WHEREAS, pursuant to the current ENA, the IURA is scheduled to submit a proposed Disposition and
Development Agreement (DDA) to Vecino by July 30, 2019 for a 10‐day review period to accept or
submit a counter‐offer, and
WHEREAS, IURA staff is still developing preliminary draft terms for the DDA and a second extension
would allow the draft DDA to consider responses by Vecino, the IURA, and IURA legal counsel to
incorporate into proposed DDA, and
WHEREAS, Vecino does not object to a second 30‐day extension of the ENA schedule, and
WHEREAS, at its July 23, 2019 meeting, the IURA Economic Development Committee considered this
matter and recommended the following; now, therefore, be it
IURA Minutes
July 25, 2019
Page 3 of 18
RESOLVED, that the IURA hereby authorizes a second 30‐day extension of the time schedule
contained in the Exclusive Negotiation Agreement between the IURA and Vecino Group of NY, LLC,
and be it further
RESOLVED, that the revised schedule for IURA submission of the proposed Disposition and
Development Agreement to Vecino is August 29, 2019, and be it further
RESOLVED, that the IURA Chairperson is authorized, subject to review by IURA legal counsel, to
execute Amendment #2 to the Exclusive Negotiation Agreement.
Carried Unanimously: 5‐0
2. Draft Disposition & Development Agreement Discussion
Bohn reported he has been actively working with Vecino Group New York, LLC (“Vecino”) on narrowing
down the sets of remaining questions and issues raised in response to the most recent project
submission. Considerable time was spent working out the conference center details and exploring
various financing approaches for it. At least one funding application for the conference center will be
submitted to New York State (Upstate Revitalization Initiative), which will serve a critical role in the
conference center’s financial viability. The developers have been consulting with the State about its
overall interest in the project, and its timelines and benchmarks. The State strongly recommends
submitting the application in the first quarter of 2020, given the extraordinary funding demand.
Bohn explained the conference center project is challenging to finance. For the preferred project to
move forward, the developer needs to know if the conference center will be financially feasible. The
decision on the conference center should be made in time for Vecino to apply to NYS for funding of a
defined project in the first quarter of 2020. The conference center’s financing includes two major
funding sources: (1) NYS grant funding; and (2) a hospitality sector self‐assessment, possibly through
establishment of a Tourism Improvement District (TID). Various financing models are being explored
including private sector financing and tax‐exempt, revenue bonds.
It was agreed that a late January, 2020 deadline should be established for IURA and developer
determination that a submitted conference center financing plan is feasible.
Farrell asked if there had been any discussion with local hoteliers. Bohn replied, yes. Local hotels seem
highly motivated to identify a working conference center financing model (e.g., higher bedroom tax
rate for hotels closest to downtown).
Proulx asked if a New York State enabling law would need to be enacted for the TBID. Bohn replied,
no. Tompkins County could to adopt home rule legislation according to Civitas Advisors.
Bohn noted the developers are waiting for the project’s residential market‐demand study to be
completed, but the general understanding is that Ithaca possesses a strong market demand for
affordable housing.
IURA Minutes
July 25, 2019
Page 4 of 18
Bohn walked through several project components for which some open issues need to be resolved:
Assurances related to the property management company’s (CRM Rental Management, Inc.)
organizational capacity, qualifications, and experience
Construction impact mitigation measures for Cinemapolis (and other adjacent property owners)
Definition of precise project site boundary in relation to City Hall
Architectural and pedestrian‐access improvements in open areas surrounding the site (e.g., Home
Dairy Alley)
Proulx noted the Committee asked the developers about the typical length of a property management
contract for this kind of project, since the IURA would need to be consulted on any future changes.
Proulx indicated it would be worth further discussing construction impact mitigation for Cinemapolis.
Temporary closure of the theatre would most likely be required (~150 days). The theatre has stated
the prospect of long‐term closure risks being catastrophic for its operations, since it would jeopardize
its relationships with film distributors. Vecino and Cinemapolis are collaborating to identify alternative
locations for at least two screens during the theatre’s closure. Further discussion is needed to resolve
the issue, especially since it remains unclear when it would be safe to occupy that part of site.
Chiang remarked, until Vecino knows exactly what the project specifications will entail, it cannot define
those kinds of details with any degree of accuracy. She stressed there will most certainly be periods
when that portion of the site is categorically unsafe (e.g., demolition). In terms of alternative locations,
it may be possible to work with the Arthaus project and arrange screenings at the Cherry Artspace.
Vecino has also investigated using the former Cinemapolis site in Center Ithaca, but that may no longer
be suitable.
Farrell suggested exploring the State Theatre as a possible alternative. Chiang replied she is not sure if
that has been pursued, although it is a good idea. Vecino is also attempting to ensure peak
construction hours conflict as little as possible with Cinemapolis’ operating hours.
Proulx remarked the Committee discussed the comparative merits of VERSION 2.1 and VERSION 2.2. It
ultimately voted 3‐to‐1 in favor of VERSION 2.2, for many of the reasons cited in the various letters and
public comments that have been received, namely that VERSION 2.2 would maximize the amount of
affordable housing. Some concerns were expressed that VERSION 2.2 would be too tall and dense for
the location. Other questions were raised that existing data do not provide a clear understanding of
the demand for the type and affordability‐level of the housing units.
Farrell asked what information the market‐demand study would contain that the IURA does not
already have. Bohn replied it would identify the project’s “capture rate.” Capture rate is the
percentage of age, size, and income‐qualified renter households in the primary market area that a
property must capture to fill its units. Capture rate is calculated by dividing the total number of units
at the property by the total number of age, size, and income‐qualified renter households in the primary
market area. The Arthaus project’s capture rate, for example, was 2.6%. NYS likes to see a capture
rate lower than 10%. He believes the study’s geographic area would be ~20,000 households,
representing almost the entire County. Bohn anticipated the Green Street Garage project would have
about a 5% capture rate.
IURA Minutes
July 25, 2019
Page 5 of 18
Myrick observed the project would be in an even better location than the Arthaus project. He
continues to have a strong sense there is a great need for affordable housing in the city, which all
available data also seem to support. He would personally prefer VERSION 2.2.
Farrell asked if the project’s funding would be delayed if its housing units are not filled quickly enough.
Bohn replied, yes. Receipt of the developer fee would be deferred.
Chiang explained Vecino based its pro forma on a 95% occupancy rate. It has not encountered any
problems achieving targeted occupancy rates in other communities. The financial risk is being borne by
Vecino. She noted Vecino would not simply be able to infuse additional cash into project. The State
does not permit injecting more funding into housing projects, since if a project does not achieve full
occupancy, no reserves would be available to keep the project viable. Vecino is confident it will
achieve the 95% occupancy rate.
Graham asked if the project would be locked into renting to households within the 50%, 60%, and 80%
of Area Median Income (AMI) band. Chiang replied, yes. Vecino would be prohibited from renting to
higher‐income households.
Graham noted he periodically observes a certain amount of stigma associated with low‐income housing
projects, so he wonders if the actual housing demand will necessarily be as high projected. He asked if
Vecino has encountered any problems associated with that. Chiang replied, no. Vecino’s Utica project
has been open for a year and it only took 3 days to lease up. Vecino’s Elmira project has already
received 60% of the total number of housing applications, 45 days before its scheduled opening. She
does not foresee any problems with the lease‐up process for this project.
Lewis asked what size the Utica project is. Chiang replied, 59 units. Lewis noted the Green Street
Garage project will be substantially larger, so she shares some of Graham’s concerns. She also has
concerns working with a property management company the city has no experience with. She is
concerned with the potential pressure to cut corners in vetting potential tenants. It is important
affordable housing is viewed favorably in the community.
Farrell remarked the community has had a good history with affordable housing projects, like
Breckenridge Place, which people have a positive attitude towards. The aesthetics of the Green Street
Garage project will be important in that respect.
Myrick asked if CRM Rental Management, Inc. manages large numbers of housing units. Chiang
replied, yes. It manages 5,000 units, including larger projects of up to 305 units.
Lewis asked if the property management would be on‐site. Chiang replied, yes. There would be 1 FTE
property manager and 1 FTE maintenance staff person. The supportive housing component, with 3‐7
FTE staff persons, would complement the property management team. Furthermore, the project’s
staff would not be siloed, but would be working together.
IURA Minutes
July 25, 2019
Page 6 of 18
Farrell asked if tenant incomes would be recertified annually. Chiang replied, yes. She believes
recertifications take place at the expiration of each lease.
Bohn added LIHTC projects are required to undergo an annual tenant income review. Tenants whose
incomes increase over their AMI threshold would not be required to terminate their leases, but they
would have to pay 30% of their income towards rent.
Graham asked what the market‐demand study would include in its analysis. Bohn replied it would
include both existing and imminent/future projects.
Rosario expressed appreciation for all the due diligence being done in analyzing the various
components of the project. He remains in favor of VERSION 2.2.
Farrell indicated she was originally concerned about the project’s height, so leaned towards VERSION
2.1. She now leans towards VERSION 2.2.
Graham remarked he is still not persuaded of the merits of VERSION 2.2, considering the number of
other local affordable housing units coming online at same time. He is also concerned with the mass
and height of the building. He would lean towards VERSION 2.1.
Rosario noted one reason he voted for the Vecino proposal was that it committed to comply with the
City’s Downtown Design Guidelines, so he is confident the end‐result will be aesthetically and
architecturally compatible with its surroundings.
Bohn noted there appears to be consensus to support VERSION 2.2.
B. Modification to Loan Extension – State Theatre of Ithaca, Inc. (PB‐LF #2)
Proulx explained the IURA approved an extension of the loan for 10 years, several months ago. Some
additional information has subsequently come to light, regarding Mack Travis’ retirement from the
theatre’s board. As a result, the theatre now requests that Mr. Travis’ personal financial guarantee be
released. The theatre has paid down the loan significantly. The IURA also has collateral on two other
mortgages, so it should be well‐secured without the benefit of the personal financial guarantee. The
theatre also recently enrolled in an automated payment plan.
Moved by Proulx, seconded by Farrell:
ModificaƟon to Loan Extension ― State Theatre of Ithaca, Inc. (PB‐LF #2)
WHEREAS, on February 28, 2019, the IURA approved a 10‐year extension of the $458,500 loan
issued to the State Theatre of Ithaca, Inc. (STI) in 2009 for acquisition of the historic State Theatre,
and
IURA Minutes
July 25, 2019
Page 7 of 18
WHEREAS, on June 26, 2019, STI requested the existing collection collateral and financial guarantees
securing the loan be modified in recognition of 10 years of successful operations and loan
repayments which reduce the need for the original amount of loan security, and
WHEREAS, STI specifically requests release of the limited personal guarantee of M. and C. Travis, and
WHEREAS, as of June 30, 2019, the outstanding principal balance of the loan is $340,775.80, and
WHEREAS, the IURA loan is secured by the following collateral and financial guarantees:
1st mortgage lien on the State Theatre building property located at 117 W. State Street;
2nd mortgage lien on property located at 209‐17 W. State Street;
$200,000 limited personal guarantee of M. and C. Travis, and
WHEREAS, the assessed value of the State Theatre property is $1,850,000, and
WHEREAS, the assessed value of the property located at 209‐217 W. State is $700,000, and
WHEREAS, the estimated collateral value of the mortgages is in excess of 150% of the outstanding
loan balance, and
WHEREAS, STI has established an automatic payment system to make timely loan payments and is
current on IURA loan payments, and
WHEREAS, the IURA Economic Development Committee reviewed this matter at its June 23, 2019
meeting, and recommends the following; now, therefore, be it
RESOLVED, that the IURA hereby approves the request from State Theatre of Ithaca, Inc. to release
all personal financial guarantees on the State Theatre of Ithaca, Inc. loan originally issued on March
5, 2009 (PB‐LF #2), and be it further.
RESOLVED, that IURA Chairperson, upon the advice of IURA legal counsel, is hereby authorized to
execute all necessary and appropriate documents to implement this resolution.
Carried Unanimously: 5‐0
C. Appointment of Committee Chairperson
Moved by Farrell, seconded by Myrick:
Appointment of 2019 IURA Economic Development Committee (EDC) Chairperson
WHEREAS, IURA by‐laws provide that the committee membership shall elect its own committee
Vice‐Chairperson and nominate a candidate for committee Chairperson for consideration by the
Agency, and
IURA Minutes
July 25, 2019
Page 8 of 18
WHEREAS, per the by‐laws, an Agency member shall fill either the committee Chairperson or
committee Vice‐Chairperson position, and
WHEREAS, officers of each committee serve a one‐year term, but continue to hold office until their
successor is selected or appointed, and
WHEREAS, the current Committee Chairperson and Vice‐Chairpersons are Chris Proulx and Doug
Dylla, respectively, and
WHEREAS, at its meeting of July 23, 2019, the Committee elected Doug Dylla as Vice‐Chairperson;
now, therefore be it
RESOLVED, that the IURA hereby appoints Chris Proulx as Chairperson of the IURA Economic
Development Committee.
Carried Unanimously: 5‐0
D. Committee Chairperson Report
None.
VII. Audit Committee
A. Approval of 2018 Financial Audit Report
Rosario explained the FY2018 Financial Audit Report raised no issues, findings, recommendations, or
concerns of any kind. Since the IURA is considered a component of the City, the IURA’s audit only
represents a small proportion of the overall City‐wide audit. The positive report also included a
programmatic audit of IURA’s CDBG projects.
Moved by Rosario, seconded by Farrell:
Approve Audited 2018 IURA Financial Report
WHEREAS, the Ithaca Urban Renewal Agency (IURA) derives the majority of its finances from grants
awarded to the City of Ithaca that are administered by the IURA, and
WHEREAS, for financial reporting purposes the IURA is a blended component unit of the City of Ithaca
whose financial activity is reported in the Special Grant Fund, a governmental fund of the City of Ithaca
financial statements, and
WHEREAS, the IURA contracts separate from the City to have its finances audited within 90 days of the
end of its fiscal year to comply with the Public Authorities Accountability Act, and
WHEREAS, the IURA received an audited 2018 IURA financial report on March 20, 2018, and
IURA Minutes
July 25, 2019
Page 9 of 18
WHEREAS, at its July 2019 meeting, the IURA Governance Committee reviewed the financial report and
attached correspondence, and
WHEREAS, at its July 2019 meeting, the IURA Audit Committee reviewed the financial report and
attached correspondence and recommends the following; now, therefore, be it
RESOLVED, that the Financial Report of the Ithaca Urban Renewal Agency for the period January 1,
2018 through December 31, 2018, prepared by the accounting firm of Insero & Company, LLP, be
approved.
Carried Unanimously: 5‐0
B. Appointment of Committee Chairperson
Moved by Farrell, seconded by Proulx:
Selection of 2019 IURA Audit Committee Chairperson
WHEREAS, IURA by‐laws provide that the committee membership shall elect its own committee
Vice‐Chairperson and nominate a candidate for committee Chairperson for consideration by the
Agency, and
WHEREAS, per the by‐laws, an Agency member shall fill either the committee Chairperson or
committee Vice‐Chairperson position, and
WHEREAS, officers of each committee serve a one‐year term, but continue to hold office until their
successor is selected or appointed, and
WHEREAS, the current Committee Chairperson and Vice‐Chairpersons are Eric Rosario and Karl
Graham, respectively, and
WHEREAS, at its July 25, 2019 meeting, the Committee elected Karl Graham as Vice‐Chairperson and
nominated Eric Rosario as Chairperson of the IURA Governance Committee; now, therefore be it
RESOLVED, that Eric Rosario is appointed as Chairperson of the IURA Audit Committee.
Carried Unanimously: 5‐0
C. Committee Chairperson Report
None.
IURA Minutes
July 25, 2019
Page 10 of 18
VIII. Governance Committee (GC)
A. Modification to Financing Terms for INHS Scattered Site Phase II Project (CD‐RLF #45/2018 #7)
Rosario explained the IURA approved a total of $260,000 for the INHS Scattered Site Preservation Phase 2
project, since renamed “Cayuga Flats.” The project recently received its Low‐Income Housing Tax Credit
(LIHTC) funding. Subsequent to the original project application, the 301 S. Geneva St. property was
removed from the project scope, resulting in an INHS repayment to the IURA of $31,338 towards the
CDBG loan. At this time, to maximize private investment and the State’s financial assistance, INHS is
requesting slightly different terms for the loan assistance. The proposal would result in an equivalent
dollar amount and would involve no substantive changes.
Moved by Graham, seconded by Rosario:
2018 AcƟon Plan ― ModificaƟon of Financing Terms for
INHS Scattered Site Phase 2 Project (2018 Project 7 & CD‐RLF #45)
WHEREAS, the IURA approved a total of $260,000 to the INHS Scattered Site Preservation Phase 2
project reconstruct or rehabilitate 29 rental housing units at the following locations:
203‐209 Elm Street
111 W. Clinton Street
406 S. Plain Street
227 S. Geneva Street
502 W. State Street, (Project) and
WHEREAS, the Project has been renamed as ‘Cayuga Flats’ by the sponsor, Ithaca Neighborhood
Housing Services, Inc. and
WHEREAS, IURA committed the following loan assistance to the Project:
EXISTING:
Source Amount Term Interest rate Repayment
Terms
CDBG
(CD‐RLF #45) $160,000 30 years 2% interest only Subject to cash
flow
HOME 2018 $100,000 TBD TBD TBD
And,
WHEREAS, the 301 S. Geneva St. property has been removed from the project scope resulting in
INHS repayment of $31,338 of the CDBG loan, and
WHEREAS, in May 2019, the Project was awarded an allocation of Low Income Housing Tax Credits
and other assistance from New York State Homes and Community Renewal, and
WHEREAS, the Project is subject to a 50‐year affordability agreement, and
IURA Minutes
July 25, 2019
Page 11 of 18
WHEREAS, to maximize private investment and NYS financial assistance, INHS requests the
following terms for IURA loan assistance:
PROPOSED:
Source Amount Term Interest rate Repayment
Terms
CDBG
(CD‐RLF #45) $128,662 30 years 0% annually
2% of loan
amount due
annually, cash
flow contingent
HOME 2018 $100,000 50 years 1% interest only Cash flow
contingent
WHEREAS, the outstanding loan balance and any accrued interest on IURA loan assistance is due
and payable at the end of the loan term, and
WHEREAS, at its July 19, 2019 meeting, the IURA Governance Committee considered this matter
and recommends approval of the requested loan terms; now, therefore, be it
RESOLVED, that the IURA hereby approves the following loan terms for assistance to the Cayuga
Flats project (formerly Scattered Site Preservation Project – Phase 2):
Source Amount Term Interest rate Repayment
Terms
CDBG
(CD‐RLF #45) $128,662 30 years 0% annually
2% of loan
amount due
annually, cash
flow contingent
HOME 2018 $100,000 50 years 1% interest only Cash flow
contingent
And be it further
RESOLVED, that the Director of Community Development is authorized to issue a revised loan
commitment letter to implement this resolution, and be it further
RESOLVED, that the IURA Chair, subject to review by IURA legal counsel, is authorized to execute
loan agreements to implement this resolution.
Carried Unanimously: 5‐0
IURA Minutes
July 25, 2019
Page 12 of 18
B. Appointment of Committee Chairperson
Moved by Proulx, seconded by Farrell:
Selection of 2019 IURA Governance Committee Chairperson
WHEREAS, IURA by‐laws provide that the committee membership shall elect its own committee
Vice‐Chairperson and nominate a candidate for committee Chairperson for consideration by the
Agency, and
WHEREAS, per the by‐laws, an Agency member shall fill either the committee Chairperson or
committee Vice‐Chairperson position, and
WHEREAS, officers of each committee serve a one‐year term, but continue to hold office until their
successor is selected or appointed, and
WHEREAS, the current Committee Chairperson and Vice‐Chairpersons are Eric Rosario and Kathy
Schlather, respectively, and
WHEREAS, at its July 19, 2019 meeting, the Committee elected Kathy Schlather as Vice‐Chairperson
and nominated Eric Rosario as Chairperson of the IURA Governance Committee; now, therefore be it
RESOLVED, that Eric Rosario is appointed as Chairperson of the IURA Governance Committee (GC).
Carried Unanimously: 5‐0
C. Election of IURA Officers
Moved by Rosario, seconded by Graham:
2019 Annual Election of IURA Officers
WHEREAS, officers of the IURA consist of a Chairperson, Vice Chairperson, and Secretary, and
WHEREAS, Section 2 of Article III of the IURA by‐Laws call for election of the Chairperson and Vice‐
Chairperson of the IURA at each annual May meeting of the Agency, and
WHEREAS, Section 2 of Article III of the IURA by‐Laws further states that the Agency shall appoint an
Executive Director, who shall serve as secretary to the Agency, and
WHEREAS, by resolution dated May 22, 2008, the IURA appointed the Director of Planning &
Development for the City of Ithaca, ex‐officio, as the IURA Executive Director, and
WHEREAS, per New York State enabling legislation creating the IURA, an IURA members serve at the
pleasure of the Mayor and shall continue to hold office until their successor is appointed, and
IURA Minutes
July 25, 2019
Page 13 of 18
WHEREAS, current IURA officers are:
• Svante Myrick, Chairperson
• Tracy Farrell, Vice‐Chairperson
• JoAnn Cornish, Secretary (ex‐officio as Director of Planning & Development), and
WHEREAS, the IURA Governance Committee discussed this matter at its July 19, 2019 meeting and
forwarded this matter for IURA action; now, therefore, be it
RESOLVED, that the IURA hereby elects Svante Myrick as Chairperson and Tracy Farrell as Vice‐
Chairperson of the IURA.
Carried Unanimously: 5‐0
D. Committee Chairperson Report
None.
IX. Neighborhood Investment Committee (NIC)
A. Appointment of Committee Chairperson
Moved by Farrell, seconded by Rosario:
Selection of 2019 IURA Neighborhood Investment Committee (NIC) Chairperson
WHEREAS, IURA by‐laws provide that the committee membership shall elect its own committee
Vice‐Chairperson and nominate a candidate for committee Chairperson for consideration by the
Agency, and
WHEREAS, per the by‐laws, an Agency member shall fill either the committee Chairperson or
committee Vice‐Chairperson position, and
WHEREAS, officers of each committee serve a one‐year term, but continue to hold office until their
successor is selected or appointed, and
WHEREAS, the current Committee Chairperson and Vice‐Chairpersons are Karl Graham and Tracy
Farrell, respectively, and
WHEREAS, at their July 12, 2019 meeting the Committee elected Fernando de Aragón as Vice‐
Chairperson and nominated Karl Graham as Chairperson of the IURA Neighborhood Investment
Committee; now, therefore be it
RESOLVED, that Karl Graham is appointed as Chairperson of the IURA Neighborhood Investment
Committee.
Carried Unanimously: 5‐0
IURA Minutes
July 25, 2019
Page 14 of 18
B. HUD Entitlement Program: Urban Bus Stop Upgrades ― Contract ModificaƟon (2017 Project #12)
Graham explained the Committee adopted a resolution, which was inadvertently omitted from today’s
agenda. The IURA originally allocated $25,000 in CDBG funds for upgrades to three bus stops.
Tompkins Consolidated Area Transit, Inc. (TCAT) has completed the work, but $5,120.67 in funding
remains unspent and unobligated. TCAT requests IURA approval to use those remaining funds for
additional work on the in‐bound bus stop on Elm Street at West Village Apartments. The existing bus
shelter would be relocated and a pad installed. The Committee recommends approving the contract
modification.
Farrell remarked the City should also make sidewalk‐related improvements near the bus stop, including
modifying the curb to make the sidewalk fully accessible.
Myrick replied he actually discussed the issue with City Transportation Engineer Eric Hathaway at a
recent Board of Public Works (BPW) meeting. Hathaway agreed to prioritize that work. Myrick will
follow up with Hathaway about the issue.
Mendizabal added that TCAT is performing some work on part of the sidewalk and curb.
Alternatively, Farrell noted, the City could simply compensate TCAT to perform the rest of the work.
Myrick replied that is certainly something that could be explored.
Moved by Graham, seconded by Farrell:
HUD EnƟtlement Program: Urban Bus Stop Upgrades ― Contract ModificaƟon
(2017, Project #12)
WHEREAS, the 2017 HUD Entitlement Program Action Plan allocated $25,000 in CDBG funds to
Project #12, Urban Bus Stop Dynamic Displays and Amenities Upgrade, sponsored by Tompkins
Consolidated Area Transit (TCAT) to upgrade three bus stops (Albany St. at Salvation Army, Third
Street at Hancock, and Chestnut Hill Apartments), and
WHEREAS, TCAT has completed upgrades at the three bus stops named in the 2017 Project #12,
Urban Bus Stop Dynamic Displays and Amenities Upgrade, and $5,120.67 of CDBG funding remains
unobligated, and
WHEREAS, on July 3, 2019, TCAT requested IURA permission to use $5,120.67 in remaining funds
from the 2017 Project #12 contract to make improvements at an additional bus stop, and
WHEREAS, TCAT has identified the in‐bound bus stop at on Elm Street at West Village Apartments as
needing improvements, including those to meet ADA‐compliance standards, and
WHEREAS, West Village Apartments provide affordable housing to 229 low‐to‐moderate income
households, and
IURA Minutes
July 25, 2019
Page 15 of 18
WHEREAS, the bus stop at West Village Apartments is a high‐ridership stop, with 14,600 in‐bound
boardings, and
WHEREAS, the Ithaca Urban Renewal Agency (IURA) is designated by the City of Ithaca as the Lead
Agency to develop, administer, and implement the HUD Entitlement Grant Program, including funds
received through the Community Development Block Grant (CDBG) Program, and
WHEREAS, the original project included upgrades at multiple bus stops with a city‐wide service area,
and the addition of a fourth bus stop does not change the number of low/moderate‐income
beneficiaries and therefore does not require a Program Amendment to the Action Plan; and
WHEREAS, this matter has been reviewed by the Neighborhood Investment Committee of the IURA,
which recommends the following; now therefore, be it
RESOLVED, the IURA approves a contract amendment with TCAT to expand the scope of services to
include establishment of an improved in‐bound bus stop at the Elm Street/West Village Place
intersection as a fourth site for improvement for the Urban Bus Stop Dynamic Displays and
Amenities Upgrade Project (2017, Project #12), and be it further
RESOLVED, that the contract amount shall remain at $25,000, and be it further
RESOLVED, that the IURA Chairperson, subject to review by IURA legal counsel, shall be authorized
to execute a contract amendment to implement this resolution.
Carried Unanimously: 5‐0
C. Committee Chairperson Report
Graham reported the Committee reviewed an Affordable Housing Production Report (1990‐2011)
spreadsheet, which listed all IURA‐ and City‐funded housing projects over that period, including
homeowner, rental, and rehabilitation projects. It is a good illustration of the impact the IURA and the
City have had on affordable housing in the community. At some point, the IURA Board may also like to
review it.
X. Other New/Old Business
A. Review of IURA Financials: June 2019
Bohn reported virtually all HUD Entitlement Program projects are progressing well, including prior slow
projects. Only the following two projects are experiencing delays at this time:
2018 Project 1: Neighbor to Neighbor Homeowner Rehab (CDBG)
2018 Project 18: Domestic Violence Center Renovation (CDBG)
IURA Minutes
July 25, 2019
Page 16 of 18
Bohn noted the Neighbor to Neighbor project has been delayed, partially because of leadership and
staffing changes. It is admittedly not a high‐capacity organization, since it relies so heavily on
volunteers. The project should recommence in earnest this Summer. He knows INHS has referred
some potential projects to Neighbor to Neighbor, which is also examining potential projects at Nate’s
Floral Estates.
Mendizabal added Neighbor to Neighbor has also begun collaborating with the Center for
Transformative Action, which is a significant organizational transition. IURA staff will meet with
Neighbor to Neighbor staff about the project.
Bohn reported the Domestic Violence Center is waiting for funding from the State’s Dormitory
Authority of the State of New York (DASNY), which usually seems to take a long time, and which has
delayed the project. Mendizabal will follow up with the center’s Executive Director. To a large extent, the
delay is beyond its control, since it needs enough funding on‐hand to hire a contractor.
Bohn reported all loan repayments are current, except the Finger Lakes School of Massage, which
represents the first time it has been delinquent since the school’s recent much‐publicized management
and accreditation crisis. Bohn has asked for an update on the situation from the school.
Bohn reported all lease payments were current this month, except the Ithaca Farmers’ Market, which
only just submitted its payment.
Bohn walked through the following financial reports:
IURA Minutes
July 25, 2019
Page 17 of 18
IURA Minutes
July 25, 2019
Page 18 of 18
B. IURA Chairperson Report
None.
C. Common Council Liaison Report
Lewis reported that the last Common Council meeting saw a large turn‐out of people concerned about
the April 6th altercation on the Commons involving the Ithaca Police Department. Some progress has
also been made on the City’s electric scooter policy. A working group has been developing a
Memorandum of Understanding with a local provider. A pilot scooter program would most likely not be
launched until Spring 2020. Myrick added that he conducted an internal investigation of the April 6th
incident. He and the Chief of Police identified 7 strategies to address the issue (e.g., de‐escalation and
implicit bias trainings).
Lewis reported Common Council has been engaged in ongoing discussions about minimum height
restrictions along State Street/Martin Luther King, Jr. Street, but has not yet made any decision, given
the complexity of the issues involved.
D. Staff Report
None.
XI. Adjournment
The meeting was adjourned by consensus at 10:32 A.M.
— END —