Loading...
HomeMy WebLinkAbout01_Project Manual and Specifications Student & Campus Life Multiple Deficiencies Code Remediation – Phase 1A Project Manual & Specifications March 13, 2019 Owner Cornell University Ithaca, NY 14853 Architect IBI Group 59-61 Court Street, Suite 300 Binghamton NY 13901 Tel: (607) 772-0007 STUDENT & CAMPUS LIFE MULTIPLE DEFICIENCIES CODE REMEDIATION – PHASE 1A CLARA DICKSON TABLE OF CONTENTS PAGE 1 Self – Pricing Invitation to Bid Self – Pricing Bid Form DIVISION 1 - GENERAL REQUIREMENTS Section 01 11 00 Summary of the Work Section 01 14 00 Work Restrictions Section 01 25 00 Substitutions and Product Options Section 01 31 19 Project Meetings Section 01 31 50 Electronic Project Management Section 01 32 16 Construction Schedules Section 01 33 00 Submittal Procedures Section 01 35 29 General Health & Safety Section 01 35 43 General Environmental Requirements Section 01 35 44 Spill Control Section 01 41 00 Regulatory Requirements Section 01 42 00 References Section 01 45 00 Quality Control Section 01 66 00 Storage and Protection Section 01 71 23 Field Engineering Section 01 77 00 Project Close Out Section 01 78 36 Warranties and Bonds Section 01 78 39 Record Documents STUDENT & CAMPUS LIFE MULTIPLE DEFICIENCIES CODE REMEDIATION – PHASE 1A CLARA DICKSON TABLE OF CONTENTS PAGE 2 DIVISION 2 – hazmat Section 02 82 02 Lead Based Paint Handling Procedures DIVISION 5 – Metals Section 05 01 70.61 Decorative Metal Repair Section 05 52 13 Pipe and Tube Railings DIVISION 9 – Painting Section 09 91 13 Exterior Painting Section 09 91 23 Interior Painting DRAWING LIST CDH – G000 COVER SHEET CDH – A100 LEVEL 1 FLOOR PLAN CDH – A101 LEVEL 2 FLOOR PLAN CDH – A102 LEVEL 3 FLOOR PLAN CDH – A103 LEVEL 4 FLOOR PLAN CDH – A104 LEVEL 5 FLOOR PLAN CDH – A300 ENLARGED STAIR PLANS CDH – A301 ENLARGED STAIR PLANS CDH – A302 STAIR DETAILS END OF DOCUMENT Rev.: 02-2017 BID FORM BF-1 STUDENT AND CAMPUS LIFE MULTIPLE DEFICIENCIES CODE REMEDIATION - PHASE 1A Cornell University, Ithaca, New York BID FORM Submitted by: Date To: Brenda Frank, Director Facilities Contracts 121 Humphreys Service Building Cornell University Ithaca, New York 14853 Gentlemen: The undersigned, (Name of Bidder) a (Type of Firm, State of Incorporation, if applicable) of (Address) having carefully examined the Short Form Contract, the Invitation to Bid and associated Bid Documents as well as the premises and conditions affecting the work, proposes to furnish all material, equipment, labor, plant, machinery, tools, supplies, services, applicable taxes and specified insurance necessary to perform the entire work, as set forth in, and in accordance with the said documents for the following considerations: 1. BASE BID a. All work complete, for the sum of ($ ) for MATERIALS, SUPPLIES, LABOR, and SERVICES AND ALL OTHER COSTS. Rev.: 02-2017 BID FORM BF-2 2. START OF WORK AND TIME FOR COMPLETION a. The undersigned agrees, if awarded the Contract, to commence work at the site within ten (10) calendar days after date of issuance of written notice to proceed and to complete the project no later than August 30th 2019. 3. ACCEPTANCE a. The undersigned agrees that this Proposal shall remain in force and effect for a period of not less than sixty (60) calendar days following the bid due date or such other time as may be agreed to by the Owner and Contractor. b. If written notice of acceptance of this Proposal is mailed, telegraphed or delivered to the undersigned within sixty (60) calendar days after the date of opening of Bids, or any time thereafter before this Proposal is withdrawn, the undersigned will within ten (10) calendar days after the date of such mailing, telegraphing or delivery of such notice, execute an Agreement between Contractor and Owner, amended and/or supplemented, if required, in accordance with the Proposal as accepted. c. It is understood and agreed that the Owner reserves the right to accept any of the Alternate Proposals listed within thirty (30) calendar days following the award of a construction contract. d. It is understood and agreed that the Owner reserves the right to reject any or all proposals, to waive any informalities in bidding, and to hold all proposals for the above noted period of time. 4. ADDENDUM RECEIPT a. Receipt of the following addenda to the Terms and Conditions, Drawings or Specifications is acknowledged: Addendum No. Dated: Addendum No. Dated: Addendum No. Dated: Rev.: 02-2017 BID FORM BF-3 CERTIFICATE OF NON-COLLUSION By submission of this bid, each bidder and each person signing on behalf of any bidder certifies, and in the case of a joint bid each party thereto certifies as to its own organization, under penalty of perjury, that to the best of his knowledge and belief: a. The prices in this bid have been arrived at independently without collusion, consultation, communication, or agreement, for the purpose of restricting competition, as to any matter relating to such prices with any other bidder or with any competitor. b. Unless required by law, the prices which have been quoted in this bid have not been knowingly disclosed by the bidder and will not knowingly be disclosed by the bidder prior to opening, directly or indirectly, to any other bidder or with any competitor. c. No attempt has been made or will be made by the bidder to induce any other persons, partnership, or corporation to submit or not submit a bid for the purpose of restricting competition. (Bidder) By: Title: Dated: Rev.: 02-2017 BID FORM BF-4 CERTIFICATE AS TO CORPORATE BIDDER I, _____________________________________________________, certify that I am the _____________________________ of the Corporation named as Bidder within this Bid Form for General Contractors; that __________________________________, who signed said Bid Form on behalf of the bidder was then _______________________________ of said Corporation; that I know his signature; that his signature thereto is genuine and that said Bid Form and attachments thereto were duly signed, sealed and executed for and in behalf of said Corporation by authority of its governing body. (Secretary-Clerk) (CORPORATE SEAL) Dated: MARCH 13, 2019 GENERAL REQUIREMENTS FOR STUDENT & CAMPUS LIFE MULTIPLE DEFICIENCIES CODE REMEDIATION – PHASE 1A CLARA DICKSON CORNELL UNIVERSITY ITHACA, NEW YORK MARCH 13, 2019 SECTION 01 11 00 SUMMARY OF WORK .....................................................................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 WORK UNDER OTHER CONTRACTS .........................................................3 1.3 CONTRACT MILESTONES .......................... Error! Bookmark not defined. 2.0 PRODUCTS – NOT USED .........................................................................................3 3.0 EXECUTION – NOT USED .......................................................................................3 SECTION 01 14 00 WORK RESTRICTIONS ..................................................................1 1.0 GENERAL ....................................................................................................................1 1.1 RELATED DOCUMENTS ...............................................................................1 1.2 CONTRACTOR USE OF PREMISES ..............................................................1 1.3 UNIVERSITY CLOSURES ..............................................................................2 1.4 WATER USE RESTRICTION ..........................................................................2 1.5 PARKING ..........................................................................................................2 1.6 CHANGEOVERS AND CONTINUITY OF SERVICES ................................3 1.7 OBSTACLES, INTERFERENCE AND COORDINATION ............................4 1.8 EXISTING EQUIPMENT, MATERIALS, FIXTURES, ETC. ........................4 1.9 EXAMINATION OF PREMISES, DRAWINGS, ETC. ...................................5 1.10 STAND DOWN DATES ...................................................................................6 1.11 WORKING HOURS ..........................................................................................7 2.0 PRODUCTS – NOT USED .........................................................................................7 3.0 EXECUTION – NOT USED .......................................................................................7 SECTION 01 25 00 SUBSTITUTIONS AND PRODUCT OPTIONS .............................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 DEFINITIONS ...................................................................................................1 1.3 ACTION SUBMITTALS ..................................................................................2 1.4 PRODUCTS LIST .............................................................................................2 1.5 QUALITY ASSURANCE .................................................................................2 1.6 PROCEDURES..................................................................................................3 1.7 EQUIVALENTS – APPROVED EQUAL ........................................................3 1.8 CONTRACTOR'S OPTIONS ............................................................................4 1.9 SUBSTITUTIONS .............................................................................................6 1.10 COMPARABLE PRODUCTS ..........................................................................7 1.11 CONTRACTOR'S REPRESENTATION ..........................................................8 1.12 ARCHITECT'S DUTIES ...................................................................................8 2.0 PRODUCTS – NOT USED .........................................................................................8 3.0 EXECUTION – NOT USED .......................................................................................8 SECTION 01 31 19 PROJECT MEETINGS ......................................................................1 MARCH 13, 2019 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 PRE-CONSTRUCTION MEETING .................................................................1 1.3 PROGRESS MEETINGS ..................................................................................3 1.4 LEED MEETINGS ............................................................................................4 1.5 PRE-INSTALLATION CONFERENCE(S) ......................................................5 1.6 COMMISSIONING MEETINGS ......................................................................5 2.0 PRODUCTS – NOT USED .........................................................................................6 3.0 EXECUTION – NOT USED .......................................................................................6 SECTION 01 31 50 ELECTRONIC PROJECT MANAGEMENT .................................1 1.0 GENERAL ....................................................................................................................1 1.1 SUMMARY .......................................................................................................1 1.2 RELATED SECTIONS .....................................................................................1 1.3 DEFINITIONS ...................................................................................................1 1.4 PROCEDURES..................................................................................................1 1.5 PROCESS OVERVIEW ....................................................................................2 1.6 ADDITIONAL INFORMATION ......................................................................5 2.0 PRODUCTS – NOT USED .........................................................................................5 3.0 EXECUTION – NOT USED .......................................................................................5 SECTION 01 32 16 CONSTRUCTION SCHEDULE .......................................................1 1.0 GENERAL ....................................................................................................................1 1.1 SUMMARY .......................................................................................................1 1.2 FORM OF SCHEDULES ..................................................................................1 1.3 CONTENT OF SCHEDULES ...........................................................................1 1.4 PROGRESS REVISIONS .................................................................................2 1.5 SUBMISSIONS .................................................................................................3 2.0 PRODUCTS - NOT USED ..........................................................................................3 3.0 EXECUTION ...............................................................................................................3 3.1 DISTRIBUTION................................................................................................3 SECTION 01 33 00 SUBMITTAL PROCEDURES ..........................................................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 SUBMITTAL REGISTRY AND SCHEDULE.................................................1 1.3 SHOP DRAWINGS ...........................................................................................3 1.4 PRODUCT DATA .............................................................................................3 1.5 SAMPLES..........................................................................................................4 1.6 QUALITY ASSURANCE AND QUALITY CONTROL SUBMITTALS.......5 1.7 COORDINATION DRAWINGS ......................................................................6 1.8 CONTRACTOR RESPONSIBILITIES ............................................................9 MARCH 13, 2019 1.9 SUBMITTAL PROCEDURES ........................................................................10 1.10 RECORD SUBMITTALS ...............................................................................12 1.11 RESUBMISSION REQUIREMENTS ............................................................12 1.12 ARCHITECT'S DUTIES .................................................................................12 1.13 DISTRIBUTION..............................................................................................13 2.0 PRODUCTS – NOT USED .......................................................................................14 3.0 EXECUTION – NOT USED .....................................................................................14 SECTION 01 35 29 GENERAL HEALTH & SAFETY ....................................................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 CONTRACTOR’S PROJECT SITE SPECIFIC PLAN ....................................1 1.3 ASBESTOS........................................................................................................2 1.4 LEAD .................................................................................................................3 1.5 MERCURY COLLECTION ............................ Error! Bookmark not defined. 1.6 ANIMAL USE FACILITIES-HAZARD COMMUNICATION ............. Error! Bookmark not defined. 1.7 SITE VISITS ......................................................................................................4 1.8 CONFINED SPACE ..........................................................................................4 2.0 PRODUCTS – NOT USED .........................................................................................4 3.0 EXECUTION – NOT USED .......................................................................................4 SECTION 01 35 43 GENERAL ENVIRONMENTAL REQUIREMENTS ....................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 RELATED SECTIONS .....................................................................................1 1.3 SUBMITTALS ..................................................................................................1 1.4 JOB SITE ADMINISTRATION .......................................................................1 1.5 CLEARING, SITE PREPARATION AND SITE USE .....................................2 1.6 SPOIL AND BORROW ....................................................................................2 1.7 NOISE AND VIBRATION ...............................................................................2 1.8 DUST CONTROL .............................................................................................3 1.9 PROTECTION OF THE ENVIRONMENT .....................................................3 1.10 TEMPORARY RE-ROUTING OF PIPING AND DUCTWORK ....................4 1.11 HAZARDOUS OR TOXIC MATERIALS .......................................................4 1.12 DISPOSAL OF WASTE MATERIAL AND TITLE ........................................5 2.0 PRODUCTS – NOT USED .........................................................................................5 3.0 EXECUTION – NOT USED .......................................................................................5 SECTION 01 35 44 SPILL CONTROL ..............................................................................1 1.0 GENERAL ....................................................................................................................1 1.1 SPILL PREVENTION .......................................................................................1 1.2 SPILL CONTROL PROCEDURES ..................................................................1 MARCH 13, 2019 1.3 SPILL REPORTING AND DOCUMENTATION ............................................4 2.0 PRODUCTS – NOT USED .........................................................................................5 3.0 EXECUTION – NOT USED .......................................................................................5 SECTION 01 41 00 REGULATORY REQUIREMENTS ................................................1 1.0 GENERAL ....................................................................................................................1 1.1 PERMITS AND LICENSES .............................................................................1 1.2 INSPECTIONS ..................................................................................................1 1.3 COMPLIANCE..................................................................................................2 1.4 OWNER’S REQUIREMENTS .........................................................................2 2.0 PRODUCTS – NOT USED .........................................................................................2 3.0 EXECUTION – NOT USED .......................................................................................2 SECTION 01 42 00 REFERENCES ....................................................................................1 1.0 GENERAL ....................................................................................................................1 1.1 INTENT OF CONTRACT DOCUMENTS.......................................................1 1.2 RELATED DOCUMENTS ...............................................................................2 1.3 DEFINITIONS ...................................................................................................2 1.4 OWNER AGREEMENTS .................................................................................4 1.5 INDUSTRY STANDARDS ..............................................................................4 1.6 ABBREVIATIONS AND ACRONYMS ..........................................................5 2.0 PRODUCTS - NOT USED ........................................................................................22 3.0 EXECUTION - NOT USED ......................................................................................22 SECTION 01 45 00 QUALITY CONTROL .......................................................................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 CONTROL OF ON-SITE CONSTRUCTION ..................................................1 1.3 CONTROL OF OFF-SITE OPERATIONS.......................................................2 1.4 TESTING ...........................................................................................................3 1.5 OWNER'S REPRESENTATIVE ......................................................................3 2.0 PRODUCTS – NOT USED .........................................................................................3 3.0 EXECUTION – NOT USED .......................................................................................3 SECTION 01 66 00 STORAGE AND PROTECTION ......................................................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 TRANSPORTATION AND HANDLING ........................................................1 1.3 ON-SITE STORAGE.........................................................................................1 1.4 PALM ROAD STORAGE .................................................................................2 1.5 PROTECTION ...................................................................................................2 1.6 PROTECTION AFTER INSTALLATION .......................................................3 MARCH 13, 2019 2.0 PRODUCTS – NOT USED .........................................................................................4 3.0 EXECUTION – NOT USED .......................................................................................4 SECTION 01 71 23 FIELD ENGINEERING .....................................................................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 QUALIFICATION OF SURVEYOR ................................................................1 1.3 SURVEY REFERENCE POINTS .....................................................................1 1.4 PROJECT SURVEY REQUIREMENTS ..........................................................2 1.5 RECORDS .........................................................................................................2 1.6 SUBMITTALS ..................................................................................................2 2.0 PRODUCTS – NOT USED .........................................................................................3 3.0 EXECUTION – NOT USED .......................................................................................3 SECTION 01 74 00 CONSTRUCTION WASTE MANAGEMENT .................. ERROR! BOOKMARK NOT DEFINED. 1.0 GENERAL .................................................. ERROR! BOOKMARK NOT DEFINED. 1.1 SUMMARY ..................................................... Error! Bookmark not defined. 1.2 DEFINITIONS ................................................. Error! Bookmark not defined. 1.3 PERFORMANCE REQUIREMENTS ............ Error! Bookmark not defined. 1.4 SUBMITTALS, GENERAL ............................ Error! Bookmark not defined. 1.5 ACTION SUBMITTALS ................................ Error! Bookmark not defined. 1.6 INFORMATIONAL SUBMITTALS .............. Error! Bookmark not defined. 1.7 QUALITY ASSURANCE ............................... Error! Bookmark not defined. 1.8 WASTE MANAGEMENT PLAN .................. Error! Bookmark not defined. 2.0 PRODUCTS – NOT USED ....................... ERROR! BOOKMARK NOT DEFINED. 3.0 EXECUTION ............................................. ERROR! BOOKMARK NOT DEFINED. 3.1 PLAN IMPLEMENTATION .......................... Error! Bookmark not defined. 3.2 SALVAGING DEMOLITION WASTE ......... Error! Bookmark not defined. 3.3 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL ....................................................... Error! Bookmark not defined. 3.4 RECYCLING DEMOLITION WASTE .......... Error! Bookmark not defined. 3.5 RECYCLING CONSTRUCTION WASTE .... Error! Bookmark not defined. 3.6 DISPOSAL OF WASTE.................................. Error! Bookmark not defined. SECTION 01 77 00 PROJECT CLOSEOUT .....................................................................1 1.0 GENERAL ....................................................................................................................1 1.1 INSPECTIONS ..................................................................................................1 1.2 SUBMITTALS ..................................................................................................2 1.3 FINAL CLEAN UP ...........................................................................................3 1.4 ON-SITE CONSTRUCTION TRAILER REMOVAL .....................................4 2.0 PRODUCTS – NOT USED .........................................................................................4 MARCH 13, 2019 3.0 EXECUTION – NOT USED .......................................................................................4 SECTION 01 78 36 WARRANTIES AND BONDS ...........................................................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 SUMMARY .......................................................................................................1 1.3 DEFINITIONS ...................................................................................................1 1.4 QUALITY ASSURANCE .................................................................................2 1.5 WARRANTY REQUIREMENTS.....................................................................2 1.6 SUBMITTAL REQUIREMENTS .....................................................................3 1.7 SUBMITTALS REQUIRED .............................................................................4 2.0 PRODUCTS – NOT USED .........................................................................................4 3.0 EXECUTION ...............................................................................................................4 3.1 FORM OF SUBMITTALS ................................................................................4 3.2 TIME OF SUBMITTALS .................................................................................5 3.3 ROOF WARRANTY PACKAGE .....................................................................5 SECTION 01 78 39 RECORD DOCUMENTS...................................................................1 1.0 GENERAL ....................................................................................................................1 1.1 DESCRIPTION..................................................................................................1 1.2 MAINTENANCE OF DOCUMENTS AND SAMPLES..................................1 1.3 RECORDING ....................................................................................................1 1.4 SUBMITTAL .....................................................................................................6 2.0 PRODUCTS – NOT USED .........................................................................................6 3.0 EXECUTION – NOT USED .......................................................................................6 CORNELL UNIVERSITY SECTION 01 11 00 Ithaca, New York SUMMARY OF THE WORK STUDENT AND CAMPUS LIFE SUMMARY OF WORK 01 11 00-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 11 00 SUMMARY OF WORK 1.0 GENERAL 1.1 DESCRIPTION A. Work to be Done The work to be done includes the following (refer to drawings and technical specifications for a full complement of the required work): 1. Test existing paint for lead on railing systems. Abate lead contained paint as described in Technical Specifications enough to accomplish work scope. 2. Test existing metals to be modified to determine metal compositions for welding. 3. Existing guardrail modifications shall include work in six (6) interior stairwells spanning five (5) stories in height: a. Extend existing metal newel posts with like material by cutting and welding new sections in place. b. Add horizontal steel railing material to comply with Building Code height and spacing regulations. c. Add steel fall protection at existing window well locations adjacent to stairwells. 4. Remove, extend, and re-install existing hand/guardrails at one half flight exterior stair. 5. Prepare, prime, and paint all affected railings and posts to match existing colors and sheens. a. Paint posts top to bottom. b. Paint new railing work. c. Touch up paint any additional areas disturbed during construction. B. The Scope of the Work 1. The scope of the WORK in all SECTIONS of this Specification shall consist of the furnishing of all labor, materials, equipment and appliances and the performance of the Work required by the Contract Documents and/or by the conditions at the site, joining CORNELL UNIVERSITY SECTION 01 11 00 Ithaca, New York SUMMARY OF THE WORK STUDENT AND CAMPUS LIFE SUMMARY OF WORK 01 11 00-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A all parts of this Work with itself and the Work of others to form a complete, functioning entity. 2. Items not specifically mentioned in the Specifications or shown on the drawings, but which are inherently necessary to make a complete working installation, shall be included. 3. It is the intent and purpose of the Contract Documents to cover and include under each item all materials, machinery, apparatus, and labor necessary to properly install materials and equipment, adjust and put into perfect operation the respective portions of the installation specified and to so interconnect the various items or sections of the work as to form a complete and operating whole. Any equipment, apparatus, machinery, material and small items not mentioned in detail, and labor not hereinafter specifically mentioned, which may be found necessary to complete or perfect any portion of the installation in a substantial manner, and in compliance with the requirements stated, implied, or intended in the Contract Documents, shall be furnished without extra cost to the Owner. The Contractor shall provide the greatest quantity, highest quality, highest degree of safety, and most stringent material, equipment or Work. Should the Drawings or the Specifications disagree in themselves or with each other, the Contractor shall provide the better quality or greater quantity of work and/or materials unless otherwise directed by written addendum to the Contract. CORNELL UNIVERSITY SECTION 01 11 00 Ithaca, New York SUMMARY OF THE WORK STUDENT AND CAMPUS LIFE SUMMARY OF WORK 01 11 00-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1.2 WORK UNDER OTHER CONTRACTS A. The Contractor shall cooperate with other contracts performing related work, including providing labor, materials and other costs necessary to satisfactorily coordinate the Contract work with work performed under others contracts. B. Concurrent / Future Work: 1. New paint and carpet work may occur in other areas, not in scope of work. C. New York State Electric & Gas (NYSEG): 1. Contractor shall be responsible for the project management of NYSEG work including coordinating any scheduling associated with the Project. 2. The Owner shall be responsible for the cost associated with the work to be performed by NYSEG. No NYSEG costs shall be carried in the Contractor’s bid. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 11 00*** CORNELL UNIVERSITY SECTION 01 14 00 Ithaca, New York WORK RESTRICTIONS STUDENT AND CAMPUS LIFE WORK RESTRICTIONS 01 14 00-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 14 00 WORK RESTRICTIONS 1.0 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General Conditions and Division 1 Specification Sections, apply to this Section. 1.2 CONTRACTOR USE OF PREMISES A. All traffic and pedestrian control measures shall be compliant with the National Manual on Uniform Traffic Control Devices for Streets and Highways (MUTCD) and 17 NYCRR Chapter V (New York Supplement), (https://www.dot.ny.gov/mutcd) and all other local laws and regulations. B. The Contractor shall carry on the Work in the manner which will cause the least interruption to pedestrian and vehicular traffic and permit access of emergency vehicles at all times. C. The Work shall be scheduled and performed in such a manner that at least one lane of traffic will be maintained on all public streets. Two flag persons, equipped with radio communication devices, must be provided for any activity blocking a traffic lane. One lane of traffic must be maintained at all times. Where traffic must cross open trenches, the Contractor shall provide suitable bridges and railings; including pedestrian bridges. D. The Contractor shall maintain 20’ minimum fire lane access to all facilities in the area. E. The Contractor shall post and maintain flag persons and suitable signs indicating that construction operations are under way and other warning signs as may be required. F. The Contractor shall safeguard the use by the public and Owner of all adjacent highways, roadways and footpaths, outside the Contract Limit Lines (work area), and shall conform to all laws and regulations concerning the use thereof, especially limitations on traffic and the movement of heavy equipment. Access to the site for delivery of construction materials and/or equipment shall be made only at the locations shown in the Contract Documents or approved by the Owner’s Representative. G. The Contractor shall make every effort to keep dirt and debris from making its way to roadways. The Contractor shall immediately remove dirt and debris which may collect on permanent roadways due to the Work. H. The Contractor shall limit the extent of its activities to that area of the site defined on the Contract Drawings as being within the Contract Limit Lines. CORNELL UNIVERSITY SECTION 01 14 00 Ithaca, New York WORK RESTRICTIONS STUDENT AND CAMPUS LIFE WORK RESTRICTIONS 01 14 00-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A I. For that portion of the Work required under this Contract which must be performed in other than the defined areas both on-site and off, including operations involving delivery and removal of materials, the Contractor shall schedule and coordinate its activities through the Owner's Representative, to meet the approval of the Owner and minimize disruption of the normal scheduled activities of the occupants of adjacent spaces. J. It is the Owner’s expectation that the Contractor will take protective measures to minimize damage caused by construction activities including, but not limited to, the use of personnel lifts, material handling equipment, on-site material storage, etc. All portions of the site, including the staging area and those areas affected by the work, shall be returned to their original condition after completion of Work. Such repair work shall include lawn restoration and reseeding, if required, and shall be included in the Contractor's Guarantee of Work. K. Routes to and from the location of the Work shall be as indicated in the Contract or as directed by the Owner's Representative. Temporary roadways shall be closed only with prior approval of the Owner's Representative. 1.3 UNIVERSITY CLOSURES A. In the event of University closure, the Contractor should use their judgement, follow their internal guidance on continuity of operations, and the direction of law enforcement, as to whether or not they will maintain operations on construction sites on campus. They should make this decision with the awareness that Cornell response to any project needs (shutdowns, emergencies) will not possible and the maintenance of roads and walks will not be to normal operating standards. B. With your safety as a top priority, the Cornell University Police allows you the ability to take advantage of our Emergency Mass Notification System that enables your cellphone to become a personal safety device for you. Contractor’s wishing to participate may text the following: CornellAlert to 67283 and you will be set up to receive alert messages. Be advised that you may stop receiving messages at any time by sending “stop” to CornellAlert. There will also be a system generated “stop” every year on August 1st at which point you will need to send the text CornellAlert to re-enlist. 1.4 WATER USE RESTRICTION C. The Contractor shall adhere to any University issued Water Use Restrictions in place at the time of construction. 1.5 PARKING A. The Owner may designate an area for parking of essential Contractor vehicles on the project site. B. The Contractor shall make all arrangements, and bear the cost, for transportation of all trade persons from the designated parking area to the construction site as necessary. C. It should be noted that there is a fee for all parking on the Cornell University campus. The Contractor is responsible for the payment for all parking costs imposed by the Owner. The Contractor should contact the Project Manager (Caterina McFadden) for additional CORNELL UNIVERSITY SECTION 01 14 00 Ithaca, New York WORK RESTRICTIONS STUDENT AND CAMPUS LIFE WORK RESTRICTIONS 01 14 00-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A information. The Contractor will be required to complete a “New Construction Employee Form” for each permit requested. This form may be found at http://finance.fs.cornell.edu/contracts/forms/contractors.cfm. D. Contractor shall cooperate with Transportation Services and/or other authorities having jurisdiction, as follows: 1. Ensure parking by all employees of the Contractor, subcontractors, material suppliers, and others connected with this project only within construction fence or the designated parking area. 2. Prohibit employees from parking in any other areas, roads, streets, grounds, etc. 3. Discharge any employee refusing to comply with these requirements. 4. Ensure proper transportation of personnel between the designated parking area and the construction site. E. The Contractor shall remove from the parking area and staging area all temporary trailers, rubbish, unused materials, and other materials belonging to the Contractor or used under the Contractor’s direction during construction or impairing the use or appearance of the property and shall restore such areas affected by the work to their original condition, and, in the event of its failure to do so, the same shall be removed by the Owner at the expense of the Contractor, and the Contractor shall be liable therefore. 1.6 CHANGEOVERS AND CONTINUITY OF SERVICES A. Make all changeovers, tie-ins and removals, etc., of any part of the Work that would affect the continuity of operation of the adjacent services at approved times that will not interfere with the Owner's operations. Secure approval of Owner before proceeding. B. Make all necessary temporary connections required to permit operation of the building services and/or equipment. Remove the connections after need has ceased. C. The Contractor may be permitted to make changeovers during normal working hours at the Owner’s discretion. Should the Contractor perform this Work outside of normal working hours, no extra payment will be made for resulting overtime expenses. D. When connecting new facilities do not shut off any existing Mechanical/Electrical facilities or services without prior written approval of Owner's Representative. E. The Contractor shall not, except in an emergency condition, shutdown any utility without the express permission of the Owner's Representative. Major, affecting life safety or outside contract limit lines, shutdowns of utilities will be performed by Cornell University to enable Contractor to perform required work. Major shutdowns shall be defined as those affecting life safety or which are outside the project site limits. F. Maintain domestic water and firewater in service at all times. No service may be out for more than twenty-four (24) hours. Maintain firewater flow capability (hose, if necessary) to all buildings and coordinate with Cornell Utilities, Cornell Environmental Health and Safety (EH&S), and City of Ithaca Fire Department. CORNELL UNIVERSITY SECTION 01 14 00 Ithaca, New York WORK RESTRICTIONS STUDENT AND CAMPUS LIFE WORK RESTRICTIONS 01 14 00-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A G. All shutdowns to be scheduled a minimum of seven (7) calendar days in advance and requests shall be submitted via ePM system to the Owner’s Representative. It is anticipated that each stairwell requiring cutting and welding of existing and new metal railings will require a shutdown of smoke alarms. The shutdown, restart, and testing will be performed by Cornell University staff. H. IN THE EVENT OF AN EMERGENCY WHERE THE OWNER'S REPRESENTATIVE IS NOT AVAILABLE, THE CONTRACTOR SHALL DIAL 911 IMMEDIATELY. 1.7 OBSTACLES, INTERFERENCE AND COORDINATION A. General 1. Plans show general design arrangement. Install work substantially as indicated and verify exact location and elevations; DO NOT SCALE PLANS. 2. Due to small scale of Drawings, it is not possible to indicate all offsets, fittings, changes in elevations, interferences, etc. Make necessary changes in the Work, equipment locations, etc., after notification to the Owner's Representative and Architect. Obtain approval from same, as part of Contract, to accommodate work to obstacles and interferences encountered. 3. Obtain written approval for all major changes before installing. If requested, submit drawings, detailing all such deviations or changes. 4. Exposed to view mechanical units, ductwork, conduit, pipes or other building equipment are essential parts of the artistic effect of the building design and shall be installed in locations as shown on the drawings. Conformance to given dimensions and alignments with the structural system, walls, openings, indicated centerlines are a requirement of the Contract and the Contractor shall familiarize himself with the critical nature of proper placement of these items. The Contractor shall notify the Architect of conflicts which would cause such equipment to be installed in locations other than as indicated on the Drawings. The Contractor shall not proceed with the installation of exposed to view mechanical units, ductwork, conduit, pipes, etc. until all conflicts have been identified by the Contractor and resolutions to conflicts approved by the Architect. B. Interference 1. Install work so that all items are operable and serviceable and avoid interfering with removal of rails, filters, belt guards and/or operation of doors, etc. Provide easy and safe access to valves, controllers, motor starters and other equipment requiring frequent attention. 1.8 EXISTING EQUIPMENT, MATERIALS, FIXTURES, ETC. A. Where existing equipment, piping, fittings, etc. are to be removed, Contractor shall submit complete list to Owner. All items that Owner wishes to retain shall be carefully removed and salvaged and delivered to building storage where directed by Owner. Items that Owner does not wish to retain shall be removed from the site and legally disposed. CORNELL UNIVERSITY SECTION 01 14 00 Ithaca, New York WORK RESTRICTIONS STUDENT AND CAMPUS LIFE WORK RESTRICTIONS 01 14 00-5 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1.9 EXAMINATION OF PREMISES, DRAWINGS, ETC. A. Before Submitting Proposal 1. Examine all Drawings and Specifications relating to Work of all trades to determine scope and relation to other work. 2. Examine all existing conditions affecting compliance with Plans and Specifications, by visiting site and/or building. 3. Ascertain access to site, available storage and delivery facilities. B. Before Commencing Work on Any Phase or in any Area 1. Verify all governing dimensions at site and/or building. 2. Inspect all adjacent work. 3. All work is to be conducted in such a manner as to cause a minimum degree of interference with the Campus’ operation and academic schedule. Prior to the commencement of each phase, submit Shutdown / Demo action plans that clearly describe the steps required to safely shut down utilities, systems and infrastructure that are within the work area (or effecting the work area); and those outside the work area and within approximately 25 feet of the work area limits, as approved by the Owner. The Shutdown / Demo action plan shall identify the shut off point(s) for each utility, system and infrastructure as well as the secondary shut off point(s) to account if the primary points fail or are otherwise inaccessible. To identify shutoff points, trace each utility, system and infrastructure in the presence of the campus representative from the work area to the shutoff points and place clear label on same indicating what the shutoff point is and what it effects and whether it is the primary or secondary shut off. The Shutdown / Demo action plan shall describe the shutdown procedure, identify tools and material required for shutdown, sequence of activities required for proper shutdown, the name of the person(s) or trade(s) deemed competent to perform each activity in the shutdown sequence and names and telephone numbers of the campus staff required to provide access to shut off points, assist in the shut off or perform portions of the shutdown activities. Additionally, the plan will address the Contractor’s plan for maintaining MEP to adjacent occupied areas, inclusive of planned tie-in points for any and all necessary, temporary infrastructure, alarming, monitoring etc. Submit the Shutdown / Demo action plan for review and approval at least two weeks prior to field work in the work area. Field work shall not begin until the Shutdown / Demo action plan is reviewed. Contractor is to assign and include a competent crew, knowledgeable of each unique system involved (i.e. Mechanic, Electrician, Sheet metal, Plumber, Controls, IT, etc.). Field investigation is to include any and all necessary ladders, scaffold, temp lighting, cutting tools, photos, labels, PPE, etc. needed to properly locate, access and label shut off points. The University is explicitly requesting heightened awareness and an earnest mitigation of impact. This requirement supplements all other contractual obligations, and requires the dedication of no less than an aggregate 40 hours. C. Tender of Proposal Confirms Agreement CORNELL UNIVERSITY SECTION 01 14 00 Ithaca, New York WORK RESTRICTIONS STUDENT AND CAMPUS LIFE WORK RESTRICTIONS 01 14 00-6 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1. All items and conditions referred to herein and/or indicated on accompanying Drawings. 2. No consideration, additional monies or time extensions will be granted for alleged misunderstanding. D. Existing or Archived Drawings 1. Existing or Archived drawings of impacted buildings are appended in electronic format only for reference and informational purposes. These historic drawings are not to be considered contract drawings and are provided “FOR INFORMATION ONLY”. The Owner makes no representation as to the accuracy of the drawings as representing current conditions. 1.10 STAND DOWN DATES A. Strict and effective enforcement by Contractor’s management and supervision of the following dates and hours is required. a. Exam Quiet week and Spring Exams  Wednesday, May 8  Thursday, May 9  Friday, May 10th, 2019  Saturday, May 11th, 2019  Sunday, May 12th, 2019  Monday, May 13th, 2019  Tuesday, May 14th, 2019  Wednesday, May 15th, 2019  Thursday, May 16th, 2019  Friday, May 17th, 2019  Saturday, May 18th, 2019 b. Commencement Weekend  Saturday, May 25th, 2019  Sunday, May 26th, 2019 c. Reunion Weekend  Saturday, June 8th, 2019  Sunday, June 9th, 2019 1. Restricted Work Dates (delivery & demolition restrictions but otherwise work as usual): Friday, May 24th, 2019 Commencement weekend- deliveries and work outside fence stop at noon Thursday, Friday June 6 - 9, 2019 Reunion guest arrivals- no work outside fence; no demo or utility work inside fence CORNELL UNIVERSITY SECTION 01 14 00 Ithaca, New York WORK RESTRICTIONS STUDENT AND CAMPUS LIFE WORK RESTRICTIONS 01 14 00-7 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A Friday, June 6th, 2019 Reunion weekend- deliveries and work outside fence stop at noon 2. Student and Campus Life Residence Halls Open August 23, 2019  No deliveries, no hauling materials into or out of the project site.  All work to be contained to the fenced area of the project site. 1.11 WORKING HOURS A. Normal work hours are 9:30AM-dusk Monday-Saturday except during above noted restrictions. This means that Contractor shall not permit any noise generating activities that could disturb campus occupants or residents to take place outside of these hours. Should any conditions necessitate work to extend beyond these hours – Contractor may submit a detailed request with reasonable advance notice to Cornell. Cornell (at its sole discretion) may issue a written relaxation of the above but Contractor is advised never to assume that it will be granted. B. During Construction periods, no work shall take place prior to 9:30AM in a Residence Hall, Fraternity, Co-Op, Sorority, or any type of Housing Unit. Residence Halls require 72 hours notification to the Student & Academic Services representative prior to entering a Residence Hall or Student Room. This does not apply to Fraternity, Co-Op or Sorority House which require 24 hours notification to the Facilities Manager. C. Contractor shall be responsible to complete and submit a Dispensation of Hours to the Department of Labor for overtime or extended hours desired to be worked on the project as needed. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 14 00*** CORNELL UNIVERSITY SECTION 01 25 00 Ithaca, New York SUBSTITUTIONS AND PRODUCT OPTIONS STUDENT AND CAMPUS LIFE SUBSTITUTIONS 01 25 00-1 MULTIPLE DEFICIENCIES AND PRODUCT OPTIONS March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 25 00 SUBSTITUTIONS AND PRODUCT OPTIONS 1.0 GENERAL 1.1 DESCRIPTION A. The Contractor shall furnish and install the products specified, under the options and conditions for substitutions stated in this Section. 1.2 DEFINITIONS A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor. 1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions that are beyond the Contractor’s control, such as unavailability of product, or regulatory changes. a. Products that are not available from Contractor’s preferred suppliers does not constitute unavailability of product. 2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner. B. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent. 1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents. 2. New Products: Items that have not previously been incorporated into another project or facility. Items salvaged from other projects are not considered new products. Items that are manufactured or fabricated to include recycled content materials are considered new products, unless indicated otherwise. 3. Comparable Product: Product that is demonstrated and approved through submittal process to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product. CORNELL UNIVERSITY SECTION 01 25 00 Ithaca, New York SUBSTITUTIONS AND PRODUCT OPTIONS STUDENT AND CAMPUS LIFE SUBSTITUTIONS 01 25 00-2 MULTIPLE DEFICIENCIES AND PRODUCT OPTIONS March 13, 2019 CODE REMEDIATION – PHASE 1A C. Basis-of-Design Product Specification: A specification in which a specific manufacturer's product is named and accompanied by the words "basis-of-design product," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of additional manufacturers named in the specification. 1.3 ACTION SUBMITTALS A. Substitution Requests: Submit indicated number of copies of each Substitution Request Form, attached hereto, for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles. 1. In addition to submission of Substitution Request Form, substitutions shall be listed on the Bid Form with description, specification references, and corresponding change in base bid 1.4 PRODUCTS LIST A. Within thirty (30) days after the award of Contract, submit to the Architect five copies of a complete list of products which are proposed for installation. B. Tabulate the products by listing under each specification section title and number. C. For products specified only by reference standards, list for each such product: 1. Name and address of the manufacturer. 2. Trade name. 3. Model or catalog designation. 4. Manufacturer's data: a. Reference standards. b. Performance test data. 1.5 QUALITY ASSURANCE A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers. B. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, select product compatible with products previously selected, even if previously selected products were also options. CORNELL UNIVERSITY SECTION 01 25 00 Ithaca, New York SUBSTITUTIONS AND PRODUCT OPTIONS STUDENT AND CAMPUS LIFE SUBSTITUTIONS 01 25 00-3 MULTIPLE DEFICIENCIES AND PRODUCT OPTIONS March 13, 2019 CODE REMEDIATION – PHASE 1A 1. Contractor is responsible for providing products and construction methods compatible with other products and construction methods. 2. If a dispute or compatibility issue arises over concurrently selectable but incompatible products, Architect will determine which products shall be used. 1.6 PROCEDURES A. Coordination: Modify or adjust affected work as necessary to integrate work of accepted substitutions and approved comparable products. 1.7 EQUIVALENTS – APPROVED EQUAL A. Equivalents or Approvals - General 1. The words “similar and equal to”, or “or equal”, “equivalent” and such other words of similar content and meaning shall for the purposes of this Contract be deemed to mean similar or equivalent to one of the named products. For the purposes of Paragraph A and B of this Section 1.4 and for the purposes of Bidding Documents, the word “products” shall be deemed to include the words “articles”, “materials”, “items”, “equipment” and “methods”. Whenever in the Contract documents one or more products are specified, the words “similar and equal to” shall be deemed inserted. 2. Whenever any product is specified in the Contract documents by a reference to the name, trade name, make or catalog number of any manufacturer or supplier, the intent is not to limit competition, but to establish a standard of quality which the Architect has determined is necessary for the Project. The Contractor may at its option use any product other than that specified in the Contract Documents provided the same is approved by the Architect in accordance with the procedures set forth in Paragraph B of this Section 1.4. In all cases the Architect shall be the sole judge as to whether a proposed product is to be approved and the Contractor shall have the burden of proving, at its own cost and expense, to the satisfaction of the Architect, that the proposed product is similar and equal to the named product. In making such determination the Architect may establish such objective and appearance criteria as it may deem proper that the proposed product must meet in order for it to be approved. 3. Nothing in the Contract Documents shall be construed as representing, expressly or implied, that the named product is available or that there is or there is not a product similar and equal to any of the named products and the Contractor shall have and make no claim by reason of the availability or lack of availability of the named product or of a product similar and equal to any named product. 4. The Contractor shall have and make no claim for an extension of time or for damages by reason of the time taken by the Architect or by reason of the failure of the Architect to approve a product proposed by the Contractor. 5. Request for approval of proposed equivalents will be received by the Architect only from the Contractor. CORNELL UNIVERSITY SECTION 01 25 00 Ithaca, New York SUBSTITUTIONS AND PRODUCT OPTIONS STUDENT AND CAMPUS LIFE SUBSTITUTIONS 01 25 00-4 MULTIPLE DEFICIENCIES AND PRODUCT OPTIONS March 13, 2019 CODE REMEDIATION – PHASE 1A B. Equivalents or Approvals After Bidding 1. Request for approval of proposed equivalents will be considered by the Architect after bidding only in the following cases: (a) the named product cannot be obtained by the Contractor because of strikes, lockouts, bankruptcies or discontinuance of manufacturer and the Contractor makes a written request to the Architect for consideration of the proposed equivalent within ten (10) calendar days of the date it ascertains it cannot obtain the named product; or (b) the proposed equivalent is superior, in the opinion of the Architect, to the named product; or (c) the proposed equivalent, in the opinion of the Architect, is equal to the named product and its use is to the advantage of the Owner, e.g., the Owner receives an equitable credit, acceptable to it, as a result of the estimated cost savings to the Contractor from the use of the proposed equivalent or the Owner determines that the Contractor has not failed to act diligently in placing the necessary purchase orders and a savings in the time required for the completion of the construction of the Project should result from the use of the proposed equivalent; or (d) the proposed equivalent, in the opinion of the Architect, is equal to the named product and less than ninety (90) calendar days have elapsed since the Notice of Award of the Contract. 2. Where the Architect pursuant to the provisions of this Section 1.4 approves a product proposed by the Contractor and such proposed product requires a revision or redesign of any part of the work covered by this Contract, all such revision and redesign and all new Drawings and details required therefore shall be subject to approval of the Architect and shall be provided by the Contractor at its own cost and expense. 3. Where the Architect pursuant to the provisions of this Section approves a product proposed by the Contractor and such proposed product requires a different quantity and/or arrangement of duct work, piping, wiring, conduit or any other part of the work from that specified, detailed or indicated in the Contract Documents, the contractor shall provide the same at its own cost and expense. 1.8 CONTRACTOR'S OPTIONS A. For products specified only by reference standard, select any product meeting that standard, by any manufacturer. B. For products specified by naming several products or manufacturers, select any one of products and manufacturers named. 1. Products: a. Restricted List (Products): Where Specifications include paragraphs or subparagraphs titled “Products” or that include the phrase “provide one of the following”, and include a list of names of both manufacturers and products, provide one of the products listed that complies with requirements. Comparable products for Contractor's convenience will not be considered. - Substitutions may be considered, unless otherwise indicated. CORNELL UNIVERSITY SECTION 01 25 00 Ithaca, New York SUBSTITUTIONS AND PRODUCT OPTIONS STUDENT AND CAMPUS LIFE SUBSTITUTIONS 01 25 00-5 MULTIPLE DEFICIENCIES AND PRODUCT OPTIONS March 13, 2019 CODE REMEDIATION – PHASE 1A b. Non-restricted List (Available Products): Where Specifications include paragraphs or subparagraphs titled “Available Products” or that include the phrase “include, but are not limited to, the following”, and include a list of names of both available manufacturers and products, provide one of the products listed, or an unnamed product, that complies with requirements. Comply with requirements in "Comparable Products" Article for consideration of an unnamed product. 2. Manufacturers: a. Restricted List (Manufacturers): Where Specifications include paragraphs or subparagraphs titled “Manufacturers” or that include the phrase “provide products by one of the following”, and include a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements. Comparable products for Contractor's convenience will not be considered. - Substitutions may be considered, unless otherwise indicated. b. Non-restricted List (Available Manufacturers): Where Specifications include paragraphs or subparagraphs titled “Available Manufacturers” or that include the phrase “include, but are not limited to, the following”, and include a list of available manufacturers, provide a product by one of the manufacturers listed, or a product by an unnamed manufacturer, that complies with requirements. Comply with requirements in "Comparable Products" Article for consideration of an unnamed manufacturer's product. 3. Basis-of-Design Product: Where Specifications name a product, or refer to a product indicated on Drawings, and include a list of manufacturers, provide the specified or indicated product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. a. Restricted List (List of Manufacturers): Where Specifications include paragraphs or subparagraphs titled “Basis-of-Design Product”, and include a list of other manufacturers' names, provide the specified or indicated product or a comparable product by one of the other named manufacturers that complies with requirements. - Comply with requirements in "Comparable Products" Article for consideration of an unnamed product by one of the other named manufacturers. - Substitutions may be considered, unless otherwise indicated. b. Non-restricted List (No List of Manufacturers): Where Specifications include paragraphs or subparagraphs titled “Basis-of-Design Product”, and do not include a list of other manufacturers’ names, provide the specified or indicated product or a comparable product by another manufacturer that complies with requirements. Comply with requirements in "Comparable Products" Article for consideration of an unnamed manufacturer's product. CORNELL UNIVERSITY SECTION 01 25 00 Ithaca, New York SUBSTITUTIONS AND PRODUCT OPTIONS STUDENT AND CAMPUS LIFE SUBSTITUTIONS 01 25 00-6 MULTIPLE DEFICIENCIES AND PRODUCT OPTIONS March 13, 2019 CODE REMEDIATION – PHASE 1A C. For products specified by naming one or more products or manufacturers and stating "or equal", the Contractor shall submit a request as for substitutions, for any product or manufacturer not specifically named. Such substitution shall have been listed on Bid Form as required in Instructions to Bidders. If not so listed, no substitution will be allowed. D. For products specified by naming only one product and manufacturer, no option and no substitution will be considered unless listed on the Bid Form as provided in the Instructions to Bidders. Base Bid must include the specified product or manufacturer. Substitutions will be at the sole discretion of the Owner. 1.9 SUBSTITUTIONS A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 21 days prior to time required for preparation and review of related submittals. B. Substitutions for Convenience: Submit requests for substitution within thirty (30) days of contract award. C. Submit a separate request for each substitution. Support each request with: 1. Completed "Request for Substitution" form in eBuilder. A request for substitution of a product, material, or process for that specified in the Contract Documents must be formally submitted as such accompanied by evidence that the proposed substitution ﴾1﴿ is equal in quality and serviceability to the specified item; ﴾2﴿ will not entail changes in detail and construction of Other Work; ﴾3﴿ will be acceptable to the Architect and Owner's Design Consultant's in achieving design and artistic intent; and ﴾4﴿ will not result in a cost and/or schedule disadvantage. 2. Complete data substantiating compliance of the proposed substitution with requirements stated in Contract Documents: a. Product identification, including manufacturer's name and address. b. Manufacturer's literature; identify: - Product description. - Reference standards. - Performance and test data. c. Samples, as applicable. d. Name and address of similar projects on which product has been used, and the date of each installation. 3. An itemized comparison of the proposed substitution with the product specified listing any variations. 4. Data relating to any changes in the construction schedule. CORNELL UNIVERSITY SECTION 01 25 00 Ithaca, New York SUBSTITUTIONS AND PRODUCT OPTIONS STUDENT AND CAMPUS LIFE SUBSTITUTIONS 01 25 00-7 MULTIPLE DEFICIENCIES AND PRODUCT OPTIONS March 13, 2019 CODE REMEDIATION – PHASE 1A 5. The effect of the substitution on each separate contract of the Project. 6. List any changes required in other work or projects. 7. Designate any required license fees or royalties. 8. Designate availability of maintenance services, and source of replacement materials. D. Substitutions shall not result in additions to the Contract Sum. E. Substitutions will not be considered as having been accepted when: 1. They are indicated or implied on shop drawings or product data submittals without a formal request from the Contractor. 2. They are requested by a subcontractor or supplier. 3. The acceptance will require substantial revision of Contract Documents. F. Substitute products shall not be ordered or installed without written acceptance of the Owner. G. The Owner and the Architect shall be the sole judges of the acceptability of a proposed substitution. 1.10 COMPARABLE PRODUCTS A. Conditions for Consideration: Contractor's request for approval of comparable product will be considered when the following conditions are satisfied. If the following conditions are not satisfied, Architect may reject or return requests without action, except to record noncompliance with these requirements. Where products or manufacturers are specified by name, submit the following, in addition to other required submittals, to obtain approval of an unnamed product or manufacturer: 1. Evidence that the proposed product does not require revisions to the Contract Documents that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work. 2. Detailed comparison of significant qualities of proposed product with those named in the Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the product specified. 3. Evidence that proposed product provides specified warranty. 4. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners, if requested. 5. Samples, if requested. CORNELL UNIVERSITY SECTION 01 25 00 Ithaca, New York SUBSTITUTIONS AND PRODUCT OPTIONS STUDENT AND CAMPUS LIFE SUBSTITUTIONS 01 25 00-8 MULTIPLE DEFICIENCIES AND PRODUCT OPTIONS March 13, 2019 CODE REMEDIATION – PHASE 1A 1.11 CONTRACTOR'S REPRESENTATION A. In making a formal request for a substitution the Contractor represents that: 1. By submitting Shop Drawings, Product Data, Samples and similar submittals, the Contractor thereby represents that he has determined and verified all dimensions, quantities, field dimensions, relations to existing work, coordination with work to be installed later, coordination with information on previous Shop Drawings, Product Data, or Samples and compliance with all the requirements of the Contract Documents. The accuracy of all such information is the responsibility of the Contractor. 2. The Contractor has personally investigated the proposed product and has determined that it is equal to or superior in all respects to that specified. 3. The Contractor will provide the same warranties or bonds for the substitution as for the product specified. 4. The Contractor will coordinate the installation of an accepted substitution into the Work, and will make such changes as may be required for the Work to be complete in all respects. 5. The Contractor waives all claims for additional costs related to the substitution which may subsequently become apparent. 1.12 ARCHITECT'S DUTIES A. Review Contractor's requests for substitutions with reasonable promptness. B. Transmit evaluations and recommendations to the Owner, so that the Owner can notify the Contractor of the decision for acceptance or rejection of the request for substitution. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 25 00*** CORNELL UNIVERSITY SECTION 01 31 19 Ithaca, New York PROJECT MEETINGS STUDENT AND CAMPUS LIFE PROJECT MEETINGS 01 31 19-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 31 19 PROJECT MEETINGS 1.0 GENERAL 1.1 DESCRIPTION A. The Owner will schedule and administer pre-construction meeting, periodic progress meetings, and specially called meetings throughout the progress of the work. 1. Prepare agenda for meetings. 2. Distribute written notice of each meeting four days in advance of meeting date. 3. Make physical arrangements for meetings. 4. Preside at meetings. 5. Record the minutes; include all significant proceedings and decisions. 6. Duplicate and distribute copies of minutes after each meeting. a. To all participants in the meeting. b. To all parties affected by decisions made at the meeting. c. To the Architect. B. Representatives of Contractor, subcontractors and suppliers attending the meetings shall be qualified and authorized to act on behalf of the entity each represents. 1.2 PRE-CONSTRUCTION MEETING A. Schedule at least fifteen (15) days after date of Notice to Proceed. B. Location: A central site, convenient for all parties. C. Attendance: 1. Owner's Representative(s) 2. Contractor(s) 3. Architect and its professional consultants 4. Major Subcontractors 5. Major suppliers 6. Safety Representatives for the Owner and Contractor CORNELL UNIVERSITY SECTION 01 31 19 Ithaca, New York PROJECT MEETINGS STUDENT AND CAMPUS LIFE PROJECT MEETINGS 01 31 19-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 7. Commissioning Agent D. Minimum Agendum: 1. Distribution and discussion of: a. List of major subcontractors and suppliers b. Projected Construction Schedules 2. Critical work sequencing a. Identification of major shut downs and approximate schedule 3. Major equipment deliveries and priorities 4. Project Coordination a. Designation of responsible personnel 5. Procedures and processing of: a. Field decisions b. Proposal requests c. Submittals d. Change Orders e. Applications for Payment f. Requests for Information g. Daily Reports 6. Adequacy of distribution of Contract Documents 7. Procedures for maintaining Record Documents 8. Use of premises: a. Office, work and storage areas b. Owner's requirements c. Job site personnel conduct d. Building access and security 9. Temporary facilities, controls and construction aids a. Storm Water Pollution Prevention Plan (SWPPP) CORNELL UNIVERSITY SECTION 01 31 19 Ithaca, New York PROJECT MEETINGS STUDENT AND CAMPUS LIFE PROJECT MEETINGS 01 31 19-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 10. Temporary utilities 11. Safety and first-aid procedures a. Contractor’s Project Site Specific Plan 12. Security procedures 13. Housekeeping procedures 14. Affirmative Action Plan and Reporting requirements 1.3 PROGRESS MEETINGS A. Schedule regular periodic meetings on the site, not less than once every two weeks throughout the Construction period. B. Attendance: 1. Architect 2. Architect's professional consultants when, in the opinion of the Owner, needed 3. General Contractor, including Site Superintendent 4. Owner's Representatives 5. Commissioning Agent, as appropriate to agenda 6. Subcontractors as appropriate to the agenda 7. Suppliers as appropriate to the agenda 8. Safety Representative C. Minimum Agenda: 1. Review, approval of minutes of previous meeting 2. Review percentage of work to be in place by next meeting by individual trades 3. Review of work progress since previous meeting 4. Field observations, problems, and conflicts 5. Problems which impede Construction Schedule 6. Review of off-site fabrication, delivery schedules 7. Corrective measures and procedures to regain projected schedule 8. Revisions to Construction Schedule CORNELL UNIVERSITY SECTION 01 31 19 Ithaca, New York PROJECT MEETINGS STUDENT AND CAMPUS LIFE PROJECT MEETINGS 01 31 19-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 9. Planned progress and schedule, during succeeding work period 10. Coordination of schedules 11. Review submittal schedules; expedite as required 12. Maintenance of quality standards 13. Building Commissioning 14. Review status of all issued proposal requests and change orders 15. Review proposed changes for: a. Effect on Construction Schedule and on completion date b. Effect on other contracts of the Project 16. Other business D. All decisions, instructions, and interpretations given by the Architect/Engineer or its representative at these meetings shall be binding and conclusive on the Contractor. 1.4 LEED MEETINGS A. Owner will schedule an initial LEED coordination conference within twenty-one (21) days after date of Notice to Proceed, and Owner will schedule periodic LEED meetings on the site at not less than intervals required for LEED compliance. 1. Attendance: a. Architect b. Architect's professional consultants when, in the opinion of the Owner, needed c. General Contractor, including Site Superintendent d. Owner's Representatives, including Owner’s LEED Project Coordinator, and Owner’s Commissioning Agent. e. Subcontractors as appropriate to the agenda f. Suppliers as appropriate to the agenda 2. Minimum Agenda: a. Review, approval of minutes of previous LEED meetings b. LEED Project Checklist c. General requirements for LEED-related procurement and documentation CORNELL UNIVERSITY SECTION 01 31 19 Ithaca, New York PROJECT MEETINGS STUDENT AND CAMPUS LIFE PROJECT MEETINGS 01 31 19-5 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A d. Project closeout requirements and LEED certification procedures e. Roles of Contractor’s LEED Coordinator and Owner’s LEED Project Coordinator f. Construction waste management g. Construction operations and LEED requirements and restrictions h. Other business of significance that affects Owner’s sustainable design goals and that could affect meeting requirements for LEED certification B. All decisions, instructions, and interpretations given by the Owner’s LEED Project Coordinator or its representative at these meetings shall be binding and conclusive on the Contractor. 1.5 PRE-INSTALLATION CONFERENCE(S) A. The Contractor to hold pre-installation conferences where required by individual specification sections or others at the discretion of the Owner. Minimum attendees would be Architect and/or their specific sub-consultant, Owner, Contractor, Subcontractor, key Suppliers, testing & inspection firm, Facilities Engineering subject matter expert, etc. Minimum agenda would include review of key submittals, RFI’s, safety, logistics, material procurement, quality control, etc. Contractor to assemble and distribute the Agenda minimum 48 hours prior to meeting as well as distribute meeting minutes a minimum of seven (7) calendar days after the meeting. B. Submit a list of pre-installation meetings with preliminary dates within fifteen (15) days of issuance of the Notice to Proceed. 1.6 COMMISSIONING MEETINGS A. The Commissioning (Cx) Agent will schedule and conduct Cx coordination meetings as noted below. 1. Kick-off Meeting near the beginning of construction 2. TAB/ATC coordination meeting prior to commencement of TAB services 3. Routine commissioning meetings during the Acceptance Phase on a not less than bi- weekly basis. B. Attendance: 1. Architect's professional consultants when, in the opinion of the Owner, needed 2. General Contractor, including Site Superintendent 3. Owner's Representative 4. Commissioning Agent CORNELL UNIVERSITY SECTION 01 31 19 Ithaca, New York PROJECT MEETINGS STUDENT AND CAMPUS LIFE PROJECT MEETINGS 01 31 19-6 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 5. Subcontractors involved in the Cx process a. Mechanical Contractor b. Electrical Contractor c. ATC Contractor d. TAB Contractor e. Fire Alarm Contractor f. Suppliers as appropriate to the agenda C. Minimum A genda: 1. Review, approval of minutes of previous Commissioning Meetings 2. Schedule update 3. Action items 4. Update Cx Record 5. New Issues 6. Coordination and look ahead until next meeting 7. Other business of significance that affects commissioning goals D. All decisions, instructions, and interpretations given by the Owner’s Commissioning Agent or its representative at these meetings shall be binding and conclusive on the Contractor. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ****END OF SECTION 01 31 19*** CORNELL UNIVERSITY SECTION 01 31 50 Ithaca, New York ELECTRONIC PROJECT MANAGEMENT STUDENT AND CAMPUS LIFE ELECTRONIC 01 31 50-1 MULTIPLE DEFICIENCIES PROJECT MANAGEMENT March 13, 2019 CODE REMEDIATION – PHASE 1A (ePM) SYSTEM SECTION 01 31 50 ELECTRONIC PROJECT MANAGEMENT 1.0 GENERAL 1.1 SUMMARY D. Owner Provided System: The Contractor will utilize the Owner’s electronic Project Management (e-PM) system eBuilder on this project. 1. The Owner shall manage the day to day use of the Owner provided ePM system and organize the training, support and maintenance of the ePM Website System for the entire project team for the period of its use on the Project. E. There are no fees to utilize this system. 1.2 RELATED SECTIONS A. General Conditions Article 9 – Coordination and Cooperation. B. Section 01 33 00 – Submittal Procedures 1.3 DEFINITIONS A. ePM: defined as an internet-based information and project communication system that allows the entire project team to collaborate in a centralized and secured repository. All project-specific correspondence, workflow processes, and documentation will be stored and routed within the ePM system. 1.4 PROCEDURES A. Users will be provided a username and password. The Contractor shall log into the e-PM system to enter the Project Documentation listed in section 2.0. All correspondence should be communicated through the e-PM system. B. Training 1. The Owner will hold training sessions to familiarize team members with the system, and all Contractor staff are expected to attend one of these sessions or otherwise receive proper training on the system’s use. All cost for personnel time and travel to attend the training as needed shall be included in the Contractor’s proposal C. The Contractor shall provide on-site personnel with personal computer(s) and personal computer equipment that will allow the Contractor’s personnel to access and use the ePM Website System in a timely and efficient manner. At a minimum the Contractor is to provide the following equipment and software: CORNELL UNIVERSITY SECTION 01 31 50 Ithaca, New York ELECTRONIC PROJECT MANAGEMENT STUDENT AND CAMPUS LIFE ELECTRONIC 01 31 50-2 MULTIPLE DEFICIENCIES PROJECT MANAGEMENT March 13, 2019 CODE REMEDIATION – PHASE 1A (ePM) SYSTEM 1. Web Browser: with high-speed connection, up/down loading capability 2. Color printer and plotter capable of full-size document production 3. Scanner: capable of scanning a high volume of project documents clearly and quickly 4. Digital Camera: (1) single lens reflex (SLR) type camera 5. Portable Document Format (PDF) Reader/writer software D. Contractor shall log on to the ePM Website System on a daily basis, and as necessary to be kept fully appraised of the project developments, correspondence, assigned tasks and other matters that occur on the site. These may include but are not limited to RFI’s, action items, meeting minutes, discussion threads, schedule updates, submittals, submittal log, punch list items, daily reports, site photos and/or videos and pre- construction surveys. 1.5 PROCESS OVERVIEW A. The Contractor is required to timely and accurately post, review, respond, and collaborate with other team members using the following features and/or workflow processes within the ePM system. B. Project Team Directory – Contractor shall provide an updated directory of contact information for all companies, subcontractors and project team members who are engaged on this project. C. Request for Information (RFI): All project RFI’s will be submitted using the ePM Website System. The submission of a Request for Information (RFI) is the Contractor’s exclusive means of requesting information from the Owner and/or Architect. Attachments to RFI’s (which may include sketches, photographs, documentation, and the like, will be uploaded to the ePM Website System and attached to the RFI electronically. D. Meeting Minutes: Contractor shall enter meeting agendas, records and minutes in the system for all applicable meetings as designated by the Owner. E. General Communications, memorandums and Letters (Project Correspondence): Shall be created in or posted to the ePM Website System in PDF format electronically linked to action items. These action items shall include names of party (ies) required to respond, time frame within which action is to be taken and any solutions the Contractor recommends. F. Drawings and Specifications: The Contract Documents will be posted to the ePM Website System as directed by the Owner. The Owner shall retain the right to assign download rights to active CAD or model files. CAD or model files, in any format, posted to the ePM Website System are for viewing and printing only and cannot be edited. G. Submittals: All submittals shall be fully electronic. Reference Section 01 33 00. CORNELL UNIVERSITY SECTION 01 31 50 Ithaca, New York ELECTRONIC PROJECT MANAGEMENT STUDENT AND CAMPUS LIFE ELECTRONIC 01 31 50-3 MULTIPLE DEFICIENCIES PROJECT MANAGEMENT March 13, 2019 CODE REMEDIATION – PHASE 1A (ePM) SYSTEM H. Submittal Schedule and Log: Contractor shall post and/or update on a daily basis. CORNELL UNIVERSITY SECTION 01 31 50 Ithaca, New York ELECTRONIC PROJECT MANAGEMENT STUDENT AND CAMPUS LIFE ELECTRONIC 01 31 50-4 MULTIPLE DEFICIENCIES PROJECT MANAGEMENT March 13, 2019 CODE REMEDIATION – PHASE 1A (ePM) SYSTEM I. Field Reporting: The Contractor shall post and/or update on a daily basis all reports required by other specification sections. These reports include, but are not limited to, daily construction reports, material location reports, unusual event reports, safety and accident reports. J. Project Photographs: Contractor shall upload project photographs to the ePM system, field by date and type including but not limited to: 1. General Progress Photographs 2. RFI Issues 3. Non-Conforming Work 4. Special Events 5. As required by individual Specification Sections K. Project Schedule: The contractor shall post, distribute, review, and/or respond to the project schedule, monthly updates, and any other schedule submittals onto the ePM in both native and PDF formats. L. Permits & Approvals: Contractor shall upload and maintain current copies of all permits and agency approvals that relate to the project. M. Issue Tracking: Contractor to log and respond to issues that are related and affect other stakeholders within the project team. N. Quality Assurance: The Owner and/or Architect will issue reports on conforming items in the ePM system. The Contractor is required to review and respond with corrective actions in the system. O. Change Management – Cost Events and Change Orders will be managed by the e-PM system and the Contractor shall be responsible for reporting potential changes and logging Requests for Change Orders in the system. The Contractor shall also upload and manage all documentation supporting Requested Change Orders. P. Pay Applications Requests (Invoices) – The Contractor shall create and submit invoices for review by the Owner. Once the invoices are agreed to by the Owner then the invoices should be submitted electronically per the instructions for the ePM system. Q. Budget and Cost Management – Contractor to provide estimates and work breakdown structure (WBS) to provide Owner with accurate budget/cost analysis. CORNELL UNIVERSITY SECTION 01 31 50 Ithaca, New York ELECTRONIC PROJECT MANAGEMENT STUDENT AND CAMPUS LIFE ELECTRONIC 01 31 50-5 MULTIPLE DEFICIENCIES PROJECT MANAGEMENT March 13, 2019 CODE REMEDIATION – PHASE 1A (ePM) SYSTEM 1.6 ADDITIONAL INFORMATION A. The Owner may change the standards for distribution and process prescribed above as required to suit the project. B. The Owner shall retain ownership of all data entered into either system and shall administrate and distribute all information contained therein. C. The Contractor shall make certain that all subcontractors performing significant work on the project shall actively participate in the e-PM system. Requirements for participation in the e-PM system shall be made part of each bid document and final contract. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ****END OF SECTION 01 31 50*** CORNELL UNIVERSITY SECTION 01 32 16 Ithaca, New York CONSTRUCTION SCHEDULE STUDENT AND CAMPUS LIFE CONSTRUCTION 01 32 16-1 MULTIPLE DEFICIENCIES SCHEDULE March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 32 16 CONSTRUCTION SCHEDULE 1.0 GENERAL 1.1 SUMMARY A. The Contractor shall, within fourteen (14) calendar days of Notice to Proceed, prepare and submit to the Owner estimated construction progress schedules for the entire Work, with sub-schedules of related activities which are essential to the progress of the Work. B. Conferences will be held with the Architect, Owner and Contractor at the start of the project to agree mutually on a progress schedule which must be diligently followed. C. Submit revised progress schedules periodically and when requested to do so by Owner. D. Submit to Owner and Architect a cash flow projection in accordance with Schedule of Values. E. Submit electronic versions of all schedules, including updates, as well as all back-up to the submitted schedules. 1.2 FORM OF SCHEDULES A. Prepare Network Analysis system, or prepare schedules in the form of a horizontal bar chart. 1. Provide separate horizontal bar for each trade or operation. 2. Horizontal time scale: Identify the first work day of each week. 3. Scale and spacing: To allow space for notations and future revisions. B. Format of listings: The chronological order of the start of each item of work. C. Identification of listings: By specification section numbers. 1.3 CONTENT OF SCHEDULES A. Construction Progress Schedule: 1. Show the complete sequence of construction by activity. 2. Show the dates for the beginning, and completion of, each major element of construction. Specifically list: CORNELL UNIVERSITY SECTION 01 32 16 Ithaca, New York CONSTRUCTION SCHEDULE STUDENT AND CAMPUS LIFE CONSTRUCTION 01 32 16-2 MULTIPLE DEFICIENCIES SCHEDULE March 13, 2019 CODE REMEDIATION – PHASE 1A a. Site clearing b. Site utilities c. Foundation work d. Structural framing e. Subcontractor work f. Equipment installations g. Finishes h. Pre-Installation meetings 3. Show projected percentages of completion for each item, as of the first day of each month. 4. Show estimated dates for the beginning and completion of work which must be completed by or coordinated with the Owner such as hazardous materials abatement, moving, training and other such items as they are identified. B. Submittals Schedule for Shop Drawings, Product Data and Samples: Confer with the Architect and agree on all elements of the Submittals Schedule. The schedule will be based on the understanding that minimum turn-around time in the Architect's office is ten (10) working days. Some submittals or groups of submittals may take longer to review. Submittals which do not conform to the agreed schedule may be subject to delays in processing. Show: 1. The dates for Contractor's submittals. 2. The dates reviewed submittals will be required from the Architect. 3. Confirmed lead time for manufacturing, production, fabrication and shipment to the project site of all materials which have an impact on the critical path of the Project's construction schedule. 1.4 PROGRESS REVISIONS A. Indicate progress of each activity to date of submission. B. Show changes occurring since previous submission of schedule: 1. Major changes in scope 2. Activities modified since previous submission 3. Revised projections of progress and completion 4. Other identifiable changes CORNELL UNIVERSITY SECTION 01 32 16 Ithaca, New York CONSTRUCTION SCHEDULE STUDENT AND CAMPUS LIFE CONSTRUCTION 01 32 16-3 MULTIPLE DEFICIENCIES SCHEDULE March 13, 2019 CODE REMEDIATION – PHASE 1A C. Provide a narrative report as needed to define: 1. Problem areas, anticipated delays, and the impact on the schedule. 2. Corrective action recommended, and its effect. 3. The effect of changes on schedules of other prime contractors. 1.5 SUBMISSIONS A. Submit initial Construction Progress Schedules within fifteen (15) calendar days after award of Contract. 1. Owner will review schedules and return review copy within ten (10) days after receipt. 2. If required, resubmit within seven (7) days after return of review copy. B. Submit progress revision schedules to accompany each application for payment. C. Submit Submittals Schedule within thirty (30) calendar days after date of commencement of work. D. Submit one reproducible transparency and one opaque reproduction. 2.0 PRODUCTS - NOT USED 3.0 EXECUTION 3.1 DISTRIBUTION A. Distribute copies of the reviewed schedules to: 1. Owner Job Site personnel 2. Subcontractors 3. Other concerned parties B. Instruct recipients to report to the Contractor, in writing, any problems anticipated by the projections of the schedule. ***END OF SECTION 01 32 16*** CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 33 00 SUBMITTAL PROCEDURES 1.0 GENERAL 1.1 DESCRIPTION A. Section includes administrative and procedural requirements for submittals, including the following: 1. Shop Drawings 2. LEED Submittals 3. Product Data 4. Samples 5. Quality Assurance and Quality Control Submittals 6. Coordination Drawings 7. Certification of Asbestos free products 8. Owner audio/visual 9. Owner furnishings and fixed equipment B. Designate in the construction schedule, and/or in a separate Submittals Schedule, the dates for submission and the dates reviewed Shop Drawings, Product Data and Samples will be needed. C. With the exception of physical samples and color charts, or as otherwise approved by the Owner, all submittals shall be electronic images in PDF format created electronically (saved with commenting allowed) which shall be submitted for review and approval via the electronic project management web site. PDFs shall be created directly from the native file format electronically. Scanning of paper to PDF shall be used minimally. Any non- electronic submittals shall be approved on a case by case basis and logged into the electronic management system as directed by a Cornell representative. 1.2 SUBMITTAL REGISTRY AND SCHEDULE A. The Architect shall provide a draft submittal registry in the template needed for eBuilder importation. It will be part of the contract documents and turned over to the Contractor in native format for their use. The Contractor shall be responsible for review and completion of the registry including addition of dates identified below and other information as deemed necessary by the Owner. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A B. The submittal registry and schedule shall list all submittals required by the specifications, listed in order by the specification section in which they are required. Coordinate the Submittal Schedule with the Contractor's Critical Path Method Construction Schedule and other related documents. C. The Submittal Registry shall include the following information: 1. Title (by Architect for Contractor review) 2. Related specification section and paragraph numbers (by Architect for Contractor review) 3. Subsection (by Architect for Contractor review) 4. Category of Submittal (Certification, Mock-Up, Operations/Maintenance Manual, Product Data, Sample, Shop Drawing, Test Report, As Built, etc.) (by Architect for Contractor review) 5. Submittal Description including description of the part of the Work covered by the submittal (by Architect for Contractor review) 6. Name of Subcontractor, if applicable (Contractor provided, optional) 7. Date due from Subcontractor (Contractor provided, optional) 8. Date due to be submitted for review (Contractor provided, required) 9. Date due for submittal review to be completed (Contractor provided, required) 10. Date for transmittal to Subcontractor (Contractor provided, optional) 11. Date for material or product delivery to project (Contractor provided, required) 12. Priority. Low, normal or high (Contractor provided, required) D. Schedule a resubmittal for each major submittal. Except where specified otherwise in the contract documents, provide review times for submittals in accordance with Submittal Procedures and Architect’s Duties below. E. Distribution: Initially submit the Submittal Schedule to the Owner for review via the electronic Project Management system. A submittal schedule compliant with the requirements of this section showing all submittals for the preliminary schedule submission duration shall be submitted with the Contractor’s preliminary schedule submittal described in Section 01 32 16. The schedule shall also enumerate all submittals to be processed after the initial preliminary schedule submission duration period, although the date for these submittals does not have to be indicated. A final baseline submittal schedule showing all submittals for the entire project shall be included in the baseline schedule submittal described in section 01 32 16. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A F. Updating: The Submittal Schedule shall be kept up-to-date by the Contractor until all submittals are approved. Failure to provide the requested information, or delay in submitting required submittals may result in the payment request being returned to the Contractor until the required schedule or submittals are received. 1.3 SHOP DRAWINGS A. Drawings shall be newly prepared information drawn accurately to scale by skilled draftsperson and presented in a clear and thorough manner. 1. Highlight, encircle, or otherwise indicate deviations from Contract Documents. 2. Do not reproduce Contract Documents or copy standard information as basis of Shop Drawings. 3. Standard information prepared without specific reference to Project is not Shop Drawing. B. Shop Drawings include fabrication and installation Drawings, setting diagrams, schedules, patterns, templates and similar Drawings. Include the following information: 1. Dimensions. 2. Identification of products and materials included by sheet and detail number. 3. Compliance with specified standards. 4. Notation of coordination requirements. 5. Notation of dimensions established by field measurements. 6. Submittal: a. For electronic transmittal, submittals shall be distributed electronically via the electronic project management system and will be reviewed and returned electronically marked with action taken. b. Maintain returned document as a “Record Document”. 1.4 PRODUCT DATA A. Product Data includes brochures, diagrams, standard schedules, performance charts, and instructions that illustrate physical size, appearance and other characteristics of materials and equipment. All submittals shall identify all products as being asbestos free, see Section 01 35 29. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A B. Collect Product Data into a single submittal for each element of construction or system. 1. Clearly mark each copy to show applicable choices and options. Failure to do so with result in rejection of the submission. 2. Show performance characteristics and capacities. 3. Show dimensions and clearances required. 4. Show wiring or piping diagrams and controls. 5. Where Product Data includes information on products that are not required, eliminate or mark through information that does not apply. 6. Supplement standard information to provide information specifically applicable to the Work. 7. Preliminary Submittal: Submit single copy of Product Data where selection of options by Architect is required. 8. Submittals: a. For electronic transmittal, submittals shall be distributed electronically via the electronic project management system and will be reviewed and returned electronically marked with action taken. b. Maintain one (1) copy as a “Record Document”. 1.5 SAMPLES A. Samples include partial sections of manufactured or fabricated components, cuts or containers of materials, color range sets, and swatches showing color, texture, and pattern. B. Office samples shall be of sufficient size and quantity to clearly illustrate: 1. Functional characteristics of the product, with integrally related parts and attachment devices. 2. Full range of color, texture and pattern. C. Field samples and mock-ups: 1. Contractor shall erect, at the Project site, at a location acceptable to the Architect. 2. Size or area: that specified in the respective specification section. 3. Fabricate each sample and mock-up complete and finished. 4. Remove mock-ups when directed by the Architect. 5. Perform necessary work to bring any area disturbed by mock-ups to the areas original condition. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-5 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A D. Submit fully fabricated Samples cured and finished as specified and physically identical with material or product proposed. 1. Mount or display Samples in manner to facilitate review of qualities indicated. 2. Identify Samples with generic description, product name, and name of manufacturer. 3. Submit Samples for review and verification of size, kind, color, pattern, and texture. 4. Where variation in color, pattern, texture, or similar characteristics is inherent in material or product represented, submit at least three (3) multiple units that show approximate limits of variations. 5. Preliminary Submittals: Submit one (1) full set of choices where Samples are submitted for Architect’s selection of color, pattern, texture, or similar characteristics from a range of standard choices. 6. Submittals: a. Submit four (4) sets for Architect’s review. Architect will return at least one (1) set marked with action taken. Maintain sets of Samples, as returned, at Project Site, for quality comparisons throughout course of construction. Additionally, for electronic transmittal, photograph sample and its label and attached to the submittal item electronically via the electronic project management. 1.6 QUALITY ASSURANCE AND QUALITY CONTROL SUBMITTALS A. Quality assurance and quality control submittals include design data, test reports, certifications, manufacturer’s instructions, and manufacturer’s field reports. B. Professional design services or certifications: Where Contract Documents require professional design services or certifications by a design professional, Contractor shall cause such services or certifications to be provided by a qualified design professional, whose registration seal shall appear on drawings, calculations, specifications, certifications, Shop Drawings, and other submittals prepared by such professional. Architect shall be entitled to rely upon adequacy, accuracy, and completeness of services, certifications, or approvals performed by such design professionals. C. Inspection and Test Reports: Requirements for submittal of inspection and test reports from independent testing agencies as specified in the Contract Documents. D. Manufacturer’s instruction: Preprinted instructions concerning proper application or installation of system or product. E. Manufacturer’s field reports: Reports documenting testing and verification by manufacturer’s field representative to verify compliance with manufacturer’s standards or instructions. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-6 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A F. Submittals: 1. For electronic transmittal, submittals shall be distributed electronically via the electronic project management system and will be reviewed and returned electronically marked with action taken. 2. Maintain one (1) additional copy as “Record Document”. 1.7 COORDINATION DRAWINGS A. The Contractor shall coordinate and manage the preparation and submittal of coordinated layouts of the mechanical, electrical and fire protection systems and equipment for all areas; drawn at a scale not less than 1/4" per foot showing on both plan and elevation including but not limited to all equipment, ducts, pipe sleeves, piping including plumbing and, sprinkler system, lighting, special supports and other items contained within the space. Show mechanical and electrical services as well as architectural and structural features drawn to scale. Provide electronic record of each coordination drawing submitted in TIFF and PDF formats to the Owner. Provide coordination drawings for all corridors, laboratories, offices, mechanical rooms, boiler room, shafts, tunnels, and all congested areas. Copies of coordination drawings shall be distributed to all trades to assure a complete, coordinated installation of work within the space available. B. Submittal and review of coordination drawings will be required thirty (30) days prior to commencement of fabrication and/or installation of any work item. C. Prepare and submit coordinated layouts of the mechanical and electrical systems and equipment for all areas; drawn at a scale not less than 3/8 inch =1 foot (1:32) showing on both plan and elevation including but not limited to all equipment, ducts, pipe sleeves, piping including plumbing and, sprinkler system, lighting, special supports and other items contained within the space. Show mechanical and electrical services as well as architectural and structural features drawn to scale. Provide copies of each coordination drawing submitted. Provide coordination drawings for all spaces, including but not limited to, corridors, laboratories, offices, mechanical rooms, boiler room, shafts, tunnels, and other areas. Copies of coordination drawings shall be distributed to all trades to assure a complete, coordinated installation of work within the space available. 1. Show architectural, structural and other adjacent work requiring coordination with services. Show items, including but not limited to, access doors, ceiling grids, ceiling construction, structural decks and framing, fixtures, devices, and other adjacent work coordinated with services and architectural layouts shown on Drawings. 2. Prepare plans, sections, elevations, and details as needed to describe relationship of various systems and components. Supplement plan drawings with section drawings where required to adequately represent the Work. 3. Include room names and numbers of each space. 4. Coordinate the addition of trade-specific information to the coordination drawings by multiple entities in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-7 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 5. Contract drawings are diagrammatic. Exact location of receptacles, light fixtures, exit signs, fire alarm devices, and other devices shall be coordinated with the Architectural Drawings and shall not be scaled from locations indicated on the Mechanical and Electrical Drawings. Coordinate modifications in layout as necessary to complete the Work in accordance with the design intent. 6. Coordinate modifications in layout and components necessary to ensure maintenance accessibility and prevent conflict between each portion of the Work. 7. Maintain maximum headroom at all locations. Unless indicated otherwise, all mechanical and electrical systems and associated components are to be installed as tight to underside of structure as possible. 8. Indicate functional and spatial relationships of components of architectural, structural, mechanical, plumbing, fire protection, electrical systems, communications systems, security systems, and other portions of the Work. Drawings shall indicate dimensions, to avoid interference with existing conditions, structural frame, ceilings, partitions, services, and other portions of the Work. Where conflicts occur with placement of materials of various portions of the Work, Contractor shall be responsible to resolve conflicts and coordinate the available space to accommodate each portion of the Work. Adjustments resulting from coordination shall be initialed and dated by the entity(s) affected by the adjustments. 9. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation. 10. Show location and size of access doors and access panels required for access to concealed dampers, valves, and other controls. 11. Indicate required installation sequences. 12. Indicate dimensions, elevations, and alignments shown on the Drawings. Specifically note dimensions, elevations, and alignments that appear to be in conflict with submitted equipment and minimum clearance requirements and notify Architect. Provide alternate sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract. 13. Indicate suspended ceiling heights and show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. 14. Indicate locations of fire-rated partitions, smoke partitions, and other required barriers. 15. Plenum Space: Indicate sub-framing for support of ceiling and wall systems, mechanical and electrical equipment, toilet partitions, overhead-mounted equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components and notify Architect. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-8 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 16. Exposed Ceiling Construction: In addition to other indicated information, show fully- dimensioned locations of all items exposed at ceiling space. Indicate alignment requirements and centerline locations of light fixtures, ducts, piping, conduit, and other services. Show dashed outline locations of laboratory casework, shelving, and other items that extend 7 feet or more above the floor. 17. Mechanical and Electrical Rooms: Provide coordination drawings for mechanical and electrical rooms showing plans and elevations of mechanical, plumbing, fire- protection, fire-alarm, and electrical equipment. Indicate paths of egress from rooms. Indicate paths for equipment removal from rooms. Indicate clear areas required for access and maintenance. 18. Structural Penetrations: Indicate scheduled and requested penetrations and openings required for all disciplines. Request un-scheduled penetrations and openings where Contractor has reviewed, analyzed, and coordinated all possible routing options and structural penetrations are only feasible option to accommodate indicated ceiling heights. Refer to the drawings for general guidelines and request confirmation by Architect for structural penetrations. 19. Mechanical and Plumbing Work: Show dimensioned locations, sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, accessories, and support systems. Show locations of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment. 20. Electrical Work: Show electrical distribution, systems, equipment, and runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger. Show light fixture, exit light, emergency battery pack, smoke detector, fire alarm, and other device locations. Show panel board, switch board, switchgear, transformer, bus way, generator, and motor control center locations. Show location of pull boxes and junction boxes, dimensioned from column center lines. Show lighting control systems. Show cable tray layouts including vertical and horizontal offsets and transitions, clearances for access above and to side of cable trays, and vertical elevation of cable trays above the floor or bottom of ceiling structure. 21. Fire Suppression System: Show locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads. 22. Refer to individual Sections for additional Coordination Drawing requirements for Work in those Sections. 23. Contractor Sign-Off: Contractor and each entity performing portions of the Work shall sign and date coordination drawings. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-9 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 24. Review: Architect will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect will so inform Contractor, who shall make changes as directed and resubmit. Review of coordination drawings shall not reduce Contractor’s responsibility for final coordination of installation and maintenance clearances of systems and equipment with existing conditions and each portion of the Work. D. Submittal and review of coordination drawings will be required before work can start in any given area of the building. 1.8 CONTRACTOR RESPONSIBILITIES A. Review submittals for compliance with Contract Documents and approve submittals prior to transmitting to the Architect. B. Specifically record deviations from Contract Document requirements, including minor variations and limitation. Comply with requirements of Section 01 25 00 Substitutions and Product Options. C. Contractor’s approval of submittals shall indicate that the Contractor has determined and verified materials, field measurements and field construction criteria, and has checked and coordinated information within each submittal with requirement of the Work and Contact Documents. Field conflicts which arise from the contractor’s failure to fully review and approve submittals before ordering equipment, will result in the contractor being burdened with all costs to remediate the situation. D. Contractor shall be responsible for: 1. Compliance with the Contract Documents 2. Confirming and correlating quantities and dimensions 3. Selecting fabrication processes and techniques of construction. 4. Coordination of the work represented by each submittal with other trades. 5. Performing the work in a safe and satisfactory manner. 6. Compliance with the approved Construction Schedule. 7. All other provisions of the agreements. E. It is understood that the Architect's notation on the submittals is not to be construed as an authorization for additional work or additional cost. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-10 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A F. If any notations represent a change to the Contract Sum, submit a cost proposal for the change in accordance with procedures specified before proceeding with the work. G. It is understood that the Architect's notation on the submittal is not to be construed as approval of colors. Make all color-related submittals at one time. H. Notify the Architect by letter of any notations made by the Architect which the Contractor finds unacceptable. Resolve such issues prior to proceeding with the Work. I. Begin no fabrication of work until all specified submittal procedures have been fulfilled. J. Do not submit shop drawings, product data or samples representing work for which such submittals are not specified. The Architect shall not be responsible for consequences of inadvertent review of unspecified submittals. K. The review of shop drawings shall not relieve the Contractor of the responsibility for proper construction and the furnishing of materials and labor required even though the same may not be indicated on the review shop drawings. L. Certify that only asbestos free material is used in the execution of all work. Reference Section 01 35 39 1.9 SUBMITTAL PROCEDURES A. Coordination 1. Coordinate submittals with performance of construction activities in accordance with the Submittal Schedule approved by the Architect and Owner. 2. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals and related activities that require sequential activity. 3. Prepare and transmit each submittal in accordance with the Submittals Schedule, agreed to by all entities involved. 4. Prepare, review, approve and transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay. 5. Architect's Review: Allow ten (10) working days for Architect's initial processing of each submittal requiring the Architect’s review and response, except for longer periods required as noted below, and where processing must be delayed for coordination with subsequent submittals. The Architect will advise the Contractor promptly when it is determined that a submittal being processed must be delayed for coordination. Allow ten (10) working days for Architect's reprocessing of each submittal. Notify the Architect when processing time for a submittal is critical to the progress of the work, and the work would be expedited if its processing time could be shortened. An additional five (5) working days will be required for items specified in Divisions 2, 3, 5, 23 and 26, and for Architectural Woodwork, Hollow Metal Work and Hardware Schedules. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-11 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 6. Allow time for delivery in addition to review. 7. Allow time for reprocessing each submittal. 8. No extension of Contract Time will be authorized because of failure to prepare submittals sufficiently in advance of Work to permit processing. 9. Submittals made which do not conform to the schedule are subject to delays in processing by the Architect. 10. Refer to Section 01 32 16 Construction Schedules for requirements of the Submittals Schedule. 11. Failure of the Contractor to obtain approval of Shop Drawings shall render all work thereafter performed to be at Contractor’s sole risk, cost and expense. B. Submittal Preparation 1. Place permanent label or title block on each submittal for identification. 2. Indicate name of entity that prepared each submittal on label or title block. 3. Provide space on label or beside title block on Shop Drawings to record Contractor's stamp, initialed or signed, certifying to review of submittal, action taken, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the Work and of Contract Documents. 4. Complete all fields on submittal item details in ePM system including meaningful description. 5. Include the following information on submittal documentation: a. Drawing, detail or specification references, including section number, as appropriate to clearly identify intended use of product. b. Field dimensions, clearly identified as such. c. Relation to adjacent or critical features of the work or materials. d. Applicable standards, such as ASTM or Federal Specification numbers. e. Provide a blank space for the Architect’s stamps f. On transmittal, record relevant information including deviations from Contract Document requirements, including minor variations and limitations. 6. Identification of revisions on re-submittals, other than those noted by the Architect on previous submittals. 7. Shop drawings with the comment "by others" are not acceptable. All such work must specifically identify the related responsible subcontractor. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-12 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A C. Submittal Transmittal: 1. Transmit submittals via the electronic project management system to Architect unless otherwise noted or directed. 2. Prepare and generate transmittal in ePM system for submission of samples. Package sample and other each submittal appropriately for transmittal and handling. 1.10 RECORD SUBMITTALS A. Provide a record copy of the submittal to the Commissioning Agent in electronic format. Record copy shall be a clean copy (free of notes from the design professional) which has been updated to reflect the “as-installed” system. Provide document in PDF format. B. Record copy of the submittal must be forwarded to the Commissioning Agent within fourteen (14) calendar days of the final approved submittal. C. Provide a record copy of the submittal (electronic format) for the O&M Manual. 1.11 RESUBMISSION REQUIREMENTS A. Make any corrections or changes noted on previous submittals. B. Shop Drawings and Product Data: 1. Revise initial drawings or data, and resubmit as specified for the initial submittal. 2. Indicate any changes which have been made other than those noted by the Architect. C. Samples: Submit new samples as required for initial submittal. 1.12 ARCHITECT'S DUTIES A. Review submittals with reasonable promptness as identified in 1.8, paragraph 5 of this Section. B. Notations on the Submittal Review Stamp or eBuilder file mean the following: 1. "Approved (APP)" indicates that no deviations from the design concept have been found and Work may proceed. 2. "Approved as Noted (AAN)" indicates that deviations from the design concept which have been found are noted, and the Contractor may proceed accordingly. 3. "Revise and Resubmit (RAR)" indicates that Work covered by submittal, including purchasing, fabrication, delivery, or other activity may not proceed. Revise or prepare new submittal according to Architect’s notations; resubmit without delay. Repeat if necessary to obtain different action mark. CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-13 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 4. “Rejected (REJ)” indicates that Work covered by submittal, including purchasing, fabrication, delivery, or other activity may not proceed. Revise or prepare new submittal according to Architect’s notations; resubmit without delay. Repeat if necessary to obtain different action mark. 5. “On Hold (ONH)” is used in a very limited capacity and means that the Contractor should not take action until the reason for hold has been cleared and may be required to revise and resubmit. 6. “Not Reviewed (NRV)” is used for submittals that were submitted in error, duplicate, or other reason that does not require review by the Architect but need to be closed by the Contractor upon return to them 7. “For Record Only (FRO)”: Submittals for information or record purposes, including Quality Assurance and Quality Control Submittals, and Material Safety Data Sheets (MSDS), will not require responsive action by the Architect. a. Architect will forward informational submittals without action. b. Architect will reject and return informational submittals not in compliance with Contract Documents. C. Incomplete Submittals: Architect will return incomplete submittals without action. D. Unsolicited Submittals: Architect will return unsolicited submittals to sender without action. E. Return submittals to Contractor for distribution, or for resubmission. 1.13 DISTRIBUTION A. Distribute reviewed Shop Drawings and copies of Product Data when possible via the electronic project management system to: 1. Job site file 2. Record Documents file 3. Subcontractors 4. Installers 5. Suppliers 6. Manufacturers 7. Fabricators 8. Architect 9. Owner CORNELL UNIVERSITY SECTION 01 33 00 Ithaca, New York SUBMITTAL PROCEDURES STUDENT AND CAMPUS LIFE SUBMITTAL PROCEDURE 01 33 00-14 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A B. Do not permit use of unmarked copies or rejected copies of submittals in connection with construction at Project Site or elsewhere where Work is in progress. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 33 00*** CORNELL UNIVERSITY SECTION 01 35 29 Ithaca, New York GENERAL HEALTH & SAFETY STUDENT AND CAMPUS LIFE GENERAL HEALTH 01 35 29-1 MULTIPLE DEFICIENCIES & SAFETY March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 35 29 GENERAL HEALTH & SAFETY 1.0 GENERAL 1.1 DESCRIPTION A. This Section provides requirements for general health and safety during the project. The requirements of this Section shall apply to both Contractor and all tiers of sub-contractors involved in the project. B. In addition to the requirements of this Section, all laws and regulations by applicable local, state, and federal agencies shall apply to the work of this contract. In some cases the requirements of these Specifications may by intention exceed such legal requirements, but in no case shall this Specification be interpreted or understood to reduce or eliminate such requirements. 1.2 CONTRACTOR’S PROJECT SITE SPECIFIC PLAN A. Contractors are required to submit a Project Site Specific Plan (PSSP) for review by Cornell University representatives before commencement of work on the site. The PSSP should address site specific information, controls and or requirements as it relates to the entire scope of work for the project. All contractors shall use the Project Site Specific Plan Template below to develop their Project’s PSSP. The template may be downloaded at: https://sp.ehs.cornell.edu/osh/occupational-safety/contractor-safety/Pages/default.aspx 1. Within the PSSP Template are example(s) to use as reference. The provided examples demonstrate Cornell University’s expectations for providing detailed site specific information, controls and requirements. 2. Project Site Specific Plan’s that inadequately address site specific operations will be returned with comments for resubmission. Failure to submit a PSSP may result in delay of project and/or denial of the payment. 3. All projects must have the PSSP submitted via e-Builder for review and comment. B. PSSP submittal should be submitted a minimum of ten (10) days prior to the commencement of work on site. The Contractor may opt to submit their PSSP in phases. The Contractor must submit a phase submission plan using the PSSP Submission table included in the PSSP template for approval by Owner’s Representative with initial submission. Submit remaining phases no later than ten (10) days prior to the start of a new, predetermined project phase or milestone. 1. Projects having less than a ten (10) day turn-around shall coordinate their submittal with the Owner’s Representative, who should coordinate with Occupational Health, Safety CORNELL UNIVERSITY SECTION 01 35 29 Ithaca, New York GENERAL HEALTH & SAFETY STUDENT AND CAMPUS LIFE GENERAL HEALTH 01 35 29-2 MULTIPLE DEFICIENCIES & SAFETY March 13, 2019 CODE REMEDIATION – PHASE 1A and Injury Prevention (OHSIP), the University Fire Marshall’s Office and Contract College’s Codes Enforcement Official, if applicable. C. The Contractor is responsible for its employees and its subcontractors. Subcontractors are required to submit their PSSP to the General Contractor. The General Contractor is responsible to ensure all subcontractor(s) PSSP’s are adequate per their scope of work. D. The General Contractor is required to ensure their project’s PSSP is accurately maintained throughout the duration of the contract. Resubmission is required for any new scope elements not previously addressed by the Contractor’s original PSSP. E. Definitions: 1. Project Site Specific Plan (PSSP): A structured document that details the scope of the contract work and related site specific controls, requirements and information for University and Contractor personnel. This document is not intended to be all inclusive of all applicable local, state and federal laws and regulations for which the General Contractor and its Subcontractor(s) are expected to comply. 2. Authority Having Jurisdiction (AHJ): • The organization, office or individual responsible for approving equipment, an installation or a procedure (NYS Fire Code). • The local government, county government or state agency responsible for the administration and enforcement of an applicable regulation or law (NYS Building Code-§202.2). 3. Occupational Health, Safety and Injury Prevention (OHSIP): A division of Cornell University’s Environmental Safety and Health Department. The OHSIP division can be contacted at (607)-255-8200 or by email at askEHS@cornell.edu 4. SME: The University’s subject matter expert. 1.3 ASBESTOS A. All products provided for use in construction at Cornell University are to be free of asbestos. At Substantial Completion, prior to beneficial service, the Contractor shall provide a signed certification form “Exhibit AC” stating that all Contractor supplied & installed products are 100% asbestos free. The Contractor has to attach applicable Safety Data Sheets/ Material Safety Data Sheets for each product documenting a 100% asbestos free status. The University may provide random testing of products for asbestos content. Any Contractor installed product found to contain asbestos shall be classified as defective work. Defective work shall be corrected by the Contractor as specified in the General Conditions. B. Attached for the Contractor’s information are asbestos reports which represent samples taken within the building. C. Based on the above, disposal of asbestos containing material is not anticipated. CORNELL UNIVERSITY SECTION 01 35 29 Ithaca, New York GENERAL HEALTH & SAFETY STUDENT AND CAMPUS LIFE GENERAL HEALTH 01 35 29-3 MULTIPLE DEFICIENCIES & SAFETY March 13, 2019 CODE REMEDIATION – PHASE 1A 1.4 LEAD A. Building may contain lead based paint. The Contractor shall protect workers in accordance with OSHA regulations. The Contractor selects the means and/or methods to address the presence of lead based paint, and must concurrently protect its workers based on the Contractor’s means and/or methods. The Contractor is required to submit a lead plan that is site specific, indicating that the protective measures the Contractor proposes meet the OSHA standard 1926.62 “Lead in Construction Standards”. This site specific plan should address the particular methods the Contractor intends to protect its workers, the building occupants and the building structure based on its selection of addressing the presence of lead based paint. 1.5 PROTECTION FROM FIRE A. General: Follow fire-prevention plan and the following: 1. Comply with NFPA 241-Standard for Safeguarding Construction, Alteration, and Demolition Operations requirements unless otherwise indicated. 2. Remove and keep area free of combustibles, including rubbish, paper, waste, and chemicals, unless necessary for the immediate work. a. If combustible material cannot be removed, provide fire blankets to cover such materials. B. Heat-Generating Equipment and Combustible Materials: Comply with the following procedures while performing work with heat-generating equipment or combustible materials, including welding, torch-cutting, soldering, brazing, removing paint with heat, or other operations where open flames or implements using high heat or combustible solvents and chemicals are anticipated: 1. All shutdowns to be scheduled a minimum of seven (7) calendar days in advance and requests shall be submitted via ePM system to the Owner’s Representative. It is anticipated that each stairwell requiring cutting and welding of existing and new metal railings will require a shutdown of smoke alarms. The shutdown, restart, and testing will be performed by Cornell University staff. 2. Do not perform work with heat-generating equipment in or near rooms or in areas where flammable liquids or explosive vapors are present or thought to be present. 3. Use fireproof baffles to prevent flames, sparks, hot gases, or other high-temperature material from reaching surrounding combustible material. 4. Prevent the spread of sparks and particles of hot metal through open windows, doors, holes, and cracks in floors, walls, ceilings, roofs, and other openings. Close and seal all doors leading into a stairwell at all levels while welding, cutting, or any procedure producing fumes, smoke, or dust. C. Fire-Control Devices: Provide and maintain fire extinguishers, fire blankets, and rag buckets for disposal of rags with combustible liquids. Maintain each as suitable for the type of fire risk in each work area. Ensure that nearby personnel are trained in fire-extinguisher and blanket use. D. Sprinklers: Where sprinkler protection exists and is functional, maintain it without interruption while operations are being performed. If operations are performed close to sprinklers, shield them temporarily with guards. 1. Remove temporary guards at the end of work shifts, whenever operations are paused, and when nearby work is complete. CORNELL UNIVERSITY SECTION 01 35 29 Ithaca, New York GENERAL HEALTH & SAFETY STUDENT AND CAMPUS LIFE GENERAL HEALTH 01 35 29-4 MULTIPLE DEFICIENCIES & SAFETY March 13, 2019 CODE REMEDIATION – PHASE 1A 1.6 PROTECTION FROM FUMES AND SMOKE A. Provide portable welding fume extractor during welding, soldering, brazing, or metal cutting procedures. a. Acceptable Manufacturer and Product; i. Sentry Air System Inc. – 400 Series Standard Flow B. Provide temporary power as specified in Section 01 14 00. a. Portable welding fume extractors shall be compatible with 115V/1PH/60Hz power feed. C. Filter Efficiencies: a. HEPA Filter - Up to 99.97% efficient on particles down to 0.3 microns. b. ASHRAE Filter - Up to 95% efficient on particles down to 0.5 microns. D. Sound Level: 60 dba at 3 ft. 1.7 SITE VISITS A. The undertaking of periodic Site Visits by Architects, Engineers or the Owner shall not be construed as supervision of actual construction, or make them responsible for the safety of any persons; or make them responsible for means, methods, techniques, sequences or procedures of construction selected by the Contractor or its Subcontractors; or make them responsible for safety programs and precautions incident to the Work, or for the safe access, visit, use, Work, travel or occupancy of any person. 1.7 CONFINED SPACE A. The Contractor shall be responsible for the identification of confined space in accordance with OSHA requirements. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 35 29*** CORNELL UNIVERSITY SECTION 01 35 29 Ithaca, New York GENERAL HEALTH & SAFETY CORNELL UNIVERSITY SECTION 01 35 43 Ithaca, New York GENERAL ENVIRONMENTAL REQUIREMENTS STUDENT CAMPUS LIFE GENERAL ENVIRONMENTALS 01 35 43-1 MULTIPLE DEFICIENCIES REQUIREMENT March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 35 43 GENERAL ENVIRONMENTAL REQUIREMENTS 1.0 GENERAL 1.1 DESCRIPTION A. This Section and the listed Related Sections provides minimum requirements for the protection of the environment during the project. The requirements of this Section shall apply to both Contractor and all tiers of sub-contractors involved in the project. B. In addition to the requirements of this Section and the listed Related Sections, all laws and regulations by applicable local, state, and federal agencies shall apply to the work of this contract. In some cases the requirements of these Specifications may by intention exceed such legal requirements, but in no case shall this Specification be interpreted or understood to reduce or eliminate such requirements. C. Prior to bidding, review the entire Bidding Documents and report in writing to the Owner’s Representative any error, inconsistency, or omission that may have environmental impacts. 1.2 RELATED SECTIONS A. Section 01 35 44 – Spill Control 1.3 SUBMITTALS A. Submit the following in accordance with Section 01 33 00 – Submittals: 1. Analytical laboratory sample results and material Certifications for all imported soil and granular materials (“borrow”). 2. Contractor’s Waste Material Disposal Plan. 3. Weight tickets from the Borrow Material Supplier. 4. Proposed methods for dewatering and construction water management. 5. Analytical laboratory sample results for all waste materials. 6. Copies of manifests for all waste materials disposed of off-site. 1.4 JOB SITE ADMINISTRATION A. In accordance with Article 2 of the General Conditions, provide a competent supervisory representative with full authority to act for the Contractor at the site. B. If at any time operations under the representative’s supervision do not comply with this Section, or the representative is otherwise unsatisfactory to the Owner, replace, if requested CORNELL UNIVERSITY SECTION 01 35 43 Ithaca, New York GENERAL ENVIRONMENTAL REQUIREMENTS STUDENT CAMPUS LIFE GENERAL ENVIRONMENTALS 01 35 43-2 MULTIPLE DEFICIENCIES REQUIREMENT March 13, 2019 CODE REMEDIATION – PHASE 1A by the Owner, said representative with another representative satisfactory to the Owner. There shall be no change in superintendent without the Owner's approval. C. Remove from the Work any employee of the Contractor or any Subcontractor when so directed by the Owner. The Owner may request the removal of any employee who does not comply with these specifications. 1.5 CLEARING, SITE PREPARATION AND SITE USE A. In accordance with Section 01 14 00, only that portion of the working area that is absolutely necessary and essential for the work shall be cleared for construction. All clearing should be approved and performed to provide minimum practical exposure of soils. B. The Contractor shall make every effort to avoid the destruction of plants, trees, shrubs and lawns outside the area of construction so as not to unduly disturb the ecological or environmental quality of the area. C. Topsoil excavated as part of the Project, which can be reused as part of the Project, shall be stockpiled for future use and temporarily stabilized to prevent erosion. 1.6 SPOIL AND BORROW A. Spoil 1. Dispose of excavated material which, in the opinion of the Owner’s Representative, is unfit to be used as backfill or embankment or which is in excess of the amount required under the Contract. 2. All spoil areas shall be graded and seeded to match the surrounding area. 3. Spoil areas shall be covered and protected from erosion into adjacent storm sewers, drainage ways, land areas, or water bodies. B. Borrow Material 1. Borrow material shall be provided from a clean source. Submittals of proposed borrow material shall be reviewed by the Owner prior to delivery on-site. Submittals shall include the quantity of materials, source location and certification by the material supplier that it is free of chemicals or other foreign matter. 1.7 NOISE AND VIBRATION A. Limit and control the nature and extent of activities at all times to minimize the effects of noise and vibrations. Take adequate measures for keeping noise levels, as produced by construction related equipment, to safe and tolerable limits as set forth by the Occupational Safety and Health Administration (OSHA), the New York State Industrial Code Guidelines and Ordinances and all City, Town and Local ordinances. Equip all construction equipment presenting a potential noise nuisance with noise-muffling devices adequate to meet these requirements CORNELL UNIVERSITY SECTION 01 35 43 Ithaca, New York GENERAL ENVIRONMENTAL REQUIREMENTS STUDENT CAMPUS LIFE GENERAL ENVIRONMENTALS 01 35 43-3 MULTIPLE DEFICIENCIES REQUIREMENT March 13, 2019 CODE REMEDIATION – PHASE 1A 1.8 DUST CONTROL A. Take adequate measures for controlling dust produced by drilling, excavation, backfilling, loading, saw cutting or other means. The use of calcium chloride or petroleum-based materials for dust control is prohibited. Dust control measures are required throughout the duration of construction. B. If, in the opinion of the Owner’s Representative, the Contractor is not adequately controlling dust, the Owner will first notify the Contractor. If the Contractor does not take adequate actions necessary, the Owner may, at the Contractor’s expense, employ alternative means to control dust. C. Erect, maintain, and remove when appropriate barriers or other devices, including mechanical ventilation systems, as required by the conditions of the work for the protection of users of the project area, the protection of the work being done, or the containment of dust and debris. All such barriers or devices shall be provided in conformance with all applicable codes, laws, and regulations including OSHA. 1.9 PROTECTION OF THE ENVIRONMENT A. Construction procedures observed by the Contractor, its subcontractors and other employees shall include protection of the environment, in accordance with all pertinent Cornell standards, policies, local laws, executive orders, ordinances, and federal and state regulations. Construction procedures that are prohibited in the undertaking of work associated with this Contract include, but are not limited to: 1. Dumping of spoil material or any liquid or solid pollutant into any storm or sanitary sewer, drainage way, stream sewer, any wetlands (as defined by federal and state regulations), any surface waters, or at unspecified locations. 2. Indiscriminate, arbitrary, or capricious operation of equipment in any stream corridors, any wetlands, or any surface waters. 3. Pumping of any silt-laden water from trenches or other excavations into any storm sewers, sanitary sewers, drainage ways, wetlands, or surface waters. 4. Damaging vegetation beyond the extent necessary for construction of the facilities. 5. Disposal of trees, brush, and other debris in any location on University property, unless such areas are specifically identified on the drawing or in the specifications or specifically approved by the Owner’s site representative. 6. Permanent or unspecified alteration of the flow line of a stream. 7. Burning trash, project debris, or waste materials. B. Take all necessary precautions to prevent silt or waste of any kind from entering any drainage or waterways or downstream properties as a result of the Work. C. Runoff of potable water used for concrete curing or concrete truck or chute cleaning operations shall not be allowed to reach the storm water system or open water due to the CORNELL UNIVERSITY SECTION 01 35 43 Ithaca, New York GENERAL ENVIRONMENTAL REQUIREMENTS STUDENT CAMPUS LIFE GENERAL ENVIRONMENTALS 01 35 43-4 MULTIPLE DEFICIENCIES REQUIREMENT March 13, 2019 CODE REMEDIATION – PHASE 1A levels of residual chlorine (New York State water quality standards, 6 NYCRR Part 703.5) and other potential contaminants. If necessary, obtain permission from the local sewer authority and collect and pump the runoff to the sanitary sewer. D. Limit the nature and extent of any activities that could result in the release or discharge of pollutants. Report any such release or discharge immediately to the Owner’s Representative and clean up spills immediately, as detailed in Section 01 35 44 – Spill Control Procedures. 1.10 TEMPORARY RE-ROUTING OF PIPING AND DUCTWORK A. Obtain approval from the Owner’s Representative prior to any temporary re-routing of piping and exhaust ductwork necessary for the completion of the Work. Submit re-routing plans to the Owner’s Representative in writing. The following shall require approval of the Owner: 1. Temporary storm, sanitary or water line connections. 2. Temporary exhaust ductwork connections where such connections may impact air emissions. B. Instruct all personnel to observe extreme caution when working in the vicinity of mechanical equipment and piping. Personnel shall not operate or tamper with any existing valves, switches, or other devices or equipment without prior approval by the Owner’s Representative. 1.11 HAZARDOUS OR TOXIC MATERIALS A. Inform officers, employees, agents, contractors, subcontractors at every tier, and any other party which may come into contact with any hazardous or toxic materials as a result of its performance hereunder of the nature of such materials, and any health and safety or environmental risks associated therewith. B. Do not use hazardous or toxic materials in a manner that will violate Cornell University Policies or any state, federal, or municipal environmental health and safety regulations. In situations where the risks are unclear consult with Environmental Health and Safety (EH&S) for guidance. C. Provide complete care and treatment for any injury sustained by any parties coming into contact with any hazardous or toxic materials as a result of Contractor’s performance or failure to perform hereunder. D. At the completion of project Contractor shall remove all unused chemical products and hazardous materials from campus. Transportation of these materials shall be in accordance with all federal, state, and local regulations. Request and receive written approval from EH&S prior to disposal of any on-site disposal. CORNELL UNIVERSITY SECTION 01 35 43 Ithaca, New York GENERAL ENVIRONMENTAL REQUIREMENTS STUDENT CAMPUS LIFE GENERAL ENVIRONMENTALS 01 35 43-5 MULTIPLE DEFICIENCIES REQUIREMENT March 13, 2019 CODE REMEDIATION – PHASE 1A 1.12 DISPOSAL OF WASTE MATERIAL AND TITLE A. Prior to start of work and first payment, Contractor shall prepare and submit “Contractor Waste Material Disposal Plan” to the Owner’s Representative. The plan shall identify the waste transportation and treatment, storage or disposal (TSD) companies which will manage all waste material and any site(s) for disposal of the waste material. Contractor must use this form to document waste disposal methods and locations. B. The “Contractor Waste Material Disposal Plan” form, together with definitions associated with the form waste descriptions. Forms may be downloaded at: https://ipp.cornell.edu/content/forms-and-templates#V-Z C. Contractor shall be responsible for the proper cleanup, containment, storage and disposal of any hazardous material/chemical spill occurring during its work. For Cornell University owned hazardous waste EH&S will oversee, approve or effect the proper disposal. Title, risk of loss, and all other incidents of ownership to the Waste Material, shall vest in Contractor at the time Contractor or any transporter acting on its behalf takes physical possession of Waste Material. Complete and maintain full records of the chain of custody and control, including certificates of disposal or destruction, of all Waste Materials loaded, transported and/or disposed of. Deliver all such records to the Owner in accordance with applicable laws and regulations and any instructions from the Owner in a timely manner and in any event prior to final payment(s) under this Contract. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 35 43*** CORNELL UNIVERSITY SECTION 01 35 44 Ithaca, New York SPILL CONTROL STUDENT AND CAMPUS LIFE SPILL CONTROL 01 35 44-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 35 44 SPILL CONTROL 1.0 GENERAL 1.1 SPILL PREVENTION A. In order to minimize the potential for discharge to the environment of oil, petroleum, or hazardous substances on site, the following requirements shall apply to all projects: 1. All oil, petroleum, or hazardous materials stored or relocated temporarily on site during the construction process shall be stored in such a manner as to provide protection from vehicular damage and to provide containment of leaks or spills. Horizontal diked oil storage tanks, temporary berms or barriers, or similar methods shall be employed as appropriate at each site. 2. Any on-site filling or dispensing activities shall occur within an area in which a temporary berm, boom, or similar containment barrier has been placed to prevent the inadvertent discharge to the environment of harmful quantities of any products. 3. All oil, petroleum, or hazardous materials stored on site shall be located in such a manner as to minimize the potential of damage from construction operations or vehicles, away from drainage ways and environmentally sensitive areas, and in accordance with all fire and safety codes. B. Remove immediately from the site any storage, dispensing, or operating equipment that is leaking oil or hazardous substances or is in anyway unsuitable for the safe storage of such materials. 1.2 SPILL CONTROL PROCEDURES All Contractor personnel working at the project site shall be knowledgeable of the potential health and safety concerns associated with petroleum and other hazardous substances that could potentially be released at the project site. Following are a list of activities that should be conducted by the Contractor in the event of an oil/petroleum spill or the release of any other hazardous substance. In the event of a large quantity spill that would require cleanup procedures that are beyond the means of the Contractor, an emergency spill cleanup contractor shall be hired by the Contractor. In the event the Contractor has the personnel necessary to clean up the spill, the following procedures shall be followed: A. Personnel discovering/responding to a spill shall: 1. Identify and locate the source of the spill. If unsafe conditions exist, leave the area, inform nearby personnel, notify the site supervisor, and initiate spill reporting (Section 1. 3). CORNELL UNIVERSITY SECTION 01 35 44 Ithaca, New York SPILL CONTROL STUDENT AND CAMPUS LIFE SPILL CONTROL 01 35 44-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 2. Limit the discharge of product, if safely possible, by: (1) diverting discharge to a containment area; (2) creating temporary dikes with soils or other available materials; and (3) utilizing sorbent materials. If secondary containment is present, verify that valves and drains are closed prior to diverting the product to this area. 3. The individual discovering a spill shall initiate containment procedures to prevent material from reaching a potential migratory route, through implementation of the following actions, or any other methods necessary. Methods employed shall not compromise worker safety. a. Stop the spill at once (if possible). b. Extinguish sources of ignition (e.g., flames, sparks, hot surfaces, cigarettes, etc.). c. Clear personnel from the spill location and rope off the area. d. Utilize available spill control equipment in an effort to ensure that fires, explosions, and releases do not occur, recur, or spread. e. Use sorbent materials to control the spill at the source. f. Construct a temporary containment dike of sorbent materials, cinder blocks, bricks, or other suitable materials to help contain the spill. g. Attempt to identify the character, exact source, amount, and area of the released materials. Identification of the spilled material should be made as soon as possible so that the appropriate cleanup procedure can be identified. h. Assess possible hazards to human health or the environment as a result of the release, fire, or explosion. i. If spill response measures involve the temporary cessation of any operations, the Contractor shall monitor the affected equipment for: (1) leaks; (2) pressure buildup; (3) gas generation; or (4) ruptures in valves, pipes, or other equipment. B. Spill Cleanup: 1. Following containment of the spill, the following spill cleanup procedures shall be initiated. a. Use proper waste containers. b. Remove bulk liquid by using vacuum, pump, sorbents, or shovel and place material in properly labeled waste container. Be sure not to collect incompatible or reactive substances in the same container. c. Cleanup materials not reclaimed on-site shall be disposed of in accordance with all applicable state and federal regulations. CORNELL UNIVERSITY SECTION 01 35 44 Ithaca, New York SPILL CONTROL STUDENT AND CAMPUS LIFE SPILL CONTROL 01 35 44-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A d. Apply sorbent materials to pick up remaining liquid after bulk liquid has been removed. The Contractor shall not walk over spilled material. Absorbed material shall be picked up with a shovel and placed in a separate waste container, and shall not be mixed with bulk liquid. e. Clean spill control equipment and containers. Replace equipment in its proper location. Restock or reorder any sorbents used to clean up the spill. f. Carefully wash spilled product from skin and clothing using soap. Change clothes, if necessary, to avoid further contact with product. g. Disposal of all spilled product shall be made off-site, and shall be arranged through the Contractor. h. A Spill Report shall be completed, including a description of the event. A sample Spill Documentation Form is provided in Appendix B. C. Fire or Explosion: 1. In the event of a fire or explosion at the site, the Contractor shall: a. Verify that the local fire department and the appropriate response personnel (e.g., ambulance, police) have been notified. b. Report to the scene, if safe to do so, and evaluate the situation (e.g., spill character, source, etc.). Coordinate, as necessary, with other appropriate site and emergency personnel. c. Ensure that people are cleared from the area. d. Ensure that fires are safely extinguished (if possible), valves closed, and other immediate actions necessary to mitigate the emergency, if safe to do so. e. Initiate responsible measures necessary to prevent subsequent fires, explosions, or releases from occurring or spreading to other areas of the site. These measures include stopping processes or operations, collecting and containing released oil, or removing and isolating containers. f. Take appropriate action to monitor for: (1) leaks; (2) pressure build-ups; (3) gas generation; or (4) ruptures in pipes, valves, or other equipment. CORNELL UNIVERSITY SECTION 01 35 44 Ithaca, New York SPILL CONTROL STUDENT AND CAMPUS LIFE SPILL CONTROL 01 35 44-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1.3 SPILL REPORTING AND DOCUMENTATION In the event of a spill CALL CORNELL POLICE AT 255-1111 who will notify the appropriate departments within the university and coordinate with the contractor for external reporting, if required. The contractor shall be responsible for the initiation of spill reporting and documentation procedures. All petroleum spills must be reported to NYSDEC Spill Hotline at 1-800- 457-7362, less than two hours following discovery. Notification must be made to Cornell Environmental Health and Safety (EH&S), 607.255.8200, within 24 hours of reporting the release. The Contractor will be expected to provide EH&S with the DEC issued spill number. Any petroleum spill must be reported to NYSDEC unless ALL of the following criteria apply: TABLE 1 CRITERIA TO EXEMPT SPILL REPORTING CRITERIA DESCRIPTION Quantity The spill must be known to be less than 5 gallons. Containment The spill must be contained on an impervious surface or within an impervious structure, such that it cannot enter the environment. Control The spill must be under control and not reach a drain or leave the impervious surface. Cleanup The spill must be cleaned-up within two hours of occurrence. Environment The spill must not have already entered into the soil or groundwater or onto surface water. A release of a “reportable quantity”1 or unknown amount of a hazardous substance must also be immediately reported to NYSDEC Spill Hotline. Spills of reportable quantities of chemicals or “harmful quantities”2 of oil to navigable waters must be reported to the federal National Response Center, 1-800-424-8802. Spill Reporting Information: When making a telephone report, the caller should be prepared to provide the following information, if possible: 1. The date and time of the spill or release. 2. The identity or chemical name of the material released or spilled, including an indication of whether the material is defined as an extremely hazardous substance. 3. An estimate of the quantity of material released or spilled into the environment and the approximate duration of the event. 4. The exact location of the spill, including the name(s) of the waters involved or threatened, and/or other medium or media affected by the release or spill. 5. The source of the release or spill. 6. The name, address, and telephone number of the party in charge of, or responsible for, the facility or activity associated with the release or spill. CORNELL UNIVERSITY SECTION 01 35 44 Ithaca, New York SPILL CONTROL STUDENT AND CAMPUS LIFE SPILL CONTROL 01 35 44-5 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 7. The extent of the actual and potential water pollution. 8. The name and telephone number of the person in charge of operations at the spill site. 9. The steps being taken or proposed to contain and cleanup the released or spilled material and any precautions taken to minimize impacts, including evacuation. 10. The extent of injuries, if any. 11. Any known or anticipated acute or chronic health risks associated with the emergency, and information regarding necessary medical attention for exposed individuals. 12. Assistance required, if any. If the release of a hazardous substance or oil occurs in an amount which exceeds a reportable quantity (RQ) as defined in 40 CFR Part 110, 40 CFR Part 117, 40 CFR Part 302, or 6 NYCRR Part 597, then the Contractor shall do the following: 1. Call to the National Response Center shall be made by the person in charge of the site. The applicable phone numbers are 1-800-424-8802 or 1-202-426-2675. 2. Within 14 days of the release, submit a written description of the release. The description should include: (1) a description of the release, (2) the type of material released, (3) estimated amount of the spill; (4) the date of the release, (5) an explanation of why the release occurred; and (6) a description of the measures to be implemented to prevent and control future releases. (1)Reportable Quantity: A Reportable Quantity is the quantity of a hazardous substance or oil that triggers reporting requirements under the Comprehensive Emergency Response, Compensation, and Liability Act (CERCLA) (USEPA, September 1992). While the Contractor is legally responsible for knowing the risks of materials that are part of construction, members of the owner’s spill response team have access to information that may help identify these quantities with you. (2)Harmful Quantity: A Harmful Quantity of oil includes discharges that violate applicable water quality standards; cause a film, sheen, or discoloration on a water surface or adjoining shoreline; or cause a sludge or emulsion to be deposited beneath the water surface or shoreline (40 CFR 110.3). 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 35 44*** CORNELL UNIVERSITY SECTION 01 41 00 Ithaca, New York REGULATORY REQUIREMENTS STUDENT AND CAMPUS LIFE REGULATORY REQUIREMENTS 01 41 00-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 41 00 REGULATORY REQUIREMENTS 1.0 GENERAL 1.1 PERMITS AND LICENSES A. The Contractor shall obtain, maintain and pay for all permits and licenses necessary for the execution of the Work and for the use of such Work when completed. Such permits shall include but are not limited to building, electrical, plumbing, backflow prevention, dig safe, fill, street use and building demolition. 1. City of Ithaca building permit applications shall be presented for review at the regularly scheduled Owner’s meeting with the Authority Having Jurisdiction (AHJ). B. For any projects which include demolition of a structure or load-bearing elements of a structure, the Contractor is required to complete a “Notification of Demolition and Renovation” and provide this notification to the United State Environmental Protection Agency (EPA) in advance of the work as specified in 40 CFR 61.145. The Contractor shall also provide a copy of this notification to the Owner’s Representative prior to any demolition. CHOOSE ONE OPTION WITHIN PARAGRAPH “C”, DELETE THE OTHERS C. All Construction / Building / Hot Work and Occupancy permits shall be issued and maintained through the City of Ithaca at no cost to the Contractor. D. Ithaca Fire Department Permitting: 1. A permit is required from the Ithaca Fire Department to install or substantially repair a fire suppression, fire detection, or fire alarm system as such as defined under the Uniform Code of New York State. 2. If the scope of work is classified under the Existing Building Code of NYS as Alteration –Level 1; Alteration – Level 2; Alteration – Level 3; or Addition; a permit from the Ithaca Fire Department is required for all work affecting the fire suppression, fire detection, or fire alarm system for that building. A building permit is also required for this type of work. 3. Work classified as a ‘Repair’ under the Existing Building Code of NYS does not require a permit from the Ithaca Fire Department. 1.2 INSPECTIONS A. Apply for and obtain all required inspections, pay all fees and charges for same, include all service charges, pavement cuts and repairs. CORNELL UNIVERSITY SECTION 01 41 00 Ithaca, New York REGULATORY REQUIREMENTS STUDENT AND CAMPUS LIFE REGULATORY REQUIREMENTS 01 41 00-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1.3 COMPLIANCE A. The Contractor shall give all notices, pay all fees and comply with all laws, rules and regulations applicable to the Work. 1.4 OWNER’S REQUIREMENTS A. The Contractor, Subcontractors, and employees of the Contractor and Subcontractors shall comply with all regulations governing conduct, access to the premises, operation of equipment and systems, and conduct while in or near the premises and shall perform the Work in such a manner as not to unreasonably interrupt or interfere with the conduct of business of the Owner. B. Upon completion of the project, the Contractor agrees to provide the Owner with a summary of municipal permit fees paid. This shall include the name of the permits secured, the permit fees paid by the Contractor and a copy of the permit. If not permit fees were required, the Contractor shall so state, in writing, upon completion of the project. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 41 00*** CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 42 00 REFERENCES 1.0 GENERAL 1.1 INTENT OF CONTRACT DOCUMENTS A. Notes or instructions shown on any one Drawing, apply where applicable, to all other Drawings. B. All references to codes, specifications and standards referred to in the Specification Sections and on the Drawings shall mean, and are intended to be, the latest edition, amendment and/or revision of such reference standard in effect as of the date of these Contract Documents. C. Install All Work in Compliance with: 1. NYS Uniform Code a. International Building Code b. International Residential Code c. International Existing Building Code d. International Fire Code e. International Plumbing Code f. International Mechanical Code g. International Fuel Gas Code h. International Property Maintenance Code i. Uniform Code Supplement 2. NYS Energy Code a. International Energy Conservation Code b. ASHRAE 90.1 c. Energy Code Supplement 3. National Electric Code CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 4. Occupational Safety and Health Administration (OSHA). 5. Life Safety Code NFPA 101. 6. All local ordinances 7. Plans and Specifications in excess of code requirements and not contrary to same. 1.2 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and other Division 1 Specification Sections, apply to this Section. 1.3 DEFINITIONS A. “General”: Basic Contract definitions are included in the Conditions of the Contract. B. “Contract Documents”: The Contract Documents consist of the Agreement between Owner and Contractor, General Conditions, General Requirements, Drawings, Specifications, addenda issued before execution of the Agreement, other documents listed in the Agreement, and modifications issued after execution of the Agreement. C. “The Contract”: The Contract Documents form the Contract for construction and represent the entire integrated Agreement between the Owner and Contractor. D. “The Work”: The work comprises the completed construction required by the Contract Documents and includes all labor necessary to produce such construction and all materials and equipment incorporated in such construction. E. “Owner”: Cornell University a New York corporation. F. “Architect/Engineer”: The Architect or Engineer is the person lawfully licensed to practice architecture and/or engineering in the state of New York, identified as such in the Owner Contractor Agreement, and is referred to throughout the Contract Documents as if singular in number. The terms Architect and/or Engineer mean the Architect and/or his authorized representative. G. “Contractor”: The Contractor, person, firm, or corporation with whom the Construction Agreement contract is made by Owner. H. “Subcontractor”: A person, firm, or corporation, supplying labor and/or materials for work at site of the project for and under separate contract or agreement with Contractor. I. “As Approved” or “Approved”: Architect’s or Owner’s approval. J. “As Directed”: Owner’s direction or instruction. Other terms including "requested," "authorized," "selected," "required," and "permitted" have the same meaning as "directed." K. “Indicated”: Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as “indicated.” CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A L. “Regulations”: Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work. M. “Furnish”: Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations. N. "Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations. O. “Reinstall”. To place back into a former position. P. “Replace”. Provide a substitute for. Q. “Provide”: Furnish and install, complete and ready for the intended use. R. “Concealed’: Work installed in pipe shafts, chases or recesses, behind furred walls, above ceilings, either permanent or removable. S. “Exposed”: All capital Work not identified as concealed. T. “Project Site”: Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built. U. “As-Built Documents”: Drawings and other records that are maintained by the Contractor to record all conditions which exist when the building construction is completed. This includes both the elements of the project itself and existing elements that are encountered during the course of project construction. V. “Record Drawings”: Shows construction changes in the project and the final location of all services, lines, outlets, and connections including underground and concealed items. The “record” drawings shall be compiled by the Architect based on the working as-built drawings and revised in accordance with the marked up drawings submitted by the Contractor. W. “Shop Drawings”: Drawings, diagrams, illustrations, charts, brochures, and other data that are prepared by Contractor or any Subcontractor, manufacturer, supplier or distributor, for some portion of the work. X. “Samples”: Physical examples furnished to illustrate materials, equipment or workmanship, and to establish standards by which the work will be judged. Y. “General Conditions”: The standardized contractual provisions describing the responsibilities, rights and relationships of the Owner and Contractor under the construction contract. Z. “Contract Limit Lines”: A limit line or perimeter line established on the drawings or elsewhere in the contract documents defining the boundaries of the site available to the contractor for construction purposes. CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A AA. "to do", "provide", "furnish", "install", etc., in these Specifications or on Drawings are directions given to the Contractor; 1.4 OWNER AGREEMENTS A. Cornell University and the Tompkins-Cortland Counties Building Trades Council, Maintenance Division have entered into an agreement. The local unions which are members of the Tompkins-Cortland Counties Building Trades Council, Maintenance Division are as follows: Local #241 - International Brotherhood of Electrical Workers Local #267 - United Association of Plumbers and Steamfitters Local #281 - United Brotherhood of Carpenters Local #3NY - International Union of Bricklayers and Allied Craftworkers Local #178 - International Union of Painters and Allied Trades Local #112 - International Brotherhood of Sheetmetal Workers Local #785 - Laborers International Union of North America The definition of craft maintenance as applied to this agreement shall be as follows: All work associated with the demolition, repair, replacement, improvement to or construction of equipment, buildings, structures, utilities, and/or system or components thereof. Craft maintenance for trades assistants shall be limited to work assigned to individuals employed as building trade laborers and which directly assists the craft work performed by other employees covered by this agreement; the Employer is free to assign such work; provided, however, such assignment does not fall within the craft performed by other employees covered by this agreement. 1.5 INDUSTRY STANDARDS A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference. B. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated. C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents. 1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source. D. Abbreviations and Acronyms for Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the organizations responsible for the standards and regulations in the CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-5 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents. ADAAG Americans with Disabilities Act (ADA) (800) 872-2253 Architectural Barriers Act (ABA) (202) 272-0080 Accessibility Guidelines for Buildings and Facilities Available from Access Board www.access-board.gov CFR Code of Federal Regulations (866) 512-1800 Available from Government Printing Office (202) 512-1800 www.gpoaccess.gov/cfr/index.html FS Federal Specification (215) 697-6257 Available from Department of Defense Single Stock Point http://dodssp.daps.dla.mil Available from Defense Standardization Program www.dps.dla.mil Available from General Services Administration (202) 619-8925 www.gsa.gov Available from National Institute of Building Sciences (202) 289-7800 www.nibs.org UFAS Uniform Federal Accessibility Standards (800) 872-2253 Available from Access Board (202) 272-0080 www.access-board.gov 1.6 ABBREVIATIONS AND ACRONYMS A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents. AA Aluminum Association, Inc. (The) (703) 358-2960 www.aluminum.org AAADM American Association of Automatic Door Manufacturers (216) 241-7333 www.aaadm.com AABC Associated Air Balance Council (202) 737-0202 www.aabchq.com AAMA American Architectural Manufacturers Association (847) 303-5664 www.aamanet.org CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-6 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-7 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A AASHTO American Association of State Highway and (202) 624-5800 Transportation Officials www.transportation.org AATCC American Association of Textile Chemists and Colorists (The) (919) 549-8141 www.aatcc.org ABAA Air Barrier Association of America (866) 956-5888 www.airbarrier.org ABMA American Bearing Manufacturers Association (202) 367-1155 www.abma-dc.org ACI ACI International (248) 848-3700 (American Concrete Institute) www.aci-int.org ACPA American Concrete Pipe Association (972) 506-7216 www.concrete-pipe.org AEIC Association of Edison Illuminating Companies, Inc. (The) (205) 257-2530 www.aeic.org AF&PA American Forest & Paper Association (800) 878-8878 www.afandpa.org (202) 463-2700 AGA American Gas Association (202) 824-7000 www.aga.org AGC Associated General Contractors of America (The) (703) 548-3118 www.agc.org AHAM Association of Home Appliance Manufacturers (202) 872-5955 www.aham.org AI Asphalt Institute (859) 288-4960 www.asphaltinstitute.org AIA American Institute of Architects (The) (800) 242-3837 www.aia.org (202) 626-7300 AISC American Institute of Steel Construction (800) 644-2400 www.aisc.org (312) 670-2400 AISI American Iron and Steel Institute (202) 452-7100 www.steel.org AITC American Institute of Timber Construction (303) 792-9559 www.aitc-glulam.org CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-8 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A ALCA Associated Landscape Contractors of America (Now PLANET - Professional Landcare Network) ALSC American Lumber Standard Committee, Incorporated (301) 972-1700 www.alsc.org AMCA Air Movement and Control Association International, Inc. (847) 394-0150 www.amca.org ANSI American National Standards Institute (202) 293-8020 www.ansi.org AOSA Association of Official Seed Analysts, Inc. (505) 522-1437 www.aosaseed.com APA APA - The Engineered Wood Association (253) 565-6600 www.apawood.org APA Architectural Precast Association (239) 454-6989 www.archprecast.org API American Petroleum Institute (202) 682-8000 www.api.org ARI Air-Conditioning & Refrigeration Institute (703) 524-8800 www.ari.org ARMA Asphalt Roofing Manufacturers Association (202) 207-0917 www.asphaltroofing.org ASCE American Society of Civil Engineers (800) 548-2723 www.asce.org (703) 295-6300 ASHRAE American Society of Heating, Refrigerating and (800) 527-4723 Air-Conditioning Engineers (404) 636-8400 www.ashrae.org ASME ASME International (800) 843-2763 (The American Society of Mechanical Engineers International) (973) 882-1170 www.asme.org ASSE American Society of Sanitary Engineering (440) 835-3040 www.asse-plumbing.org ASTM ASTM International (610) 832-9585 (American Society for Testing and Materials International) www.astm.org AWI Architectural Woodwork Institute (800) 449-8811 www.awinet.org (703) 733-0600 CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-9 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A AWPA American Wood-Preservers' Association (334) 874-9800 www.awpa.com AWS American Welding Society (800) 443-9353 www.aws.org (305) 443-9353 AWWA American Water Works Association (800) 926-7337 www.awwa.org (303) 794-7711 BHMA Builders Hardware Manufacturers Association (212) 297-2122 www.buildershardware.com BIA Brick Industry Association (The) (703) 620-0010 www.bia.org BICSI BICSI (800) 242-7405 www.bicsi.org (813) 979-1991 BISSC Baking Industry Sanitation Standards Committee (866) 342-4772 www.bissc.org CCC Carpet Cushion Council (203) 637-1312 www.carpetcushion.org CDA Copper Development Association (800) 232-3282 www.copper.org (212) 251-7200 CGA Compressed Gas Association (703) 788-2700 www.cganet.com CIMA Cellulose Insulation Manufacturers Association (888) 881-2462 www.cellulose.org (937) 222-2462 CISCA Ceilings & Interior Systems Construction Association (630) 584-1919 www.cisca.org CISPI Cast Iron Soil Pipe Institute (423) 892-0137 www.cispi.org CLFMI Chain Link Fence Manufacturers Institute (301) 596-2583 www.chainlinkinfo.org CPA Composite Panel Association (301) 670-0604 www.pbmdf.com CPPA Corrugated Polyethylene Pipe Association (800) 510-2772 www.cppa-info.org (202) 462-9607 CRI Carpet & Rug Institute (The) (800) 882-8846 CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-10 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A www.carpet-rug.com (706) 278-3176 CRSI Concrete Reinforcing Steel Institute (847) 517-1200 www.crsi.org CSI Cast Stone Institute (770) 972-3011 www.caststone.org CSI Construction Specifications Institute (The) (800) 689-2900 www.csinet.org (703) 684-0300 CSSB Cedar Shake & Shingle Bureau (604) 820-7700 www.cedarbureau.org CTI Cooling Technology Institute (281) 583-4087 www.cti.org DHI Door and Hardware Institute (703) 222-2010 www.dhi.org EIA Electronic Industries Alliance (703) 907-7500 www.eia.org EIMA EIFS Industry Members Association (800) 294-3462 www.eima.com (770) 968-7945 EJCDC Engineers Joint Contract Documents Committee (703) 295-5000 www.ejdc.org EJMA Expansion Joint Manufacturers Association, Inc. (914) 332-0040 www.ejma.org ESD ESD Association (315) 339-6937 www.esda.org FMG FM Global (401) 275-3000 www.fmglobal.com FSA Fluid Sealing Association (610) 971-4850 www.fluidsealing.com FSC Forest Stewardship Council 49 228 367 66 0 www.fsc.org GA Gypsum Association (202) 289-5440 www.gypsum.org GANA Glass Association of North America (785) 271-0208 www.glasswebsite.com CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-11 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A GS Green Seal (202) 872-6400 www.greenseal.org GSI Geosynthetic Institute (610) 522-8440 www.geosynthetic-institute.org HI Hydraulic Institute (888) 786-7744 www.pumps.org (973) 267-9700 HI Hydronics Institute (908) 464-8200 www.gamanet.org HPVA Hardwood Plywood & Veneer Association (703) 435-2900 www.hpva.org HPW H. P. White Laboratory, Inc. (410) 838-6550 www.hpwhite.com IBR Institute of Boiler & Radiation Manufacturers ICEA Insulated Cable Engineers Association, Inc. (770) 830-0369 www.icea.net ICRI International Concrete Repair Institute, Inc. (847) 827-0830 www.icri.org IEC International Electrotechnical Commission 41 22 919 02 11 www.iec.ch IEEE Institute of Electrical and Electronics Engineers, Inc. (The) (212) 419-7900 www.ieee.org IESNA Illuminating Engineering Society of North America (212) 248-5000 www.iesna.org IEST Institute of Environmental Sciences and Technology (847) 255-1561 www.iest.org IGCC Insulating Glass Certification Council (315) 646-2234 www.igcc.org IGMA Insulating Glass Manufacturers Alliance (613) 233-1510 www.igmaonline.org ILI Indiana Limestone Institute of America, Inc. (812) 275-4426 www.iliai.com ISO International Organization for Standardization 41 22 749 01 11 www.iso.ch CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-12 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A Available from ANSI (202) 293-8020 www.ansi.org CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-13 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A ISSFA International Solid Surface Fabricators Association (877) 464-7732 www.issfa.net (702) 567-8150 ITS Intertek (800) 345-3851 www.intertek.com (713) 407-3500 ITU International Telecommunication Union 41 22 730 51 11 www.itu.int/home KCMA Kitchen Cabinet Manufacturers Association (703) 264-1690 www.kcma.org LMA Laminating Materials Association (Now part of CPA) LPI Lightning Protection Institute (800) 488-6864 www.lightning.org (804) 314-8955 MBMA Metal Building Manufacturers Association (216) 241-7333 www.mbma.com MFMA Maple Flooring Manufacturers Association, Inc. (847) 480-9138 www.maplefloor.org MFMA Metal Framing Manufacturers Association (312) 644-6610 www.metalframingmfg.org MHIA Material Handling Industry of America (800) 345-1815 www.mhia.org (704) 676-1190 MIA Marble Institute of America (440) 250-9222 www.marble-institute.com MPI Master Painters Institute (888) 674-8937 www.paintinfo.com MSS Manufacturers Standardization Society of The Valve and (703) 281-6613 Fittings Industry Inc. www.mss-hq.com NAAMM National Association of Architectural Metal Manufacturers (312) 332-0405 www.naamm.org NACE NACE International (800) 797-6623 (National Association of Corrosion Engineers International) (281) 228-6200 www.nace.org NADCA National Air Duct Cleaners Association (202) 737-2926 www.nadca.com CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-14 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A NAIMA North American Insulation Manufacturers Association (703) 684-0084 www.naima.org NBGQA National Building Granite Quarries Association, Inc. (800) 557-2848 www.nbgqa.com NCAA National Collegiate Athletic Association (The) (317) 917-6222 www.ncaa.org NCMA National Concrete Masonry Association (703) 713-1900 www.ncma.org NCPI National Clay Pipe Institute (262) 248-9094 www.ncpi.org NCTA National Cable & Telecommunications Association (202) 775-3550 www.ncta.com NEBB National Environmental Balancing Bureau (301) 977-3698 www.nebb.org NECA National Electrical Contractors Association (301) 657-3110 www.necanet.org NeLMA Northeastern Lumber Manufacturers' Association (207) 829-6901 www.nelma.org NEMA National Electrical Manufacturers Association (703) 841-3200 www.nema.org NETA International Electrical Testing Association (888) 300-6382 www.netaworld.org (303) 697-8441 NFHS National Federation of State High School Associations (317) 972-6900 www.nfhs.org NFPA NFPA (800) 344-3555 (National Fire Protection Association) (617) 770-3000 www.nfpa.org NFRC National Fenestration Rating Council (301) 589-1776 www.nfrc.org NGA National Glass Association (866) 342-5642 www.glass.org (703) 442-4890 NHLA National Hardwood Lumber Association (800) 933-0318 www.natlhardwood.org (901) 377-1818 NLGA National Lumber Grades Authority (604) 524-2393 CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-15 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A www.nlga.org NOFMA NOFMA: The Wood Flooring Manufacturers Association (901) 526-5016 www.nofma.org NRCA National Roofing Contractors Association (800) 323-9545 www.nrca.net (847) 299-9070 NRMCA National Ready Mixed Concrete Association (888) 846-7622 www.nrmca.org (301) 587-1400 NSF NSF International (800) 673-6275 (National Sanitation Foundation International) (734) 769-8010 www.nsf.org NSSGA National Stone, Sand & Gravel Association (800) 342-1415 www.nssga.org (703) 525-8788 NTMA National Terrazzo & Mosaic Association, Inc. (The) (800) 323-9736 www.ntma.com (540) 751-0930 NYBFU New York Board of Fire Underwriters (212) 227-3700 www.nybfu.org PCI Precast/Prestressed Concrete Institute (312) 786-0300 www.pci.org PDCA Painting & Decorating Contractors of America (800) 332-7322 www.pdca.com (314) 514-7322 PDI Plumbing & Drainage Institute (800) 589-8956 www.pdionline.org (978) 557-0720 PGI PVC Geomembrane Institute (217) 333-3929 http://pgi-tp.ce.uiuc.edu PLANET Professional Landcare Network (800) 395-2522 www.landcarenetwork.org PTI Post-Tensioning Institute (602) 870-7540 www.post-tensioning.org RCSC Research Council on Structural Connections (800) 644-2400 www.boltcouncil.org (312) 670-2400 RFCI Resilient Floor Covering Institute (301) 340-8580 www.rfci.com RIS Redwood Inspection Service (888) 225-7339 www.calredwood.org (415) 382-0662 CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-16 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-17 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SAE SAE International (877) 606-7323 www.sae.org (724) 776-4841 SBI Steel Boiler Institute SDI Steel Deck Institute (847) 458-4647 www.sdi.org SDI Steel Door Institute (440) 899-0010 www.steeldoor.org SEFA Scientific Equipment and Furniture Association (516) 294-5424 www.sefalabs.com SGCC Safety Glazing Certification Council (315) 646-2234 www.sgcc.org SIA Security Industry Association (703) 683-2075 www.siaonline.org SJI Steel Joist Institute (843) 626-1995 www.steeljoist.org SMA Screen Manufacturers Association (561) 533-0991 www.smacentral.org SMACNA Sheet Metal and Air Conditioning Contractors' (703) 803-2980 National Association www.smacna.org SMPTE Society of Motion Picture and Television Engineers (914) 761-1100 www.smpte.org SPFA Spray Polyurethane Foam Alliance (800) 523-6154 www.sprayfoam.org SPIB Southern Pine Inspection Bureau (The) (850) 434-2611 www.spib.org SPRI Single Ply Roofing Industry (781) 647-7026 www.spri.org SSINA Specialty Steel Industry of North America (800) 982-0355 www.ssina.com (202) 342-8630 SSPC SSPC: The Society for Protective Coatings (877) 281-7772 www.sspc.org (412) 281-2331 STI Steel Tank Institute (847) 438-8265 www.steeltank.com CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-18 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SWI Steel Window Institute (216) 241-7333 www.steelwindows.com SWRI Sealant, Waterproofing, & Restoration Institute (816) 472-7974 www.swrionline.org TCA Tile Council of America, Inc. (864) 646-8453 www.tileusa.com TIA/EIA Telecommunications Industry Association/Electronic (703) 907-7700 Industries Alliance www.tiaonline.org TMS The Masonry Society (303) 939-9700 www.masonrysociety.org TPI Truss Plate Institute, Inc. (703) 683-1010 www.tpinst.org TPI Turfgrass Producers International (847) 649-5555 www.turfgrasssod.org TRI Tile Roofing Institute (312) 670-4177 www.tileroofing.org UFPO Underground Facilities Protective Organization (800) 962-7962 www.ufpo.org (800) 962-7811 UL Underwriters Laboratories Inc. (877) 854-3577 www.ul.com (847) 272-8800 UNI Uni-Bell PVC Pipe Association (972) 243-3902 www.uni-bell.org USGBC U.S. Green Building Council (202) 828-7422 www.usgbc.org WASTEC Waste Equipment Technology Association (800) 424-2869 www.wastec.org (202) 244-4700 WCSC Window Covering Safety Council (800) 506-4636 www.windowcoverings.org WDMA Window & Door Manufacturers Association (800) 223-2301 www.wdma.com WI Woodwork Institute (916) 372-9943 www.wicnet.org CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-19 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-20 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A WMMPA Wood Moulding & Millwork Producers Association (800) 550-7889 www.wmmpa.com (530) 661-9591 WSRCA Western States Roofing Contractors Association (800) 725-0333 www.wsrca.com (650) 570-5441 WWPA Western Wood Products Association (503) 224-3930 www.wwpa.org B. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents. IAPMO International Association of Plumbing and Mechanical Officials (909) 472-4100 www.iapmo.org ICC International Code Council (888) 422-7233 www.iccsafe.org (703) 931-4533 ICC-ES ICC Evaluation Service, Inc. (800) 423-6587 www.icc-es.org (562) 699-0543 NEC National Electric Code C. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents. CE Army Corps of Engineers www.usace.army.mil CPSC Consumer Product Safety Commission (800) 638-2772 www.cpsc.gov (301) 504-7923 DOC Department of Commerce (202) 482-2000 www.commerce.gov DOD Department of Defense (215) 697-6257 http://.dodssp.daps.dla.mil DOE Department of Energy (202) 586-9220 www.energy.gov EPA Environmental Protection Agency (202) 272-0167 www.epa.gov CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-21 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A FAA Federal Aviation Administration (866) 835-5322 www.faa.gov FCC Federal Communications Commission (888) 225-5322 www.fcc.gov FDA Food and Drug Administration (888) 463-6332 www.fda.gov GSA General Services Administration (800) 488-3111 www.gsa.gov HUD Department of Housing and Urban Development (202) 708-1112 www.hud.gov LBL Lawrence Berkeley National Laboratory (510) 486-4000 www.lbl.gov NCHRP National Cooperative Highway Research Program (See TRB) NIST National Institute of Standards and Technology (301) 975-6478 www.nist.gov OSHA Occupational Safety & Health Administration (800) 321-6742 www.osha.gov (202) 693-1999 PBS Public Building Service (See GSA) PHS Office of Public Health and Science (202) 690-7694 www.osophs.dhhs.gov/ophs RUS Rural Utilities Service (202) 720-9540 (See USDA) SD State Department (202) 647-4000 www.state.gov TRB Transportation Research Board (202) 334-2934 www.nas.edu/trb USDA Department of Agriculture (202) 720-2791 www.usda.gov USPS Postal Service (202) 268-2000 www.usps.com CORNELL UNIVERSITY SECTION 01 42 00 Ithaca, New York REFERENCES STUDENT AND CAMPUS LIFE REFERENCES 01 42 00-22 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 2.0 PRODUCTS - NOT USED 3.0 EXECUTION - NOT USED ***END OF SECTION 01 42 00*** CORNELL UNIVERSITY SECTION 01 45 00 Ithaca, New York QUALITY CONTROL STUDENT AND CAMPUS LIFE QUALITY CONTROL 01 45 00-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 45 00 QUALITY CONTROL 1.0 GENERAL 1.1 DESCRIPTION A. The Contractor shall provide and maintain an effective Contractor Quality Control (CQC) program and perform sufficient inspections and tests of all items of work, including those of Subcontractors, to ensure compliance with Contract Documents. Include surveillance and tests specified in the technical sections of the Specifications. Furnish appropriate facilities, instruments, and testing devices required for performance of the quality control function. Controls must be adequate to cover construction operations and be keyed to the construction sequence. Construction shall not begin until the Owner has approved the CQC program. 1.2 CONTROL OF ON-SITE CONSTRUCTION A. Include a control system for the following phases of inspection: 1. Pre-Installation Meeting. For all sections where pre-installations are defined, the Contractor shall arrange for a pre-installation meeting. When practical, pre-installation meetings shall be scheduled to take place on the same day as regularly schedule progress meetings. The Contractor shall make available, during this meeting, all approved submittals and products. a. Agenda to include the following: i. Appointment ii. Appointment of official representatives of participants in the Project. iii. Review of existing conditions and affected work, and testing thereof as required. iv. Review of installation procedures and requirements. v. Review of environmental and site condition requirements. vi. Schedule of the applicable portions of the Work. vii. Schedule of submission of samples, color chips, and items for Owners consideration. viii. Requirements for temporary facilities, site sign, offices, storage sheds, utilities, fences, Section 01500. ix. Requirements for notification for reviews. Allow a minimum of 48 hour notice to Architect for review of the Work. CORNELL UNIVERSITY SECTION 01 45 00 Ithaca, New York QUALITY CONTROL STUDENT AND CAMPUS LIFE QUALITY CONTROL 01 45 00-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A x. Requirements for inspections and tests, as applicable. Schedule and undertake inspections and tests in accordance with Section 01410. xi. Delivery schedule of specified equipment. xii. Special safety requirements and procedures. b. The following minimum personnel shall be at the meeting: i. Project Manager. ii. Project Field Supervisor iii. Subcontractor iv. Architect’s Representative v. Owner’s Representative vi. Commissioning Agent, when applicable vii. Testing Agency, when applicable 2. Preparatory Inspection. Perform this inspection prior to beginning work on any definable feature of work. Include a review of contract requirements with the supervisors directly responsible for the performance of the work; check to assure that materials, products, and equipment have been tested, submitted, and approved; check to assure that provisions have been made for required control testing; examine the work area to ascertain that preliminary work has been completed; physically examine materials and equipment to assure that they conform to shop drawings and data and that the materials and equipment are on hand. 3. Initial Inspection. Perform this inspection as soon as work commences on a representative portion of a particular feature of workmanship review control testing for compliance with contract requirements. 4. Follow-up Inspections. Perform these inspections on a regular basis to assure continuing compliance with contract requirements until completion of that particular work. 1.3 CONTROL OF OFF-SITE OPERATIONS A. Perform factory quality control inspections for items fabricated or assembled off-site as opposed to "off-the-shelf" items. The CQC Representative at the fabricating plant shall be responsible for release of the fabricated items for shipment to the job site. The CQC Representative at the job site shall receive the item and note any damage incurred during shipment. The Contractor shall be responsible for protecting and maintaining the item in good condition throughout the period of on-site and during erection or installation. Although any item found to be faulty may be rejected before its use, final acceptance of an item by the Owner is based on its satisfactory incorporation into the work and acceptance of the completed project. CORNELL UNIVERSITY SECTION 01 45 00 Ithaca, New York QUALITY CONTROL STUDENT AND CAMPUS LIFE QUALITY CONTROL 01 45 00-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1.4 TESTING A. The Owner may engage the services of an independent testing laboratory to confirm that an installed item or element of work conforms to the Specification and workmanship requirements. 1.5 OWNER'S REPRESENTATIVE A. The Owner shall designate a Representative to monitor the progress and execution of the work. The Representative shall have the authority to call for test samples, to approve or to reject work performed and to stop work in progress, if, in its opinion, the work is not in conformance with the Contract Documents. The Representative shall not be authorized to make changes or interpretations of the Contract Documents. 1. The Contractor shall maintain a project Deficiency/Issues Log in e-Builder to track non- conforming materials or sub-standard workmanship identified by Owner’s Representative. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 45 00*** CORNELL UNIVERSITY SECTION 01 66 00 Ithaca, New York STORAGE AND PROTECTION STUDENT AND CAMPUS LIFE STORAGE AND PROTECTION 01 66 00-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 66 00 STORAGE AND PROTECTION 1.0 GENERAL 1.1 DESCRIPTION A. Receive, pile, store and handle all materials, equipment and other items incorporated or to be incorporated in the Work, including items furnished by the Owner in a careful and prudent manner and shall protect them against loss or damage from every source. B. Obscure from public view, in a manner acceptable to the Owner, staging and storage areas. 1.2 TRANSPORTATION AND HANDLING A. Transport and handle products in accordance with manufacturer's instructions; using means and methods that will prevent damage, deterioration, and loss, including theft. B. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction space. C. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses. D. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installation. E. Promptly inspect shipments to assure that products comply with requirements, quantities are correct and products are undamaged. F. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement or damage. 1.3 ON-SITE STORAGE A. Materials stored on the Site shall be neatly piled and protected, and shall be stored in a neat and orderly manner in locations that shall not interfere with the progress of the Work or with the daily functioning of the Institution. B. Materials subject to weather damage shall be protected against the weather by floored weatherproof temporary storage sheds. C. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage. D. Storage piles and sheds shall be located within the area designated as the Staging Area. The Contractor shall work to insure that the condition of the staging area has no negative impact CORNELL UNIVERSITY SECTION 01 66 00 Ithaca, New York STORAGE AND PROTECTION STUDENT AND CAMPUS LIFE STORAGE AND PROTECTION 01 66 00-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A on the Campus, visually or otherwise; and that outside of that area. The Contractor has no impact at all on the Campus. E. Materials stored within the building shall be distributed in such a manner as to avoid overloading of the structural frame, and never shall be concentrated in such a manner as to exceed the equivalent of 50 pounds per square foot uniformly distributed loading. Stored materials shall be moved if they interfere with the progress of the work. F. Should it become necessary during the course of the Work to move stored materials or equipment, the Contractor, at the direction of the Owner or the Owner's Representative, shall move such materials or equipment. 1.4 PALM ROAD STORAGE A. All property including construction materials and equipment stored at the Palm Road location shall be stored at the Contractor’s sole risk. The Contractor is solely responsible for repair or replacement of property due to any cause of loss. B. The Contractor agrees to hold Cornell harmless from any accident or injury occurring at Palm Road storage site associated with the Contractor’s storage. C. The Contractor understands that Cornell makes “no” warranty regarding any security at the Palm Road site. D. The Contractor agrees that it is solely responsible for any cleanup of any site contamination caused by the Contractor’s storage or storage operations and the Contractor agrees to pay for cleanup of any contamination and restore the site back to the same condition it was found. E. It shall be assumed that the Contractor is responsible for site contamination unless the Contractor has reported condition prior to moving storage materials and equipment onto the site. Each Contractor shall be responsible for their own general area whether defined formally or not but in cases where pollutants have traveled or are found in the public areas used by all contractors, the Contractor agrees as follows: 1. If it cannot be determined who is responsible for site contamination after an investigation, all contractors who could be responsible based upon location of the incident agree to share the expense of cleanup equally. F. No storage of hazardous materials or environmental contaminants is permitted at the Palm Road site. All barrels must have labels affixed identifying contents. G. Unoccupied storage containers not within the project fence shall be labeled in the Cornell standard. Signs customized for the project shall be ordered from Ithaca Plastics, Inc., 305 West Green Street, Ithaca, New York 14850, Phone - 607.272.8232, Fax - 607.277.2579, Email – db@ithacaplastics.com. 1.5 PROTECTION A. The Contractor shall provide security personnel and adopt other security measures as may be necessary to adequately protect materials and equipment stored at the site. The Contractor CORNELL UNIVERSITY SECTION 01 66 00 Ithaca, New York STORAGE AND PROTECTION STUDENT AND CAMPUS LIFE STORAGE AND PROTECTION 01 66 00-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A shall be obligated to replace or pay for all materials and equipment including items furnished by the Owner which have been damaged or stolen prior to completion of the Work. B. Protection of Utilities 1. If during the course of the Project, it is necessary to work adjacent to existing utilities, pipelines, structures and equipment, the Contractor shall take all necessary precautions to protect existing facilities from damage. 2. Locations of utilities as shown on the Contract Documents are approximate only. The Contractor shall excavate or otherwise locate to verify existing utilities in advance of its operation. C. Protective Covering 1. All finished surfaces shall be protected by the Contractor as follows: a. Door and window sills and the jambs and soffits of openings used as passageways or through which material is handled, shall be cased and protected adequately against possible damage resulting from the conduct of the work of all trades. b. All surfaces shall be clean and not marred upon delivery of the building to the Owner. The Contractor shall, without extra compensation, replace all blocks, gypsum board, plaster, paint, tile, and all other surfaces, whether or not protected, which are damaged, and shall refinish (including painting as specified) to satisfaction of Owner. c. Tight wood sheathing shall be laid under any materials that are stored on finished concrete surfaces and planking must be laid before moving any materials over these finished areas. Wheelbarrows used over such areas shall have rubber tires on wheels. d. Contractor has the responsibility for protection of carpeting and all finish flooring during all phases of the work including after installation. e. All floors exposed to view as a floor finish shall be protected by overlaying with plywood in all areas subject to construction traffic within and without the building, special care shall be taken to protect all stair finish surfaces including but not limited to flooring, wood in-fill stairs, cabinetry, counters, equipment, etc. 1.6 PROTECTION AFTER INSTALLATION A. Protect installed products, including Owner-provided products, and control traffic in immediate area to prevent damage from subsequent operations. B. Provide protective coverings at walls, projections, corners, and jambs, sills, and soffits of openings in and adjacent to traffic areas. C. Cover walls and floors of elevator cabins, and jambs of cab doors, when elevators are used by construction personnel. CORNELL UNIVERSITY SECTION 01 66 00 Ithaca, New York STORAGE AND PROTECTION STUDENT AND CAMPUS LIFE STORAGE AND PROTECTION 01 66 00-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A D. Protect finish floors and stairs from dirt, wear, and damage: 1. Secure heavy sheet goods or similar protective materials in place, in areas subject to foot traffic. 2. Lay planking or similar rigid materials in place, in areas subject to movement of heavy objects. 3. Lay planking or similar rigid materials in place, in areas where storage of products will occur. E. Protect waterproofed and roofed surfaces: 1. Restrict use of surfaces for traffic of any kind, and for storage of products. 2. When an activity is mandatory, obtain recommendations for protection of surfaces from manufacturer. Install protection and remove on completion of activity. Restrict use of adjacent unprotected areas. F. Restrict traffic of any kind across planted lawn and landscape areas. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 66 00*** CORNELL UNIVERSITY SECTION 01 71 23 Ithaca, New York FIELD ENGINEERING STUDENT AND CAMPUS LIFE FIELD ENGINEERING 01 71 23-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 71 23 FIELD ENGINEERING 1.0 GENERAL 1.1 DESCRIPTION A. The Contractor shall provide and pay for field engineering services required for the Project. 1. Survey work required in execution of the Project. 2. Verify grades, lines, levels and dimensions shown on Drawings. 3. Lay out Work from established control points and bench marks. 4. Coordinate the Work of all trades. 5. It may be necessary at times to discontinue portions of Contractor's work in order that the Owner's Representative may check measurements or surveys without interruptions or other interferences that might impair the accuracy of the results. At any time, on request of the Owner's Representative, Contractor shall discontinue its work to such extent as may be necessary for this purpose and shall cooperate in all reasonable means to the extent of providing labor, tools, or materials to assist the Owner's Representative in making measurements and surveys. 6. Notwithstanding anything set forth above, it shall be the sole responsibility of the Contractor to complete the works within the tolerances of lines and grades as given on the drawings. No direct payment or claim for additional compensation will be allowed the Contractor for any work or delay occasioned by the Owner's Representative establishing or checking lines or grades or making other measurements, and no extension of time will be allowed for such delays. B. Owner's Representative will identify existing control points and property line corner stakes indicated on the drawings, as required. 1.2 QUALIFICATION OF SURVEYOR A. The Surveyor shall be a registered civil engineer or registered land surveyor, licensed in the state in which the Project is located and acceptable to the Owner. 1.3 SURVEY REFERENCE POINTS A. Basic horizontal and vertical control points for the Project are those designated on drawings. B. Locate and protect control points prior to occupation of the site, and preserve all reference points during construction. CORNELL UNIVERSITY SECTION 01 71 23 Ithaca, New York FIELD ENGINEERING STUDENT AND CAMPUS LIFE FIELD ENGINEERING 01 71 23-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1. Make no changes or relocations without prior written approval of the Architect and Owner. 2. Report to Owner when any reference point is lost or destroyed, or requires relocation because of necessary changes in grades or locations. 3. Require surveyor to replace reference points which may be lost or destroyed. a. Establish replacements based on original survey control. C. The Contractor shall provide and shall maintain axis lines on each floor and shall establish and shall maintain grade marks 4' 0" above the finished floor on each floor level. D. The Contractor shall furnish such stakes and other required equipment, tools and materials, and all labor as may be required in laying out any part of the Work. 1.4 PROJECT SURVEY REQUIREMENTS A. Prior to start of construction operations, review and verify figures shown on Drawings and on surveys furnished by Owner. B. Establish lines and levels, locate and lay out, by instrumentation and similar appropriate means for site improvements, stakes for grading, fill and topsoil replacement, utility slopes and invert elevations, batter boards for structures, foundations, column locations and floor levels, and controlling lines and levels required for the mechanical and electrical trades. C. From time to time, verify layouts by the same methods. 1.5 RECORDS A. Maintain a complete, accurate log of all control and survey work as it progresses. 1. Make available to Architect and Owner on request: field books, notes, logs and other data developed in performing survey and control work. 2. Maintain a record plan at field office for the information and use of all parties, recording reference points, control points and bench marks. B. On completion of foundations and major site improvements, prepare a certified survey showing all dimensions, locations, angles and elevations of construction and turn over to Owner. Submit copies of certified survey in accordance with Section 01 78 39 - Record Documents. C. When all enclosing walls are complete, certify the location and plumb of the walls. 1.6 SUBMITTALS A. Submit written qualifications of surveyor to Architect and Owner prior to starting survey work. CORNELL UNIVERSITY SECTION 01 71 23 Ithaca, New York FIELD ENGINEERING STUDENT AND CAMPUS LIFE FIELD ENGINEERING 01 71 23-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A B. Submit name and address of Professional Engineer to the Architect. C. Submit documentation to verify accuracy of field engineering work. D. Submit certificate signed by registered engineer or registered surveyor certifying that elevations and improvements are in conformance, or nonconformance, with Contract Documents. 1. Indicate on record drawings all variations from Contract Drawings. 2. Indicate horizontal locations and elevations of all existing underground utilities encountered during excavation and construction. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 71 23*** CORNELL UNIVERSITY SECTION 01 77 00 Ithaca, New York PROJECT CLOSEOUT STUDENT AND CAMPUS LIFE PROJECT CLOSEOUT 01 77 00-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 77 00 PROJECT CLOSEOUT 1.0 GENERAL 1.1 INSPECTIONS A. Substantial Completion: 1. Within a minimum of five (5) days prior to substantial completion, when the Work has reached such a point of completion that the building or buildings, equipment and apparatus can be occupied and used for the purpose intended, the Contractor shall conduct a detailed inspection of the Work to ensure that all requirements of the Contract have been met and that the Work is complete and is acceptable. Contractor shall prepare and submit a list of items to be completed and corrected (Contractor's punch list), indicating the value of each item on the list and reasons why the Work is incomplete. 2. After receipt of the Contractor’s initial punch list, the Architect will make an inspection of the Work to determine that the Work is substantially complete and that requirements of the Contract have been met and that the Work is sufficiently complete and is acceptable for use. The Architect will submit a marked-up list of items to be completed and/or corrected, inclusive of the Contractor’s punch list. The Architect shall prepare a Certificate of Substantial Completion, on the basis of an inspection, when the Architect has determined that the work is substantially complete. 3. A copy of the report of the inspection will be furnished to the Contractor as the inspection progresses so that the Contractor may proceed without delay with any part of the Work found to be incomplete or defective. 4. All work performed under a Fire Protection System Installation/Alteration Operating Permit shall be inspected by the Ithaca Fire Department, or if so delegated by the Ithaca Building Department. a. A member of the Ithaca Fire Department shall witness all acceptance or reacceptance testing of work performed under a Fire Protection System Installation Operating Permit. All testing and inspections shall be in compliance with the applicable NFPA codes as referenced by Section 906.1 of the Fire Code of NYS. b. Work classified as a ‘Repair’ under the Existing Building Code does not require the Ithaca Fire Department to witness the testing of the affected systems. Systems that have been repaired must still be tested as required by the Fire Code of NYS and NFPA. c. The Ithaca Fire Department Shall Witness the Acceptance or Reacceptance Testing for the Following Conditions: - Testing of any new installation of a fire alarm, fire suppression, or fire detection system as required by the Fire Code of New York State. CORNELL UNIVERSITY SECTION 01 77 00 Ithaca, New York PROJECT CLOSEOUT STUDENT AND CAMPUS LIFE PROJECT CLOSEOUT 01 77 00-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A - Hydrostatic testing of sprinkler system where the modification affects more than twenty (20) sprinkler heads and the modified area can be isolated from the rest of the system - Installation or replacement of a fire pump or drive elements of the fire pump. - A Fire Alarm System with added or deleted components. - A Fire Alarm System where the wiring or control circuits have been modified. - A Fire Alarm System where the control unit (Fire Alarm Panel) has been replaced or the control unit software has been replaced. - A smoke control system where the master control unit, individual fan control unit, or fan drive unit has been replaced or modified - An alternative fire suppression system that has been replaced or the actuation elements have been modified. Except: fusible link replacement. - A modification or extension of the piping fur a fire standpipe system where a hydrostatic test is required by NFPA 14. B. Final Acceptance: 1. When the items appearing on the report of inspection have been completed or corrected, the Contractor shall so advise the Architect. After receipt of this notification and Contractor’s certified list of completed items, the Owner's Representative will inform the Contractor of the date and time of final inspection. A copy of the report of the final inspection containing all remaining contract exceptions, omissions and incomplete work will be furnished to the Contractor. 2. After receipt of notification of completion and all remaining contract exceptions, omissions and incomplete work from the Contractor, the Architect will make an inspection to verify completion of the exception items appearing on the report of final inspection. 1.2 SUBMITTALS A. Contractor's List of Incomplete Items: Initial punch list submittal at Substantial Completion. 1. Organize list of spaces in sequential order, starting with exterior areas first and proceeding from lowest floor to highest floor, listing by room or space number. Organize items applying to each space by major element, including categories for individual exterior face elevations, ceilings, individual walls, floors, doors, roof levels, casework, equipment, and building systems. B. Contractor's Certified List of Completed Items: Final signed punch list submittal at Final Completion. C. Certificates of Release: Occupancy permits from authorities having jurisdiction. CORNELL UNIVERSITY SECTION 01 77 00 Ithaca, New York PROJECT CLOSEOUT STUDENT AND CAMPUS LIFE PROJECT CLOSEOUT 01 77 00-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1.3 FINAL CLEAN UP A. Upon completion of the work covered by the Contract the Contractor shall leave the completed Project ready for use and occupancy without the need of further cleaning of any kind and with all Work in new condition and in perfect order. In addition, upon completion of all Work the Contractor shall remove from the vicinity of the Work all plant, buildings, rubbish, unused materials, concrete forms and other materials belonging to him or used under its direction during construction or impairing the use or appearance of the property and shall restore such areas affected by the work to their original condition, and, in the event of its failure to do so, the same shall be removed by the Owner at the expense of the Contractor, and the Contractor and/or its surety shall be liable therefore. Final clean-up shall include but not be limited to the following: 1. All finished surfaces shall be swept, dusted, washed and polished. This includes cleaning of the Work of all finishing trades where needed, whether or not cleaning by such trades is included in their respective sections of the specifications. 2. Roofs, utility tunnels, manholes and pipe trenches and spaces between the new and existing Work shall be left thoroughly cleaned. 3. Finished flooring shall be thoroughly cleaned in accordance with the manufacturer’s recommendations. 4. Where the finish of floors has been marred or damaged in any space or area, the entire floor of that space or area shall be refinished as recommended by the manufacturers of the flooring. 5. All equipment shall be in an undamaged, bright, clean, polished and new appearing condition. 6. All new glass shall be washed and polished, both sides. The Contractor shall be responsible for all breakage of glass in the area of the Work from the commencement of its activities until the building is turned over to Owner. The Contractor shall replace all broken glass and deliver the entire building with all glazing intact and clean. 7. Provide new filters for all fan convectors after final cleaning. 8. Refer to exterior clean up. Remove paint and glazing compound from surfaces. B. Clean adjacent structures and improvements of dust, dirt, and debris caused by construction operations. Return adjacent areas to condition existing before construction operations began. CORNELL UNIVERSITY SECTION 01 77 00 Ithaca, New York PROJECT CLOSEOUT STUDENT AND CAMPUS LIFE PROJECT CLOSEOUT 01 77 00-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A MAINTENANCE STOCK A. Turn over to Owner's Representative the maintenance stock specified. Contractor shall obtain signed receipt from Owner's Representative for all maintenance stock. 1.4 ON-SITE CONSTRUCTION TRAILER REMOVAL A. Within fifteen (15) days of removal of on-site construction trailers, contact Cornell Facilities Inventory Office to notify them of removal to allow for updating of Campus Police 911 Emergency Response System. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 77 00*** CORNELL UNIVERSITY SECTION 01 78 36 Ithaca, New York WARRANTIES AND BONDS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 78 36 WARRANTIES AND BONDS 1.0 GENERAL 1.1 DESCRIPTION The Contractor shall: A. Compile specified warranties and bonds. B. Compile specified service and maintenance contracts. C. Co-execute submittals when so specified. D. Review submittals to verify compliance with Contract Documents. E. Submit to Architect for transmittal to Owner. 1.2 SUMMARY A. This Section specifies general administrative and procedural requirements for warranties and bonds required by the Contract Documents, including manufacturers standard warranties on products and special warranties. 1. Refer to the General Conditions for terms of the Contractor's special warranty of workmanship and materials. 2. General closeout requirements are included in Section 01 77 00 - "Project Closeout." 3. Specific requirements for warranties for the Work and products and installations that are specified to be warranted, are included in the individual Sections of Divisions 2 through 40. 4. Certifications and other commitments and agreements for continuing services to Owner are specified elsewhere in the Contract Documents. B. Disclaimers and Limitations: Manufacturer's disclaimers and limitations on product warranties do not relieve the Contractor of the warranty on the Work that incorporates the products, nor does it relieve suppliers, manufacturers, and subcontractors required to countersign special warranties with the Contractor. 1.3 DEFINITIONS A. Standard Product Warranties are pre-printed written warranties published by individual manufacturers for particular products and are specifically endorsed by the manufacturer to the Owner. CORNELL UNIVERSITY SECTION 01 78 36 Ithaca, New York WARRANTIES AND BONDS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A B. Special Warranties are written warranties required by or incorporated in the Contract Documents, either to extend time limits provided by standard warranties or to provide greater rights for the Owner 1.4 QUALITY ASSURANCE A. Use adequate care and diligence to review Contract Documents to identify detailed requirements relating to warranties and bonds. B. Verify that each item required for this submittal conforms with specified requirements. 1.5 WARRANTY REQUIREMENTS A. In addition to standard and special warranties described in Divisions 2 through 40, Contractor shall warrant Work included in this project, for a minimum period of one (1) year following acceptance of a Certificate of Substantial Completion by Owner, to cover performance, materials, workmanship and compliance with Contract Documents. B. Corrective Work: Provide service within thirty (30) calendar days when requested by Owner. Perform services during normal working hours, unless specifically directed otherwise by Owner. Coordinate with Owner’s representative to schedule performance of corrective work. Where designated service providers cannot perform corrective work within the Owner’s required time frame, engage another qualified service provider. Submit a written statement to Owner upon completion of corrective work; document work performed and list outstanding items, if any. 1. When a completed breakdown of a piece of equipment occurs of the malfunction of a system affects the environment or program involving 50 or more persons at a time (employees and students combined), or creates a safety or security risk to the Owner, an EMERGENCY may be declared by the Owner. The Owner may declare an emergency as defined above at which time the service response must be within 4 hours and may require action during non-normal working hours. 2. When an emergency condition occurs, the Owner may take immediate corrective action to relieve the problem by making, a minimum as possible, temporary adjustments and/or repairs when necessary to decrease the problem until the designated Contractor’s representative can respond. These temporary adjustments and repairs will in no way jeopardize the existing warranty. 3. The Owner’s service staff will advise the Contractor’s Representative of all temporary adjustments and repairs done in relation to the malfunctioning equipment or facility. 4. If the Contractor fails to respond with actual service within four (4) hours, and/or the necessary repairs or adjustments are not satisfactorily complete twenty-four (24) hours, the Owner will have the authority to make the necessary repairs or adjustments and charge the Contractor for parts and labor. 5. If all adjustments and repairs done by the Owner in relation to the above conditions are done by authorized district personnel, there will be no negative effect of future warranty claims. CORNELL UNIVERSITY SECTION 01 78 36 Ithaca, New York WARRANTIES AND BONDS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A C. Related Damages and Losses: When correcting failed or damaged warranted Work, remove and replace other Work that has been damaged as a result of such failure or that must be removed and replaced to provide access for correction of warranted Work. D. Reinstatement of Warranty: When Work covered by a warranty has failed and been corrected by replacement or rebuilding, reinstate the warranty by written endorsement. The reinstated warranty shall be equal to the original warranty with an equitable adjustment for depreciation. E. Replacement Cost: Upon determination that Work covered by a warranty has failed, replace or rebuild the Work to an acceptable condition complying with requirements of Contract Documents. The Contractor is responsible for the cost of replacing or rebuilding defective Work regardless of whether the Owner has benefited from use of the Work through a portion of its anticipated useful service life. F. Owner's Recourse: Expressed warranties made to the Owner are in addition to implied warranties, and shall not limit the duties, obligations, rights and remedies otherwise available under the law. Expressed warranty periods shall not be interpreted as limitations on time in which the Owner can enforce such other duties, obligations, rights, or remedies. G. Contractor's Procurement Obligations: Do not purchase, subcontract for, or allow others to purchase or subcontract for materials or units of Work for Project where a special project guaranty, specified product warranty, certification, or similar commitment is required until it has been determined that entities required to sign or countersign such commitments are willing to do so. H. Specific Warranty. Where a special warranty, certification, or similar commitment is required on such Work or part of the Work, the Owner reserves the right to refuse to accept the Work until the Contractor presents evidence that entities required to countersign such commitments are willing to do so. 1.6 SUBMITTAL REQUIREMENTS A. Submit written warranties to the Architect prior to the date certified for Substantial Completion. If the Architect’s Certificate of Substantial Completion designates a commencement date for warranties other than the date of Substantial Completion for the Work, or a designated portion of the Work, submit written warranties upon request of the Architect or Owner. 1. When a designated portion of the Work is completed and occupied or used by the Owner, by separate agreement with the Contractor during the construction period, submit properly executed warranties to the Architect and Owner within fifteen (15) days of completion of that designated portion of the Work. CORNELL UNIVERSITY SECTION 01 78 36 Ithaca, New York WARRANTIES AND BONDS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A B. When a special warranty is required to be executed by the Contractor, or the Contractor and a subcontractor, supplier or manufacturer, prepare a written document that contains appropriate terms and identification, ready for execution by the required parties. Submit a draft to the Owner through the Architect for acceptance prior to final execution. 1.7 SUBMITTALS REQUIRED A. Submit warranties, bonds, and service and maintenance contracts as specified in the respective sections of Specifications. Submit a schedule listing all required warranties. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION 3.1 FORM OF SUBMITTALS A. The Warranties and Bonds shall be in electronic pdf format. Each submission shall include the title of the Project and the name of the Contractor. B. Provide a series of files organized in subdirectories with a summary index with hyperlinks to the various documents and or references. C. Assemble warranties, bonds and service and maintenance contracts, executed by each of the respective manufacturers, suppliers and subcontractors. D. Table of Contents: Neatly typed, in orderly sequence. Provide complete information for each item. 1. Product or work item. 2. Item description. 3. Notation of what the equipment serves (e.g. – Provides perimeter heat) 4. Warranty Provider. Is the warranty provided by a manufacturer or installer? 5. Firm, with name of principal and responsible party, address and telephone number. 6. Scope. 7. Duration. a. Date of beginning of warranty, bond or service and maintenance contract b. End date of warranty, bond or service and maintenance contract. CORNELL UNIVERSITY SECTION 01 78 36 Ithaca, New York WARRANTIES AND BONDS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-5 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 8. Provide information for Owner's personnel: a. Proper procedure in case of failure. b. Instances which might affect the validity of warranty or bond. 9. Contractor, name of responsible principal, address and telephone number. 3.2 TIME OF SUBMITTALS A. Make final submittals within ten (10) days after Date of Substantial Completion, prior to final request for payment. B. For items of work when acceptance is delayed materially beyond the Date of Substantial Completion, provide updated submittal within ten (10) days after acceptance, listing the date of acceptance as the start of the warranty period. 3.3 ROOF WARRANTY PACKAGE A. Roof warranties shall explicitly denote the specific roof panel identification number (ROOF ID) for which the warranty applies to. B. Roof panel identification numbers shall be generated in accordance with 01 78 22, FIXED EQUIPMENT INVENTORY. C. Roof warranties shall include a dimensioned roof plan with roof panel identification numbers generated in accordance with 01 78 22, FIXED EQUIPMENT INVENTORY. ***END OF SECTION 01 78 36*** CORNELL UNIVERSITY SECTION 01 78 39 Ithaca, New York RECORD DOCUMENTS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-1 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A SECTION 01 78 39 RECORD DOCUMENTS 1.0 GENERAL 1.1 DESCRIPTION A. The Contractor shall maintain at the site, during construction, one record copy of: 1. Drawings 2. Specifications 3. Addenda 4. Change Orders and other Modifications to the Contract 5. Architect's Field Orders or written instructions. 6. Final Shop Drawings, Product Data and Samples 7. Field Test records 8. Construction photographs 1.2 MAINTENANCE OF DOCUMENTS AND SAMPLES A. Store documents and samples in Contractor's field office apart from documents used for construction. 1. Provide files and racks for storage of documents. 2. Provide cabinet or storage space for storage of samples. B. File documents and samples in accordance with Data Filing Format of the Uniform Construction Index. C. Maintain documents in a clean, dry, legible condition and in good order. Do not use record documents for construction purposes. D. Make documents and samples available at all times for review by the Owner’s Representative and the Architect. 1.3 RECORDING A. Label each document "AS BUILT" in neat large printed letters. B. Record information concurrently with construction progress. CORNELL UNIVERSITY SECTION 01 78 39 Ithaca, New York RECORD DOCUMENTS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-2 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 1. Do not conceal any work until required information is recorded. C. Survey Mapping 1. Provide an accurate topographic, planimetric, utility map of as-built conditions, and mapped locations and elevations of constructed facilities / elements including as-built and exposed underground utilities. Survey work in progress as required to accurately locate constructed facilities / elements. Survey final condition of project extents at final acceptance. a. Site related elements including: - Sidewalks, ramps, curbs, and gutters - indicate type and surface material. - Streets, drive ways, parking areas, labeled with material. - Fences, walls, steps, handrails, signs, site furniture and light fixtures labeled with material. - Live trees which have a trunk diameter of three inches (3”) or greater and all isolated or specimen trees. Measure tree trunk 3’ above grade. Indicate approximate trunk diameter, “drip line” and common name of tree. - Shrubs, show outlines of shrub masses. - Streams and bodies of water. b. Utility related elements and supporting infrastructure including: - Manholes, catch basins, drain inlets, cleanouts, vent stacks, tanks, underdrains, foundation drains, monitoring wells, detention/retention/filtration facilities. Label type (sanitary or storm), dimensions and material of structure and cover/grate; pipe connections; sizes, materials, direction of flow and invert elevations. Locate and identify size, material, and invert elevations for culverts. - Water, gas, central steam, chilled water or other pressure lines, valve boxes, meter boxes, hydrants, tanks, fittings, etc. Label type, size, material, elevations at building walls and all intersections, connections and vertical angle changes. - Utility poles, above and below ground lines including but not limited to power, street lighting, traffic control communication and sensors, telephone, television, communication, fire and police call boxes, public communication or display facilities. Label utility as direct buried, in conduit, or concrete encased duct. Identify elevations at building walls and all intersections, connections and vertical angle changes. Label all utilities and associated duct banks or conduits with sizes and materials. - Existing and abandoned utilities exposed during construction. Show ends of abandoned utilities left in place and assumed continued direction of utilities. Label with information as listed above. CORNELL UNIVERSITY SECTION 01 78 39 Ithaca, New York RECORD DOCUMENTS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-3 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A 2. Survey mapping shall be done under the personal supervision of a Surveyor, registered in and licensed by the State of New York, who shall certify under his/her seal the accuracy of the survey. 3. Field Survey Accuracy: - Horizontal and Vertical mapping shall be ACSM Second Order Class II, 1 in 20,000. 4. Coordinate base: - NAD83-86 geodetic system with grid values in the New York Central State Plane coordinate system in feet with elevations in NAVD ’88 in feet. 5. Each different feature shall be drafted on a separate named CAD level/layer in Microstation or AutoCAD format using industry standard symbology of color, line style, line weight, and cells. 6. Provide an ASCII file list of coordinates for all survey points including control, feature, and topographic in the following comma delimited format: Point number, Northing coordinate, Easting coordinate, Elevation coordinate, Point description. 7. Topography and spot elevations: a. Topographic contours shall be accurately plotted at one foot (1’) contour intervals. b. Record spot grade elevations as follows: i. Within natural ground and lawn and planted areas, spot elevations shall be shown to one-tenth of a foot (0.1’). Within all areas of built-up improvements such as pavements, curbs, steps, walls, utility and drainage systems or other site improvements, spot elevations shall be shown to one-hundredth of a foot (0.01’). ii. Existing grade at building corners; and thresholds and finished floor at all entrance, exit, or access points. iii. Develop road cross sections at 50-foot intervals maximum, record spot elevations for all drive centerlines and all beginning radius of street intersections. For each cross section obtain elevations for front and back of existing sidewalk, top and bottom of curb, and centerline of the street. Obtain elevations for centerline intersection of all roads. iv. For trees of three inches to eighteen inches (3” - 18”) in diameter, record elevation at high and low side at base of trunk. For specimen trees of eighteen inches (18”) or greater diameter, indicate four (4) spot elevations on the north, south, east, and west at base of each trunk to one-hundredth (.01) foot elevation. v. Base, top, corners, and at cheek walls for all steps. Indicate elevations at top and bottom of walls and curbs. CORNELL UNIVERSITY SECTION 01 78 39 Ithaca, New York RECORD DOCUMENTS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-4 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A vi. Rim elevations of all catch basins, drain inlets, manholes, valve boxes, slabs on grade. Inverts at all sewer pipes and culverts. Bottom of structure floor and sump. D. Drawings As built drawings shall consist of making any changes neatly and clearly on the Contract Drawings using colored ink or pencil, shall be kept current by the contractor on a day-to-day basis in concert with the progress of the work. Where applicable, the change marked on a drawing is to carry the notation “per Change Order No. X”, or similar reference which cites the reason for the change. As an alternative approach the Contractor can submit a plan for producing the “As-Built” drawings via electronic mark-up in Bluebeam, Adobe Professional, or other similar program as an alternative to colored pencil or ink mark-ups. Such plan shall be subject to approval of the Owner. The day-to-day construction as built drawings shall be made available to the Architect or Owner’s Representative for review upon request. The "As built" drawings shall show all changes to the following areas of construction: 1. Architectural: a. Modifications to components dictated by the building code b. Wall, door, window locations c. Built in casework locations d. New rated door and wall schedules/ locations e. Material and products where submittals are requested 2. Civil and Structural a. Dimensions for load carrying elements, both horizontal and vertical b. Materials and products where submittals are requested c. Load carrying elements and foundation systems d. Site related elements including: - Building outlines, entranceways, areaways, roof overhangs, downspouts, significant architectural projections and other pertinent data. e. All significant changes in foundations, columns, beams, openings, concrete reinforcing, lintels, concealed anchorages and "knock-out" panels made during construction. f. Building envelope systems including roofing systems and building shell systems g. Geotechnical subsurface information CORNELL UNIVERSITY SECTION 01 78 39 Ithaca, New York RECORD DOCUMENTS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-5 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A h. Items that will require future maintenance i. Life safety critical items 3. Mechanical (HVAC, Plumbing and Fire Protection) a. Products where submittals are requested b. Final locations of all equipment. c. Final sizes and materials of piping and ductwork. d. Final locations of inaccessible piping and ductwork. e. Final locations of all controls equipment, including all sensors and actuators. f. Final locations of all valves and dampers, including all shutoff valves, balance dampers and fire dampers. g. Location of access doors for all equipment in concealed locations. h. Final location and arrangement of all mechanical equipment and concealed gas, sprinkler, domestic, sanitary and drainage systems piping and other plumbing, including, but not limited to, supply and circulating mains, principal valves, meters, clean-outs, drains, pumps and controls, vent stacks, sanitary and storm water drainage. 4. Electrical a. Products where submittals were requested. b. Circuit (wire and raceway) size, number, and type. c. Main circuit pathways for Fire Alarm, Emergency Power, and Access Control/Security systems. d. Final locations of equipment and devices, interior and exterior luminaires, and power supplies. e. Final location of electric signal system panels, final arrangement of all circuits and any significant changes made in electrical signal system design as a result of Change Order or job conditions. 5. Environmental a. Utility related elements and supporting infrastructure b. Storm water maintenance/testing access points c. Location of unusual excavation findings / contaminated soil (i.e. mercury uncovered during excavation, also on-site spills during construction), including quantity excavated/disposed. CORNELL UNIVERSITY SECTION 01 78 39 Ithaca, New York RECORD DOCUMENTS STUDENT AND CAMPUS LIFE RECORD DOCUMENTS 01 78 39-6 MULTIPLE DEFICIENCIES March 13, 2019 CODE REMEDIATION – PHASE 1A E. Specifications and Addenda Legibly mark each section to record: 1. Manufacturer, trade name, catalog number, and Supplier of each product and item of equipment actually installed. 2. Changes made by Field Order or by Change Order. 1.4 SUBMITTAL A. At Contract close-out, deliver copies of all record documents to the Owner’s Representative. B. Accompany submittal with transmittal letter in duplicate, containing: 1. Date 2. Project title and number 3. Contractor's name and address 4. Title and number of each record document 5. Certification that each document is complete and accurate 6. Signature of Contractor or its authorized representative. 2.0 PRODUCTS – NOT USED 3.0 EXECUTION – NOT USED ***END OF SECTION 01 78 39*** TECHNICAL SPECIFICATIONS FOR STUDENT & CAMPUS LIFE MULTIPLE DEFICIENCIES CODE REMEDIATION – PHASE 1A CLARA DICKSON CORNELL UNIVERSITY ITHACA, NEW YORK ____________________________________________________________________________ IBI/114475 Section 02 82 02 – Lead-Based Paint Handling Procedures Page 1 of 7 SECTION 02 82 02 LEAD -BASED PAINT HANDLING PROCEDURES 1 PART 1 GENERAL 1.1 EXAMINATION OF SPECIFICATIONS AND SITE OF WORK A. The Contractor shall carefully examine the enclosed documents and visit the site of the work. The Contractor shall fully inform himself prior to preparation of the Bid as to all existing conditions and limitations under which the work is to be performed and shall include in the Bid a sum to cover all costs of all items neces- sary to perform the work as set forth in these documents. No allowance will be made to the Contractor because of lack of such examination or knowledge. B. The building components identified as lead-based paint are not scheduled to be removed. All contractors are advised of the presence of lead-based paint in order to provide the appropriate worker and building occupant protection specified in the plans and specifications including OSHA requirements and HUD guidelines. C. All contractors shall comply with the provisions of this section when in the course of their work lead-based paint may be disturbed. 1.2 SUBMITTALS A. The Contractor shall submit the following documents prior to award of contract: 1. A description of the proposed approach to the project. This should address methodology of lead-based paint handling procedures, proposed manpower, schedule, access, storage, security, or services and facilities to be provided by the Owner for the project. 2. Verification that the project will be completed within the specified time period. B. Additional submittals shall be required from the Contractor at the completion of the project. These are specified below in this document. 1.3 SCOPE OF WORK A. The Contractor shall furnish all components required and supply all labor, materials, tools, equipment, and insurance, necessary to properly complete the work in accordance with the Contract Documents. Building components with the possibility of (untested) as lead-based painted components (>1.0 mg/cm2) include: 1. Existing paint on metal stair railings requiring removal for welding. 2. Existing shop primer on steel framing being modified, cut, or framed into with new steel. ____________________________________________________________________________ IBI/114475 Section 02 82 02 – Lead-Based Paint Handling Procedures Page 2 of 7 B.The minimum criteria by which the work shall be completed during disturbance of lead-based paint are defined in these documents. 1.4 CODES AND REGULATIONS A.The Contractor shall assume full responsibility and liability for the compliance with all applicable Federal, State, and local regulations pertaining to work practices, hauling and disposal, protection of workers, visitors to the site, and persons occupying areas adjacent to the site. The Contractor is responsible for providing medical examinations and maintaining medical records of personnel as required by the applicable Federal, State, and local regulations. The Contractor shall hold the Owner and Engineer harmless for failure to comply with any applicable work, hauling, disposal, safety, health or other regulation on the part of himself, his employees, or his subcontractors. B.Federal Requirements which govern lead-based paint handling procedures or hauling and disposal of lead-based paint waste materials include but are not limited to, the following: 1.U.S. Department of Labor, Occupational Safety and Health Admin- istration (OSHA) – 29 CFR 1926.62 2.U.S. Department of Housing and Urban Development (HUD) – Guidelines For the Evaluation and Control of Lead-Based Paint Hazards in Housing 3.U.S. Environmental Protection Agency (EPA) – Lead; Renovation, Repair, and Painting Program – 40 CFR 745 a.Certification Required - Beginning on April 22, 2010 contractors performing renovation, repair and painting projects that disturb lead-based paint in homes, child care facilities, and schools built before 1978 must be certified and must follow specific work practices to prevent lead contamination. Certified Firms must ensure that: i.All individuals performing activities that disturb painted surfaces on behalf of the firm are either certified renovators or have been trained by a certified renovator. ii.A certified renovator is assigned to each renovation and performs all of the certified renovator responsibilities. iii.All renovations performed by the firm are performed in accordance with the work practice standards of the Lead- Based Paint Renovation, Repair, and Painting Program. iv.Pre-renovation education requirements of the Lead-Based Paint Renovation, Repair, and Painting Program are performed. v.The program’s recordkeeping requirements are met. b.Training Required - Renovators are required to be certified by April 22, 2010. A certified renovator must successfully complete an eight-hour initial training course, including two hours of hands on training, offered by an accredited training provider. The course ____________________________________________________________________________ IBI/114475 Section 02 82 02 – Lead-Based Paint Handling Procedures Page 3 of 7 completion certificate serves as proof of certification. The Certified Renovator: i. Must provide on-the-job-training to workers on the work practices they will be using in performing their assigned tasks. ii. Must be physically present at the work site when warning signs are posted, while the work-area containment is being established, and while the work-area cleaning is performed. iii. Must regularly direct work being performed by other individuals to ensure that the work practices are being followed, including maintaining the integrity of the containment barriers and ensuring that dust or debris does not spread beyond the work area. iv. Must be available, either on-site or by telephone, at all times renovations are being conducted. v. Must have with them at the work site copies of their initial course completion certificate and their most recent refresher course completion certificate. vi. Must prepare required records. 1.5 ADMINISTRATIVE, SUPERVISORY AND WORKING PERSONNEL A. Lead-based Paint Project Supervisor: Provide a full-time Project Supervisor who is experienced in administration and supervision of lead-based paint projects including work practices, protective measures for building and personnel, handling and disposal procedures, etc. This person is the Contractor's Representative responsible for compliance with all applicable federal, state and local regulations, particularly those relating to lead-based paint. The Supervisor must have completed a course in lead-based paint handling procedures. The Supervisor is to be a Competent Person as required by OSHA in 29 CFR 1926. B. Lead-Based Paint Handlers: All lead-based paint handlers must have completed a course in lead-based paint handling procedures. Train, in accordance with 29 CFR 1926, all workers in the dangers inherent in handling lead-based paint and breathing lead dust and in proper work procedures and personal and area protective measures. 1.6 DAILY LOG A. The Contractor Shall: Maintain a daily log documenting the dates and time of but not limited to, the following items: 1. Meetings; purpose, attendees, brief discussion. 2. Visitations; authorized and unauthorized. 3. Personnel, by name, entering and leaving the work area. ____________________________________________________________________________ IBI/114475 Section 02 82 02 – Lead-Based Paint Handling Procedures Page 4 of 7 4.Special or unusual events, i.e. barrier breaching, equipment failures, accidents. 5.OSHA air monitoring tests and test results. 6.Documentation of Contractor's completion of the following: a.Inspection of work area preparation prior to start of removal and daily thereafter. b.Removal of any sheet plastic barriers c.Contractor's inspections prior to encapsulation, enclosure or any other operation that will conceal the condition of lead-based painted materials or the substrate from which such materials have been removed. d.Removal of waste materials from work area. e.Decontamination of equipment (list items). f.Contractor’s final inspection. 7.Provide three (3) copies of this log to the Engineer at the completion of the project. 1.7 INSPECTION A.Prior to commencement of work, the Contractor shall inspect areas in which work will be performed, and prepare a listing of damage to structure, surfaces, equipment or of surrounding properties which could be misconstrued as damage resulting from the work. 1.8 STOP WORK A.If the Owner or the Engineer presents a written stop work order immediately and automatically stop all work. All work areas shall be sealed and made safe in accordance with HUD guidelines. Do not recommence work until authorized in writing by Engineer. 1.9 TESTING LABORATORY SERVICES A.The Owner’s Representative will perform wipe sampling in accordance with HUD –Guidelines For the Evaluation and Control of Lead-Based Paint Hazards in Housing – Chapter 15. B.The Contractor shall conduct his own personal monitoring and laboratory testing to meet OSHA 29 CFR 1926.62. This monitoring and laboratory testing shall be provided by the Contractor at no additional cost to the Owner. C.Additional testing and analysis required as a result of failing test results during the course of the project or for clearance monitoring shall be the financial responsibility of the Contractor. ____________________________________________________________________________ IBI/114475 Section 02 82 02 – Lead-Based Paint Handling Procedures Page 5 of 7 D. The Contractor shall conduct Toxicity Characteristic Leachate Procedure Analysis (TCLP) to determine if the contents of waste may be disposed as construction debris or as a hazardous waste. 1.10 TEMPORARY FACILITIES A. Temporary Water Service Connection: All connections to the Owner's hot and cold-water system shall include backflow protection provided by the Contractor. Valves shall be temperature and pressure rated for operation of the temperatures and pressures encountered. After completion of use, connections and fittings shall be removed without damage or alteration to existing water piping and equipment. Leaking or dripping valves shall not be allowed. B. Electrical Service: The Contractor shall provide a grounded temporary electric power service and distribution system of sufficient size, capacity, and power characteristics to accommodate performance of work during the construction period. Install temporary lighting adequate to provide sufficient illumination for safe work and traffic conditions in every area of work. Protect each circuit with a ground fault circuit interrupter (GFCI) of proper size located in the temporary panel. Do not use outlet type GFCI devices. Lockout all existing power to or through the work area. Unless specifically noted otherwise existing power and lighting circuits to the Work Area are not to be used. 1.11 WORKER PROTECTION A. The Contractor shall require all workers to adhere to HUD guidelines and OSHA regulations. B. OSHA 1926.62 requires the Contractor to conduct an Initial Exposure Assessment, including personal air sampling and analysis, to determine if any employee may be exposed to lead at or above the action level. C. Hygiene facilities and practices including requirements that workers NOT eat, drink, smoke, chew tobacco or gum, or apply cosmetics in the Work Area; change areas, showers, eating facilities and hand washing facilities are outlined in OSHA 1926.62. D. Respiratory protection including respirator selection, respirator usage and respirator program is outlined in OSHA 1926.62 and OSHA 1910.134. E. Protective work clothing and equipment including provision and use, and cleaning and replacement is outlined in OSHA 1926.62. F. Housekeeping requirements including maintenance of lead free surfaces, clean- up and HEPA vacuuming are outlined in OSHA 1926.62. G. Medical surveillance including biological monitoring is outlined in OSHA 1926.62. H. Medical removal protection is outlined in OSHA 1926.62. ____________________________________________________________________________ IBI/114475 Section 02 82 02 – Lead-Based Paint Handling Procedures Page 6 of 7 2 PART 2 PRODUCTS NOT APPLICABLE 3 PART 3 EXECUTION 3.1 LEAD -BASED PAINT HANDLING PROCEDURES A.Lead-based paint disturbance including handling and containerization of lead- based paint and painted components shall be completed in strict accordance with the standard protocols established by HUD including, but not limited to, decontamination and waste removal procedures. B.Interior and exterior work area protection according to HUD – Guidelines For the Evaluation and Control of Lead-Based Paint Hazards in Housing – Chapter 8 - includes plasticizing floors, airlock flaps on doorways, warning signs, lockout of HVAC and removal of furniture and equipment. C.Interior and exterior work area cleanup according to HUD – Guidelines For the Evaluation and Control of Lead-Based Paint Hazards in Housing – Chapter 14 – includes HEPA vacuuming and wet-cleaning procedures. D.Approved paint removal methodology: 1.Heat gun operated below 1,100 F. 2.HEPA equipped mechanical tools 3.W et scraping 4.Chemical removal (not methylene chloride) E.Prohibited paint removal methodology: 1.Open flame burning or torching. 2.Machine grinding or sanding without HEPA. . 3.Uncontaminated hydroblasting or high pressure washing. 4.Abrasive blasting or sandblasting without HEPA. 5.Methylene chloride based chemical removers. F.All systems which may be disturbed in the performance of the work, located either inside or outside of the work area, including but not limited to electrical system, plumbing system, speaker system, fire alarm system, smoke alarm system, computer system, telecommunications system, clock system, etc. shall be protected from damage. Support systems as necessary to prevent damage during the performance of the work. Any damage to systems during the ____________________________________________________________________________ IBI/114475 Section 02 82 02 – Lead-Based Paint Handling Procedures Page 7 of 7 performance of lead-based paint handling procedures is the responsibility of the Contractor. G. Work Areas shall be isolated from the surrounding environment in accordance with HUD regulations. H. Work Areas shall be placarded with signs that conform to HUD and OSHA standards. 3.2 TRANSPORT AND DISPOSAL A. The Contractor shall dispose of all removed materials in accordance with NYS and HUD regulations. B. Lead-based paint materials which have been removed from the building shall not be stored at the site overnight unless in a locked dumpster or locked truck. 3.3 PROJECT DECONTAMINATION A. The Work Area shall be cleaned in accordance with HUD guidelines and to the satisfaction of the analytical testing laboratory technician. B. After the area has been cleaned and is determined to be dry, the contractor and the Environmental Consultant shall perform a complete Visual Inspection of the entire Work Area. If any debris, residue, dust or other matter is found the Contractor shall repeat final cleaning and continue decontamination procedure from that point. C. If Clearance Criteria are not met, repeat Final Cleaning and continue Decontamination procedure from that point. The Contractor will be responsible for the cost incurred by the Owner for additional testing after the Decontamination has been repeated. 3.4 REPAIRS AND FINAL CLEANING A. Prior to leaving the site and prior to final payment for the work, the Contractor shall repair all damages made to building structure(s) (except those structures scheduled for demolition) including, but not limited to, nail holes, duct tape marks, etc. from the temporary barrier system. The finishes shall be patched to match the existing colors and textures. All miscellaneous materials generated by the Contractor’s activities shall be removed and properly disposed of as deter- mined by the Engineer. END OF SECTION IBI/114475 05 01 70.61 - 1 SECTION 05 01 70.61 DECORATIVE METAL REPAIR PART 1 - GENERAL 1.1 SUMMARY A.Section Includes: 1.Decorative metal repairs as follows: a.Repairing metal and replacing damaged and missing components in place. b.Removing metal for shop repair and replacement of components; reinstalling repaired metal. c.Painting steel uncovered during the Work. d.Installing wood rails supported by or attached to decorative metal railings or brackets. 1.2 REFERENCES A.American Welding Society Standards: 1.A5.1/A5.1M:2012 Specification for Carbon Steel Electrodes for Shielded Metal Arc Welding. 2.A5.2/A5.2M:2018 Specification for Carbon and Low Alloy Steel Rods for Oxyfuel Gas Welding. 3.A5.5/A5.5M:2014 Specification for Low-Alloy Steel Electrodes for Shielded Metal Arc Welding. 4. A5.8M/A5.8:2011-AMD1 Specification for Filler Metals for Brazing and Braze Welding. 5.A5.11/A5.11M:2018 Specification for Nickel and Nickel-Alloy Welding Electrodes for Shielded Metal Arc Welding. 6. A5.15-90 (R2016) Specification for Welding Electrodes and Rods for Cast Iron. 7.A5.18/A5.18M:2017 Specification for Carbon Steel Electrodes and Rods for Gas Shielded Arc Welding. 8. A5.28/A5.28M:2005 (R2015) Specification for Low-Alloy Steel Electrodes and Rods for Gas Shielded Arc Welding. 9. A5.31M/A5.31:2012 Specification for Fluxes for Brazing and Braze Welding. 10.C1.4M/C1.4:2017, Specification for Resistance Welding of Carbon and Low-Alloy Steels. 11. D11.2-89 (R2006), Guide for Welding Iron Castings. 12.G2.1M/G2.1:2012, Guide for the Joining of Wrought Nickel-Based Alloys. 1.3 PREINSTALLATION MEETINGS A.Preinstallation Conference: Conduct conference at Project site. IBI/114475 05 01 70.61 - 2 1.4 SUBMITTALS A. Shop Drawings: 1. Include plans, elevations, and sections showing locations and extent of repair and replacement work, with enlarged details of replacement parts indicating materials, profiles, methods of attachment, accessory items, and finishes. 2. Include field-verified dimensions. B. Samples: For the following: 1. Newel caps to verify profile with existing material. 2. Each type of new material to be used for replacing existing or missing decorative metal. 3. Fittings and brackets. 4. Each type of exposed connection between components. Show method of finishing components at connections. 5. Each type of anchor and miscellaneous support in required finishes. C. Testing: Provide tests and results of type of metals requiring welding. D. Procedures: Provide written procedures for welding different types of metals involved in the restoration of stair railing systems. 1.5 QUALITY ASSURANCE A. Mockups: Prepare mockup of decorative metal repair processes on existing surfaces to demonstrate aesthetic effects and to set quality standards for materials and execution and for fabrication and installation. 1. Extension of newel posts at one landing including post weldment and top rail installation. 2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing. 3. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion. 1.6 DELIVERY, STORAGE, AND HANDLING A. Pack, deliver, and store decorative metal items in suitable packs, heavy-duty cartons, or wooden crates; surround with sufficient packing material to ensure that products are not deformed, cracked, or otherwise damaged. B. Store decorative metal inside a well-ventilated area, protected from weather, moisture, soiling, abrasion, extreme temperatures, and humidity. IBI/114475 05 01 70.61 - 3 PART 2 - PRODUCTS 2.1 PERFORMANCE REQUIREMENTS A.Structural Performance: Railings and handrails, including attachment to building construction, shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated: 1.Uniform load of 50 lbf/ft. (0.73 kN/m) applied in any direction. 2.Concentrated load of 200 lbf (0.89 kN) applied in any direction. 3.Uniform and concentrated loads need not be assumed to act concurrently. 2.2 METAL MATERIALS A.General: Provide decorative metal materials made of the alloys, forms, and types that match existing metals and have the ability to receive finishes matching existing finishes unless otherwise indicated. Exposed-to-view surfaces exhibiting imperfections inconsistent with existing materials are unacceptable. B.Source Limitation for Replacement Cast Materials: Obtain castings for decorative metal repair from single source from single manufacturer with resources to provide materials of consistent quality in appearance and physical properties. C.Steel: Standard and grade designated below for each form required: 1.Tubing: Cold formed, ASTM A500/A500M. 2.Steel Plate, Shapes, and Bars: ASTM A36/A36M. 3.Steel Bars: Mild steel; ASTM A29/A29M, Grade 1010. 4.Steel Sheet: ASTM A1008/A1008M, cold-rolled commercial steel sheet; matte finish; suitable for exposed applications. D.Cast Iron: Standard designated below for each type of casting: 1. Gray-Iron Castings: ASTM A48/A48M, Class 30. 2.Malleable-Iron Castings: ASTM A47/A47M, grade as recommended in writing by fabricator for type of use indicated. 2.3 PREPARATORY CLEANING MATERIALS A.Abrasive Materials: 1.Abrasives for Ferrous Metal Cleaning: Aluminum oxide paper, emery paper, fine steel wool, steel scrapers, and steel-wire brushes of various sizes. B.Antirust Coating: Fast-curing, lead- and chromate-free, self-curing, universal modified- alkyd primer according to MPI #23 (surface-tolerant, anticorrosive metal primer). 1.Surface Preparation: Use coating requiring no better than SSPC-SP 2, "Hand Tool Cleaning" or SSPC-SP 3, "Power Tool Cleaning" surface preparation according to manufacturer's literature or certified statement. IBI/114475 05 01 70.61 - 4 2. VOC Limit: Use coating with a VOC content of 400 g/L (3.3 lb/gal.) or less. 2.4 FASTENERS A. Fasteners: Fasteners of the same basic metal as fastened metal unless otherwise indicated. Use metals that are noncorrosive and compatible with each metal joined. 1. Match existing fasteners in material and in type of fastener unless otherwise indicated. 2. Use concealed fasteners for interconnecting decorative metal components and for attaching them to other work unless exposed fasteners are unavoidable or the existing fastening method]. 3. For exposed fasteners, use Phillips-type machine screws of head profile flush with metal surface unless otherwise indicated. 4. Finish heads of exposed fasteners to match finish of metal fastened unless otherwise indicated. B. Anchors, General: Use bolt heads of same basic metal as fastened metal unless otherwise indicated. Use metals that are noncorrosive and compatible with each metal anchored. C. Post-Installed Structural or Non-Structural Anchors: Fastener systems; with working capacity greater than or equal to the design load, according to an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC01 or AC58 as appropriate for the substrate. 1. Uses: Securing railings and handrails to masonry. 2. Material for Interior Locations: Carbon-steel components zinc-plated to comply with ASTM B633 or ASTM F1941 (ASTM F1941M), Class Fe/Zn 5, unless otherwise indicated. 2.5 MISCELLANEOUS MATERIALS A. Welding Electrodes and Filler Metal: Select according to AWS specifications for metal alloy welded; use metal type and alloy as recommended in writing by producer of metal to be welded or filled and as required for color match, strength, and compatibility in fabricated items. B. Brazing Rods for Cast-Iron Components: Type and alloy as recommended in writing by brazing-rod manufacturer and as required for strength and compatibility in fabricated items. C. Metal-Patching Compound: Two-part, polyester-resin metal-patching compound; knife- grade formulation as recommended in writing by manufacturer for type of metal repair indicated, tooling time required for the detail of work, and site conditions. Compound shall be produced for filling metal that has deteriorated because of corrosion. Filler shall be capable of filling deep holes and spreading to feather edge. IBI/114475 05 01 70.61 - 5 D.Anchoring Cement: Factory-packaged, nonshrink, nonstaining, hydraulic-controlled expansion cement formulation for mixing with water at Project site to create pourable anchoring, patching, and grouting compound. 1.Water-Resistant Product: At exterior locations, provide formulation that is resistant to erosion from water exposure without needing protection by a sealer or waterproof coating and that is recommended in writing by manufacturer for exterior use. E.Other Products: Select materials and methods of use based on the following, subject to approval of a mockup: 1.Previous effectiveness in performing the work involved. 2.Little possibility of damaging exposed surfaces. 3.Consistency of each application. 4.Uniformity of the resulting overall appearance. 5.Do not use products or tools that could do the following: a.Remove, alter, or in any way harm the present or future condition of existing surfaces, including surrounding surfaces not in the Contract. b.Leave an unintended residue on surfaces. 2.6 METAL FABRICATION A.Fabricate repairs of decorative metal items and components in sizes and profiles to match existing decorative metal, with accurate curves, lines, and angles. Mill joints to a tight, hairline fit. B.Provide uniform, neat seams with minimum exposure of welds. C.Provide rebates, lugs, and brackets necessary to assemble components and to attach to existing work. Drill and tap for fasteners. Use concealed fasteners where possible; use exposed fasteners to match existing work. D.Comply with AWS for recommended practices in welding and brazing. Provide welds behind finished surfaces without distorting or discoloring exposed side. Clean exposed welded joints of flux, and dress exposed and contact surfaces. 1.Use materials and methods that match color of base metal, minimize distortion, and develop maximum strength and corrosion resistance. 2.Remove flux immediately. 3.At exposed connections, match contours of adjoining surfaces, and finish exposed surfaces smooth and blended so no roughness shows after finishing. 2.7 FINISHES, GENERAL A.Appearance of Finished Work: Noticeable variations in same piece are not acceptable. Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast. IBI/114475 05 01 70.61 - 6 2.8 FERROUS METAL FINISHES A. Finish Primer: Primer complying with applicable requirements in 09 91 13 – Exterior Painting and 09 91 23 – Interior Painting for finish painting of primed existing metal. PART 3 - EXECUTION 3.1 DECORATIVE METAL REPAIR, GENERAL A. Repair Appearance Standard: Repaired surfaces are to have a uniform appearance as viewed from two feet away by Architect. B. Test existing metals requiring welds for type of metal and proper procedures for welding, brazing, or soldering according to the American Welding Society’s Soldering Handbook and Welding Handbook. C. Mechanical Non-Lead Coating Removal: Sand coating down to metal using a minimum of three steps of sanding using a finer grit at each progressive step. D. Remove paint that is tested to contain lead as specified in Section 02 82 02 – Lead- based Paint Handling Procedure. E. In repairing items, disturb remaining existing work as minimally as possible. F. Repair Decorative Metal Item: Match existing materials and features. G. Repair decorative metals by patching, piecing-in, splicing, or otherwise reinforcing metals with new metal matching existing metal. H. Replace Decorative Metal Component: Where indicated, duplicate and replace items with new metal matching existing metal. I. Weld base metal material as required in PART 1.2.A American Welding Society reference section above. J. Grind all welds, brazing, and soldering flush to the contours of the base metal. 3.2 REMOVAL, REPAIR, AND REINSTALLATION A. Reinstalling Railing Posts: After posts have been inserted into sleeves, fill annular space between post and sleeve with anchoring cement, mixed and placed to comply with anchoring material manufacturer's written instructions. Leave anchorage joint exposed, wipe off surplus anchoring material, and leave 1/8-inch (3-mm) buildup sloped away from post. B. Anchoring Existing Wood Rails: Secure wood rails to metal subrail or brackets from bottom of wood rail. Make fastener heads flush to metal surface. IBI/114475 05 01 70.61 - 7 3.3 PRIMING A.Repair Primer: Apply immediately after completing a repair. B.Finish Primer: Apply as soon after cleaning as possible. 3.4 FINISHING A.Finish coating as specified in Section 09 91 23 – Interior Painting. END OF SECTION IBI/114475 05 52 13 - 1 SECTION 055213 PIPE AND TUBE RAILINGS 1.1 SUMMARY A. Section Includes: 1. Steel pipe and tube railings. B. Related Requirements: 1. Section 057300 "Decorative Metal Railings" for ornamental railings fabricated from pipes and tubes. 1.2 COORDINATION A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' written recommendations to ensure that shop primers and topcoats are compatible with one another. B. Coordinate installation of anchorages for railings. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation. C. Schedule installation so wall attachments are made only to completed walls. Do not support railings temporarily by any means that do not satisfy structural performance requirements. 1.3 SUBMITTALS A. Product Data: For the following: 1. Grout, anchoring cement, and paint products. B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work. C. Samples: For each type of exposed finish required. 1. Wall and newel post mounting flanges. D. Welding certificates. E. Product Test Reports: For pipe and tube railings, for tests performed by a qualified testing agency, according to ASTM E894 and ASTM E935. IBI/114475 05 52 13 - 2 1.4 QUALITY ASSURANCE A.Welding Qualifications: Qualify procedures and personnel according to the following: 1.AWS D1.1/D1.1M, "Structural Welding Code - Steel." 1.5 FIELD CONDITIONS A.Field Measurements: Verify actual locations of existing walls, newel posts, railings, and other construction contiguous with metal fabrications by field measurements before fabrication. PART 2 - PRODUCTS 2.1 PERFORMANCE REQUIREMENTS A.Structural Performance: Railings, including attachment to building construction, shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated: 1.Top Rails of Guards: a.Uniform load of 50 lbf/ ft. (0.73 kN/m) applied in any direction. b.Concentrated load of 200 lbf (0.89 kN) applied in any direction. c.Uniform and concentrated loads need not be assumed to act concurrently. 2.2 METALS, GENERAL A.Metal Surfaces, General: Provide materials with smooth surfaces, without seam marks, roller marks, rolled trade names, stains, discolorations, or blemishes. B.Flanges and Anchors: Cast or formed metal of same type of material and finish as supported rails unless otherwise indicated. 2.3 STEEL AND IRON A.Tubing: ASTM A500 (cold formed) or ASTM A513; radiused corners at ¼ inch. B.Pipe: ASTM A53/A53M, Type F or Type S, Grade A, Standard Weight (Schedule 40), unless another grade and weight are required by structural loads. 1.Provide galvanized finish for exterior installations and where indicated. C.Plates, Shapes, and Bars: ASTM A36/A36M. D.Cast Iron: Either gray iron, ASTM A48/A48M, or malleable iron, ASTM A47/A47M, unless otherwise indicated. IBI/114475 05 52 13 - 3 2.4 FASTENERS A. General: Provide the following: 1. Ungalvanized-Steel Railings: Plated steel fasteners complying with ASTM B633 or ASTM F1941 (ASTM F1941M), Class Fe/Zn 5 for zinc coating. 2. Provide exposed fasteners with finish matching appearance, including color and texture, of railings. B. Fasteners for Anchoring Railings to Other Construction: Select fasteners of type, grade, and class required to produce connections suitable for anchoring railings to other types of construction indicated and capable of withstanding design loads. C. Post-Installed Anchors: Torque-controlled expansion anchors or chemical anchors capable of sustaining, without failure, a load equal to 6 times the load imposed when installed in unit masonry and 4 times the load imposed when installed in concrete, as determined by testing according to ASTM E488/E488M, conducted by a qualified independent testing agency. 1. Material for Interior Locations: Carbon-steel components zinc-plated to comply with ASTM B633 or ASTM F1941 (ASTM F1941M), Class Fe/Zn 5, unless otherwise indicated. 2.5 MISCELLANEOUS MATERIALS A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded. B. Etching Cleaner for Galvanized Metal: Complying with MPI#25. C. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and compatible with paints specified to be used over it. D. Shop Primers: Provide primers that comply with Section 099113 "Exterior Painting" and Section 099123 "Interior Painting." E. Intermediate Coats and Topcoats: Provide products that comply with Section 099113 "Exterior Painting" and Section 099123 "Interior Painting." F. Anchoring Cement: Factory-packaged, nonshrink, nonstaining, hydraulic-controlled expansion cement formulation for mixing with water at Project site to create pourable anchoring, patching, and grouting compound. 1. Water-Resistant Product: At exterior locations provide formulation that is resistant to erosion from water exposure without needing protection by a sealer or waterproof coating and that is recommended by manufacturer for exterior use. IBI/114475 05 52 13 - 4 2.6 FABRICATION A.General: Fabricate railings to comply with requirements indicated for design, dimensions, member sizes and spacing, details, finish, and anchorage, but not less than that required to support structural loads. B. Shop assemble railings to full extent, field splicing is not acceptable. C.Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on exposed surfaces. D.Form work true to line and level with accurate angles and surfaces. E.Cut, reinforce, drill, and tap as indicated to receive finish hardware, screws, and similar items. F.Connections: Fabricate railings with either welded or nonwelded connections unless otherwise indicated. G.Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings. 1.Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals. 2.Obtain fusion without undercut or overlap. 3.Remove flux immediately. 4.At exposed connections, finish exposed surfaces smooth and blended so no roughness shows after finishing and welded surface matches contours of adjoining surfaces. H.Nonwelded Connections: Connect members with concealed mechanical fasteners and fittings. Fabricate members and fittings to produce flush, smooth, rigid, hairline joints. 1.Fabricate splice joints for field connection using an epoxy structural adhesive if this is manufacturer's standard splicing method. I.Form Changes in Direction as Follows: 1.By bending. J.For changes in direction made by bending, use jigs to produce uniform curvature for each repetitive configuration required. Maintain cross section of member throughout entire bend without buckling, twisting, cracking, or otherwise deforming exposed surfaces of components. K.Close exposed ends of railing members with prefabricated end fittings. L.Provide wall returns at ends of wall-mounted handrails unless otherwise indicated. Close ends of returns unless clearance between end of rail and wall is 1/4 inch (6 mm) or less. IBI/114475 05 52 13 - 5 M. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and anchors to interconnect railing members to other work unless otherwise indicated. 1. At brackets and fittings fastened to plaster or gypsum board partitions, provide crush-resistant fillers or other means to transfer loads through wall finishes to structural supports and prevent bracket or fitting rotation and crushing of substrate. 2.7 STEEL AND IRON FINISHES A. Galvanized Railings: 1. Hot-dip galvanize exterior steel railings, including hardware, after fabrication. 2. Comply with ASTM A123/A123M for hot-dip galvanized railings. 3. Do not quench or apply post galvanizing treatments that might interfere with paint adhesion. B. Preparing Galvanized Railings for Shop Priming: After galvanizing, thoroughly clean railings of grease, dirt, oil, flux, and other foreign matter, and treat with etching cleaner. C. For nongalvanized-steel railings, provide nongalvanized ferrous-metal fittings, brackets, fasteners, and sleeves; however, galvanize anchors to be embedded in exterior concrete or masonry. D. Preparation for Shop Priming: Prepare uncoated ferrous-metal surfaces to comply with SSPC-SP 3, "Power Tool Cleaning." E. Primer Application: Apply shop primer to prepared surfaces of railings unless otherwise indicated. Comply with requirements in SSPC-PA 1, "Shop, Field, and Maintenance Painting of Steel," for shop painting. Primer need not be applied to surfaces to be embedded in concrete or masonry. 1. Shop prime uncoated railings with universal shop primer unless indicated. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Fit exposed connections together to form tight, hairline joints. B. Perform cutting, drilling, and fitting required for installing railings. Set railings accurately in location, alignment, and elevation; measured from established lines and levels and free of rack. 1. Do not weld, cut, or abrade surfaces of railing components that are coated or finished after fabrication and that are intended for field connection by mechanical or other means without further cutting or fitting. 2. Set posts plumb within a tolerance of 1/16 inch in 3 feet (2 mm in 1 m). IBI/114475 05 52 13 - 6 3.Align rails so variations from level for horizontal members and variations from parallel with rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet (6 mm in 3.5 m). C.Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials. 1.Coat, with a heavy coat of bituminous paint, concealed surfaces of aluminum that are in contact with grout, concrete, masonry, wood, or dissimilar metals. D.Adjust railings before anchoring to ensure matching alignment at abutting joints. E.Fastening to In-Place Construction: Use anchorage devices and fasteners where necessary for securing railings and for properly transferring loads to in-place construction. 3.2 RAILING CONNECTIONS A.Nonwelded Connections: Use mechanical or adhesive joints for permanently connecting railing components. Seal recessed holes of exposed locking screws using plastic cement filler colored to match finish of railings. B.Welded Connections: Use fully welded joints for permanently connecting railing components. Comply with requirements for welded connections in "Fabrication" Article whether welding is performed in the shop or in the field. C.Expansion Joints: Install expansion joints at locations indicated but not farther apart than required to accommodate thermal movement. Provide slip-joint internal sleeve extending 2 inches (50 mm) beyond joint on either side, fasten internal sleeve securely to one side, and locate joint within 6 inches (150 mm) of post. 3.3 ANCHORING POSTS A.After posts are inserted into existing sleeves, fill annular space between post and sleeve with anchoring cement, mixed and placed to comply with anchoring material manufacturer's written instructions. B.Cover anchorage joint with flange of same metal as post, attached to post with set screws. C.Leave anchorage joint exposed with 1/8-inch (3-mm) buildup, sloped away from post. 3.4 ATTACHING RAILINGS A.Anchor railing ends at walls with round flanges anchored to wall construction and connected to railing ends using nonwelded connections. B.Anchor railing ends to metal surfaces with flanges bolted to metal surfaces and connected to railing ends using nonwelded connections. IBI/114475 05 52 13 - 7 3.5 ADJUSTING AND CLEANING A. Clean by washing thoroughly with clean water and soap and rinsing with clean water. B. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with the same material as used for shop painting to comply with SSPC-PA 1 requirements for touching up shop- painted surfaces. 1. Apply by brush or spray to provide a minimum 2.0-mil (0.05-mm) dry film thickness. C. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas, and repair galvanizing to comply with ASTM A780/A780M. 3.6 PROTECTION A. Protect finishes of railings from damage during construction period with temporary protective coverings approved by railing manufacturer. Remove protective coverings at time of Substantial Completion. END OF SECTION IBI/114475 09 91 13 SECTION 09 91 13 EXTERIOR PAINTING PART 1 - GENERAL 1.1 SUMMARY A.Section includes surface preparation and application of exterior coating systems on the following substrates: 1.Exterior Substrates: a.Galvanized metal. 1.2 DEFINITIONS A.Gloss Level 3: 10 to 25 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D 523, an eggshell finish. B.Gloss Level 5: 35 to 70 units at 60 degrees, according to ASTM D 523, a semi-gloss finish. C.Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D 523, a gloss finish. D.Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D 523, a high- gloss finish. 1.3 ACTION SUBMITTALS A.Product Data: For each type of product indicated. Include preparation requirements and application instructions. B.Samples for Initial Selection: For each type of topcoat product indicated. C.Samples for Verification: For each type of coating system and in each color and gloss of topcoat indicated. 1.Submit Samples on rigid backing, 8 inches (200 mm) square. 2.Step coats on Samples to show each coat required for system. 3.Label each coat of each Sample. 4.Label each Sample for location and application area. D.Product List: For each product indicated, include the following: 1.Cross-reference to paint system and locations of application areas. Use same designations indicated on Drawings and in schedules. IBI/114475 09 91 13 2. VOC content. 1.4 DELIVERY, STORAGE, AND HANDLING A. Delivery and Handling: Deliver products to Project site in an undamaged condition in manufacturer's original sealed containers, complete with labels and instructions for handling, storing, unpacking, protecting, and installing. Packaging shall bear the manufacturer's label with the following information: 1. Product name and type (description). 2. Batch date. 3. Color number. 4. VOC content. 5. Environmental handling requirements. 6. Surface preparation requirements. 7. Application instructions. B. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F (7 deg C). 1. Maintain containers in clean condition, free of foreign materials and residue. 2. Remove rags and waste from storage areas daily. 1.5 FIELD CONDITIONS A. Apply coatings only when temperature of surfaces to be coated and surrounding air temperatures are between 50 and 95 deg F (10 and 35 deg C). B. Do not apply coatings when relative humidity exceeds 85 percent; at temperatures less than 5 deg F (3 deg C) above the dew point; or to damp or wet surfaces. C. Do not apply exterior coatings in snow, rain, fog, or mist. D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work. 1. If suspected hazardous materials are encountered, do not disturb; immediately notify Architect and Owner. IBI/114475 09 91 13 PART 2 - PRODUCTS 2.1 MANUFACTURERS A.Basis-of -Design Product: Subject to compliance with requirements, provide The Sherwin-Williams Company; products indicated or comparable product from one of the following: 1.Benjamin Moore & Co. 2.PPG Architectural Finishes, Inc. 3.Tnemec Inc. B.Source Limitations: Obtain paint materials from single source from single listed manufacturer. 1.Manufacturer's designations listed on a separate color schedule are for color reference only and do not indicate prior approval. 2.2 EXTERIOR COATINGS, GENERAL A.Material Compatibility: 1.Provide materials for use within each coating system that are compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience. 2.For each coat in a coating system, provide products recommended in writing by manufacturers of topcoat for use in coating system and on substrate indicated. 3.Provide products of same manufacturer for each coat in a coating system. B.VOC Content: Products shall comply with VOC limits of authorities having jurisdiction. 1.Flat Paints and Coatings: 50 g/L. 2.Nonflat Paints and Coatings: 150 g/L. 3.Primers, Sealers, and Undercoaters: 200 g/L. 4.Anti-Corrosive and Anti-Rust Paints Applied to Ferrous Metals: 250 g/L. 5. Zinc-Rich Industrial Maintenance Primers: 340 g/L. 6.Pre-Treatment Wash Primers: 420 g/L. 7.Floor Coatings: 100 g/L. 8.Shellacs, Clear: 730 g/L. 9.Shellacs, Pigmented: 550 g/L. IBI/114475 09 91 13 C. Colors: As selected by Architect from manufacturer's full range. 2.3 SOURCE QUALITY CONTROL A. Testing of Coating Materials: Owner reserves the right to invoke the following procedure: 1. Owner will engage the services of a qualified testing agency to sample coating materials. Contractor will be notified in advance and may be present when samples are taken. If coating materials have already been delivered to Project site, samples may be taken at Project site. Samples will be identified, sealed, and certified by testing agency. 2. Testing agency will perform tests for compliance with product requirements. 3. Owner may direct Contractor to stop applying paints if test results show materials being used do not comply with product requirements. Contractor shall remove noncomplying coating materials from Project site, pay for testing, and recoat surfaces coated with rejected materials. Contractor will be required to remove rejected materials from previously coated surfaces if, on recoating with complying materials, the two coatings are incompatible. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers. Where acceptability of substrate conditions is in questions, apply samples and perform in-situ testing to verify compatibility, adhesion, and film integrity of new paint application. 1. Report, in writing, conditions that may affect application, appearance, or performance of paint. B. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers. C. Proceed with coating application only after unsatisfactory conditions have been corrected; application of coating indicates acceptance of surfaces and conditions. 3.2 PREPARATION A. Clean substrates of substances that could impair bond of coatings, including dust, dirt, oil, grease, and incompatible paints and encapsulants. 1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce coating systems indicated. IBI/114475 09 91 13 3.3 APPLICATION A.Apply high-performance coatings according to manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual." 1.Use applicators and techniques suited for coating and substrate indicated. B.Tint each undercoat a lighter shade to facilitate identification of each coat if multiple coats of the same material are to be applied. Tint undercoats to match color of finish coat, but provide sufficient difference in shade of undercoats to distinguish each separate coat. C.If undercoats or other conditions show through final coat, apply additional coats until cured film has a uniform coating finish, color, and appearance. D.Apply coatings to produce surface films without cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections. Produce sharp glass lines and color breaks. 3.4 FIELD QUALITY CONTROL A.Dry Film Thickness Testing: Owner will engage the services of a qualified testing and inspecting agency to inspect and test coatings for dry film thickness. 1.Contractor shall touch up and restore coated surfaces damaged by testing. 2.If test results show that dry film thickness of applied coating does not comply with coating manufacturer's written recommendations, Contractor shall pay for testing and apply additional coats as needed to provide dry film thickness that complies with coating manufacturer's written recommendations. 3.5 CLEANING AND PROTECTION A.At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site. B.After completing coating application, clean spattered surfaces. Remove spattered coatings by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces. 3.6 EXTERIOR COATING SCHEDULE A.Galvanized-Metal Substrates: 1.Pigmented Polyurethane over Vinyl Wash Primer System: a.Prime Coat: Primer, vinyl wash: S-W DTM Wash Primer, B71Y1, at 0.7 to 1.3 mils dry, per coat. b.First Topcoat: Polyurethane, two-component, pigmented, matching second topcoat. IBI/114475 09 91 13 c.Second Topcoat: Polyurethane, two-component, pigmented, semi-gloss, (Gloss Level 5), MPI #72: S-W Acrolon 218 HS Acrylic Polyurethane, B65- 650 Series, at 3.0 to 6.0 mils dry, per coat. d.Second Topcoat: Polyurethane, two-component, pigmented, gloss, (Gloss Level 6), MPI #72: S-W Acrolon 218 HS Acrylic Polyurethane, B60-600 Series, at 3.0 to 6.0 mils dry, per coat. END OF SECTION IBI/114475 09 91 23 SECTION 09 91 23 INTERIOR PAINTING PART 1 - GENERAL 1.1 SUMMARY A.Section includes surface preparation and application of interior coating systems on the following substrates: 1.Interior Substrates: a. Steel. 1.2 DEFINITIONS A.Gloss Level 3: 10 to 25 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D 523, an eggshell finish. B.Gloss Level 5: 35 to 70 units at 60 degrees, according to ASTM D 523, a semi-gloss finish. C.Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D 523, a gloss finish. D.Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D 523, a high- gloss finish. 1.3 ACTION SUBMITTALS A.Product Data: For each type of product indicated. Include preparation requirements and application instructions. B.Samples for Initial Selection: For each type of topcoat product indicated. C.Samples for Verification: For each type of coating system and in each color and gloss of topcoat indicated. 1.Submit Samples on rigid backing, 8 inches (200 mm) square. 2.Step coats on Samples to show each coat required for system. 3.Label each coat of each Sample. 4.Label each Sample for location and application area. D.Product List: For each product indicated, include the following: 1.Cross-reference to paint system and locations of application areas. Use same designations indicated on Drawings and in schedules. IBI/114475 09 91 23 2. VOC content. 1.4 QUALITY ASSURANCE A. Mockups: Apply mockups of each coating system indicated to verify preliminary selections made under sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution. 1. Architect will select one surface to represent surfaces and conditions for application of each coating system specified in Part 3. a. Architect will designate items or areas required. 2. Final approval of color selections will be based on mockups. a. If preliminary color selections are not approved, apply additional mockups of additional colors selected by Architect at no added cost to Owner. 3. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing. 4. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion. 1.5 DELIVERY, STORAGE, AND HANDLING A. Delivery and Handling: Deliver products to Project site in an undamaged condition in manufacturer's original sealed containers, complete with labels and instructions for handling, storing, unpacking, protecting, and installing. Packaging shall bear the manufacturer's label with the following information: 1. Product name and type (description). 2. Batch date. 3. Color number. 4. VOC content. 5. Environmental handling requirements. 6. Surface preparation requirements. 7. Application instructions. B. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F (7 deg C). 1. Maintain containers in clean condition, free of foreign materials and residue. 2. Remove rags and waste from storage areas daily. IBI/114475 09 91 23 1.6 FIELD CONDITIONS A.Apply coatings only when temperature of surfaces to be coated and surrounding air temperatures are between 50 and 95 deg F (10 and 35 deg C). B.Do not apply coatings when relative humidity exceeds 85 percent; at temperatures less than 5 deg F (3 deg C) above the dew point; or to damp or wet surfaces. C.Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work. 1.If suspected hazardous materials are encountered, do not disturb; immediately notify Architect and Owner. PART 2 - PRODUCTS 2.1 MANUFACTURERS A.Basis-of -Design Product: Subject to compliance with requirements, provide The Sherwin-Williams Company; products indicated or comparable product from one of the following: 1.Benjamin Moore & Co. 2.PPG Architectural Finishes, Inc. 3.Tnemec Inc. B.Source Limitations: Obtain paint materials from single source from single listed manufacturer. 1.Manufacturer's designations listed on a separate color schedule are for color reference only and do not indicate prior approval. 2.2 INTERIOR COATINGS, GENERAL A.Material Compatibility: 1.Provide materials for use within each coating system that are compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience. 2.For each coat in a coating system, provide products recommended in writing by manufacturers of topcoat for use in coating system and on substrate indicated. 3.Provide products of same manufacturer for each coat in a coating system. B.VOC Content: Products shall comply with VOC limits of authorities having jurisdiction. 1.Flat Paints and Coatings: 50 g/L. 2.Nonflat Paints and Coatings: 150 g/L. IBI/114475 09 91 23 3. Primers, Sealers, and Undercoaters: 200 g/L. 4. Anti-Corrosive and Anti-Rust Paints Applied to Ferrous Metals: 250 g/L. 5. Zinc-Rich Industrial Maintenance Primers: 340 g/L. 6. Pre-Treatment Wash Primers: 420 g/L. 7. Floor Coatings: 100 g/L. 8. Shellacs, Clear: 730 g/L. 9. Shellacs, Pigmented: 550 g/L. C. Low-Emitting Materials: Interior coatings shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers." D. Colors: As selected by Architect from manufacturer's full range. 2.3 SOURCE QUALITY CONTROL A. Testing of Coating Materials: Owner reserves the right to invoke the following procedure: 1. Owner will engage the services of a qualified testing agency to sample coating materials. Contractor will be notified in advance and may be present when samples are taken. If coating materials have already been delivered to Project site, samples may be taken at Project site. Samples will be identified, sealed, and certified by testing agency. 2. Testing agency will perform tests for compliance with product requirements. 3. Owner may direct Contractor to stop applying paints if test results show materials being used do not comply with product requirements. Contractor shall remove noncomplying coating materials from Project site, pay for testing, and recoat surfaces coated with rejected materials. Contractor will be required to remove rejected materials from previously coated surfaces if, on recoating with complying materials, the two coatings are incompatible. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers. Where acceptability of substrate conditions is in questions, apply samples and perform in-situ testing to verify compatibility, adhesion, and film integrity of new paint application. IBI/114475 09 91 23 1.Report, in writing, conditions that may affect application, appearance, or performance of paint. B.Substrate Conditions: C.Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers. D.Proceed with coating application only after unsatisfactory conditions have been corrected; application of coating indicates acceptance of surfaces and conditions. 3.2 PREPARATION A.Clean substrates of substances that could impair bond of coatings, including dust, dirt, oil, grease, and incompatible paints and encapsulants. 1.Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce coating systems indicated. B.Steel Substrates: Remove rust, loose mill scale, and shop primer if any. Clean using methods recommended in writing by paint manufacturer but not less than the following: 1.SSPC-SP 11, "Power Tool Cleaning to Bare Metal." C.Shop-Primed Steel Substrates: Clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with the same material as used for shop priming to comply with SSPC-PA 1 for touching up shop-primed surfaces. 3.3 APPLICATION A.Apply coatings according to manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual." 1.Use applicators and techniques suited for coating and substrate indicated. B.Tint each undercoat a lighter shade to facilitate identification of each coat if multiple coats of the same material are to be applied. Tint undercoats to match color of finish coat, but provide sufficient difference in shade of undercoats to distinguish each separate coat. C.If undercoats or other conditions show through final coat, apply additional coats until cured film has a uniform coating finish, color, and appearance. D.Apply coatings to produce surface films without cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections. Produce sharp glass lines and color breaks. 3.4 FIELD QUALITY CONTROL A.Dry Film Thickness Testing: Owner will engage the services of a qualified testing and inspecting agency to inspect and test coatings for dry film thickness. IBI/114475 09 91 23 1. Contractor shall touch up and restore coated surfaces damaged by testing. 2. If test results show that dry film thickness of applied coating does not comply with coating manufacturer's written recommendations, Contractor shall pay for testing and apply additional coats as needed to provide dry film thickness that complies with coating manufacturer's written recommendations. 3.5 CLEANING AND PROTECTION A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site. B. After completing coating application, clean spattered surfaces. Remove spattered coatings by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces. 3.6 INTERIOR COATING SCHEDULE A. Steel Substrates: 1. Pigmented Polyurethane over Epoxy Primer System: a. Prime Coat: Primer, epoxy, anit-corrosive, for metal: S-W Macropoxy 646- 100, B58-600 Series. B73-620 Series, at 5 to 10 mils dry, per coat. b. Intermediate Coat: Polyurethane, two-component, pigmented, matching topcoat. c. Topcoat: Polyurethane, two-component, pigmented, gloss: S-W Waterbased Acrolon 100 Polyurethane, B65-720 Series, at 2.0 to 4.0 mils dry, per coat. END OF SECTION