•Requisition #2 - Finger Lakes Construction Company
By Comm. Ewanicki: Seconded by Comm. Allan
RESOLVED, That requisition #2 of Finger Lakes Construction Company for
construction services in connection with the Fall Creek subdrainage
system, be approved in the amount of $75,031.92.
Discussion followed on the floor. / 72,//7
A vote on the resolution resulted as follows:
•
Carried Unanimously
Bill --Finger Lakes Construction Company
By Comm. Banfield: Seconded by Comm._ Schickel_.f_.__.._____._.___.
RESOLVED, That bill #3 from Finger Lakes Construction Company in
connection with subsurface drainage system along Fall C eek, in the
• ��
amount of $27,109.46, be approved. �
Carried Unanimously
Requisition #4 --Finger Lakes Construction Co.
By Comm. Banfield: Seconded by Comm. Ewanicki
RESOLVED, That Requisition #4 in the contract of Finge Lakes Construction
Company for Fall Creek subdrainage, be approved in the amount of
$16,778.84.
Carried Unanimously
Bill Finger Lakes Construction Company
By Comm. Banfield: Seconded by Comm. Schickel 61A3/7(/
RESOLVED, That a final bill for the retainage due the Finger Lakes
Construction Company in connection with the Fall Creek drainage
system project be approved in the amount of $3,000.
Carried Unanimously
Change Order Tl --Finger Lakes Construction Co. j
Ry- Comm. Banfield: Ch : SeOCrderd#1 in the contract of m. Allan )Finlg er Lakes Construction
RESOLVED, That Change r
Company for field construction changes in the Fall Creek subdrainage system,
be approved in the amount°of add $10,282.77. These changes are shown on
the attached sheet.
Carried Unanimously
•
•
-2-
Invoice--Erdman, Anthony Associates
By Comm. Banfield: Seconded by Comm. Ewanicki.
RESOLVED, That an invoice from Erdman, Anthony Associates
services in connection with the Fall Creek subdrai.n, beta
amount of $1,506.17. Carried Urfa
for professional
proved in the
nimoc
usly
Bill--Modjeski & Masters Comm. Allan
By Comm. Banfield: Seconded by
RESOLVED, That a bill from Modjeski & Masters for engineering services
0 in connection with the design and specification for th. A bang Street
Bridge, be
approved in the amount of $3,454.00. •2 /yy!
pp Carrie Dnanimously
-4-
Shopping Carts in Creeks
Comm. Cleveland proposed that the Common Council be requested to
draft some foLul of legislation that would require the supermarkets
to assume responsibility for taking the shopping carts out of the
creeks or for reimbursing the City for cleaning the creeks of the
shopping carts. ////1,
Alderman Bordoni agreed to refer the recommendation to the Council.
4110
-5 -
East Clinton Street Bridge
By Comm. Allan: Seconded by Comm. Ewanicki
RESOLVED, That the Common Council be requested to establish a capital
fund for the improvement of the East Clinton Street Bridge over Six
Mile Creek in the amount of $12,000.
Discussion followed on the floor.
A vote on the resolution resulted as follows:
0/77
Carried Unanimously
Agreement with Modjeski & Masters - Professional Services
By Comm. Allan: Seconded by Cc3m] . Ewanicki V3k7RESOLVED, That contingent on the above action by the Common Cocil,
the Superintendent be authorized to enter into an agreement with
Modjeski & Masters for professional services for the design of the
rehabilitation of the East Clinton Street Bridge over Six Mile Creek;
the terms of the agreement to be materially the same as covered in the
June 11, 1979 letter from Modjeski & Masters to the Superintendent.
Carried Unanimously
—Bill from Modjeski & Masters J� ) 7q
By Comm. Macinnes: Seconded by Coutut. Ewanicki I
RESOLVED, That a bill. from Modjeski & Masters for engineering services.;
in the preparation of plans and specifications for the rehabilitation
of the East Clinton Street Bridge over Six Mile Creek be approved in
the amount of $4,089.54.
Carried Unanimously
Drainage Area
Alderman Bordoni reported on the problem of drainage in the low area
between Elmira and Spencer Roads, and also on the poor condition of the
railroad bed on the upper side of the road.
Discussion followed on the floor.
•
•
i* 9
-7-
Approach to Foot Bridge=-Cascadilla Creek at Adams Street
A derman Bordoni called attention to the approaches to the foot bridge
at Adams Street over Cascadilla Creek, commenting that the elderly
have a problem using the bridge because of the steepness and the
absence of a handrail. In addition, children have been jumping their
bicycles from the bridge, creating a safety problem. He suggested
that the Board study the possibility of erecting an L-shaped handrail
on the approaches to the bridge to aid the elderly, and prevent the
children from jumping their bicycles.
Discussion followed on the floor.
Resolution
By Coll'. Walker; Seconded by Comm.
RESOLVED, that the item of concern
bridge at Adams Street be referred
•
Cleveland
over the approaches to the foot
to the Creeks and Bridges Committee.
Carried Unanimously
Finger Lakes Constr. - request for payment - Fall Creek subdrainage system 1
Erdman, Anthony Associates - request for payment - Fall Creek subdrain 2
Modjeski & Masters - request for payment - Albany Street Bridge 3
Cleaning creeks of Shopping Carts - Request for legislation 4
E. Clinton St. Bridge - Establishment Capital Project and Agreement with
Modjeski & masters for rehabilitation of Bridge; -Request for payment 5
Drainage problems - Elmira Rd./Spencer Rd. area