HomeMy WebLinkAboutMN-IURA-2025-05-23
108 E. Green St.
Ithaca, NY 14850 (607) 274-6565
MINUTES
ITHACA URBAN RENEWAL AGENCY BOARD
9:00 A.M., Friday, May 23rd, 2025
Common Council Chambers, Third Floor (City Hall)
108 E. Green St., Ithaca, NY 14850
Members: Karl Graham, Vice-Chair; Shaianne Osterreich; Siobhan Hull
Excused: Donna Fleming; Robert G. Cantelmo (Mayor), Chair
Vacancies: 0
Common Council Liaison: (not present)
IURA Staff: Nels Bohn; Charles Pyott [virtual]
City Staff: None.
Guests: None.
I. Call to Order
Graham called the meeting to order at 9:06 A.M.
II. Agenda Additions/Deletions
None.
III. Public Comments
None.
IV. Review of Meeting Minutes: April 25, 2025
Graham moved, seconded by Osterreich, to approve the meeting minutes with no modifications.
Carried Unanimously: 3-0
V. Neighborhood Investment Committee (NIC)
A. Annual Appointment of Committee Chairperson
Graham explained that the Committee elected him as Vice-Chair and nominated Osterreich as Chair of the
Committee.
Approved: 7/25/25
IURA Minutes May 23, 2025 Page 2 of 4 Graham moved, seconded by Hull:
2025 Appointment of IURA Neighborhood Investment Committee Chairperson
WHEREAS, IURA By-laws provide that the committee membership shall elect its own committee Vice-
Chairperson and nominate a candidate for committee Chairperson for consideration by the Agency,
and
WHEREAS, per the By-laws, an Agency member shall fill either the committee Chairperson or
committee Vice-Chairperson position, and
WHEREAS, officers of each committee serve a one-year term, but continue to hold office until their
successor is selected or appointed, and
WHEREAS, the current Committee Chairperson and Vice-Chairperson are Karl Graham and Shaianne
Osterreich, and
WHEREAS, the committee elected Karl Graham as Vice-Chairperson and nominated Shaianne
Osterreich as Chairperson of the NI Committee, now, therefore be it
RESOLVED, that Shaianne Osterreich be appointed as Chairperson of the IURA Neighborhood
Investment Committee.
Carried Unanimously: 3-0
B. Committee Chairperson Report
Graham reported that committee member Brian Toy was moving out of state and expressed gratitude for
his service.
VI. Economic Development Committee (EDC)
A. Annual Appointment of Committee Chairperson
Hull explained that the committee appointed Leslie Ackerman as Vice-Chair and nominated Hull to be the
committee Chair.
Graham moved, seconded by Osterreich:
2025 Appointment of IURA Economic Development Committee Chairperson
WHEREAS, the IURA By-laws provide that the committee membership shall elect its own committee Vice-
Chairperson and nominate to the IURA Board a member to serve as Chairperson of the Committee, and
WHEREAS, IURA By-laws further require at least one officer must be an IURA member, and
WHEREAS, officers of each committee serve a one-year term, but continue to hold office until their
successor is selected or appointed, and
IURA Minutes May 23, 2025 Page 3 of 4
WHEREAS, the current committee officers are:
Chairperson: Robert Cantelmo
Vice-Chairperson: Leslie Ackerman, and
WHEREAS, at their May 13, 2025, meeting the Chair called for nominations for Vice-Chair and Chair of the
IURA Economic Development Committee, and
WHEREAS, the Economic Development Committee elected Leslie Ackerman as Vice-Chairperson and
nominated Siobhan Hull as Chairperson; now, therefore be it
RESOLVED, that the IURA hereby appoints Siobhan Hull as Chairperson of the IURA Economic
Development Committee.
Carried Unanimously: 3-0
B. Committee Chairperson Report
Hull reported that, at the meeting on May 13, 2025, Danielle Szabo, Director of Workforce Innovation,
presented on the IAED Workforce Initiative Programs to inform the committee about the training pathway
programs available in the county.
VII. New/Other/Old Business
A. Consider Rescheduling IURA Meetings to the 4th Thursday of Each Month at 9:00 AM (beginning
August 28th, 2025)
Bohn explained that he received no objections to changing the meeting day to the 4th Thursday of each
month and would follow up to confirm. The Board members agreed that, tentatively, meetings would be
held on the 4th Thursday of each month, starting August 28, 2025.
B. Review of IURA Grant Summary: April 2025
Bohn reviewed the Grants Summary, explaining that the left-hand “On Schedule” column calls out any projects
(with a ) that are not progressing on schedule and may need attention. All loan payments are current. All
lease payments are current except for Southside Community Center-RIBS, which owes one month’s rent for a
lease that has expired.
C. REPORTS: IURA Chair, Mayor, Common Council Liaison, & Staff
Mayor’s Report
None.
IURA Chairperson
None.
Common Council Liaison Report
None.
IURA Minutes May 23, 2025 Page 4 of 4
Staff Report
Bohn reported notice was received of the 2025 HUD allocation of HOME Investment Partnerships Program
(HOME) and Community Development Block Grant (CDBG) Program funds, which exceeded the anticipated
amounts.
VIII. Adjournment
The meeting was adjourned by consensus at 9:44 A.M.
— END —