HomeMy WebLinkAbout1983 County Proposition of ?,O
V �
* S
COUNTY OF TOMPKINS
PROPOSITION
ESTABLISHING A PUBLIC UTILITIES SERVICE AGENCY
AND
AUTHORIZING PROJECT NO. 1
To Be Voted Upon
at the
General Election
On November 8, 1983
TEXT OF THE
PROPOSITION
ESTABLISHING A PUBLIC UTILITIES SERVICE AGENCY
AND
AUTHORIZING PROJECT NO. 1.
Shall Resolution No. 194, 1983 entitled "Establishing The
Tompkins County Public Utility Service Agency Pursuant To
Article 14-A Of The General Municipal Law Of The State Of New
York and Authorizing Project No. 1" be approved.
Establishment of the Agency shall not result in any increase in
real property taxes, be approved?
1) The Resolution establishes the Tompkins County Public
Service Agency with authority to construct,purchase,lease,own,
acquire, use, and/or operate facilities for the purpose of
furnishing itself and the people with economical electric and gas
service. The County Board of Representatives is designated as the
Agency.
2) The Resolution requires that prior to the initiation of any
projects substantially different from previously authorized
projects, the project proposal approved by the Agency shall be
submitted to public referendum for approval of the electors.
3) The Resolution authorizes the initiation of Project No. I to
acquire and thereafter resell hydroelectric and/or such other
economical forms of electric energy from the Power Authority of
the State of New York, the State of New York'and any State
agency, any other municipal corporation, and any private or
public corporation and further provides that the Tompkins
County Public Utility Service Agency shall lease or contract for
the use of the transmission, substation,and distribution facilities
currently owned and available from others such as the Power
Authority of the State of New York and the New York State
Electric and Gas Corporation without the need for condemnation
or construction and to furnish such power to the County and/or
for resale to the inhabitants of the County;and also stated that the
estimated value of the energy to Tompkins County Public Utility
Service Agency is $1,600,000, based on present allocations and
costs, but in no event shall there be any net costs, nor net profit,
nor capital costs to the Agency. The rural and residential
customers of Tompkins County in 1982 used 200,000,000
kilowatt hours of electrical energy, 10% of which came from the
Power Authority of the State of New York. 10% equals
20,000,000 kilowatt hours at an average cost of 8c per kilowatt
hours equaling $1,600,000. Therefore, the value of the energy
which the Agency hopes to attract is $1,600,000.
SECTION 5. This Resolution and the notice of submission
thereof shall be published in the newspapers designated by the
Board of Representatives, once in each week for six consecutive
weeks immediately proceeding the November 8, 1983 general
election.
* * s * r
FORM OF SUBMISSION OF THE
PROPOSITION
ESTABLISHING A PUBLIC UTILITIES SERVICE AGENCY
AND
AUTHORIZING PROJECT NO. 1
Shall Resolution No. 194, 1983 entitled "Establishing The
Tompkins County Public Utility Service Agency Pursuant To
Article 14-A Of The General Municipal Law Of The State Of New
York and Authorizing Project No. I,"which Project No. I will be
to receive and redistribute through existing power lines any
available allocation of low-cost hydroelectric power and will not
result in any increase in real property taxes, be approved?
* * s
A full copy of the Resolution adopted by the Tompkins County Board of
Representatives on the 9th day of August 1983 establishing the Tompkins County Public
Utility Service Agency is available at the Office of the Board of Elections,128 East Buffalo
Street, Ithaca, New York.