HomeMy WebLinkAboutREPORT OF ENGINEER March 1984VILLAGE OF CAYUGA HEIGHTS REPORT OF ENGINEER March 1984 SEWAGE TREATMENT PLANT Because only one acceptable bid was received for providing a sludge conveyor on February 21, 1984, at a price of $21,785, the Engineers at Calocerinos & Spina recommended that the requests for bids be readvertised and a new bid opening be set for 2:00 p.m., March 20. Plant operator, Gleason, and the Engineer drove to Calocerinos & Spina, Liverpool, N.Y., and then to Baldwinsville, N.Y. and Utica, N.Y. to inspect installations of belt filter presses manufactured by Ashbrook- Simon - Hartley. SIDEWALKS Additional report material was submitted to the Board at a special meeting March 3, to proceed on proposed plans for 1983 -84 sidewalk construction. Acceptance of the proposed plan is needed as soon as possible. VILLAGE OF CAYUGA HEIGHTS REPORT OF ZONING OFFICER March 1984 One zoning permit was issued for an addition at an estimated construction cost of $10,000. One sign permit was issued. The first building permit was issued for an addition for $10,000. Other requests for building permits have been received. Because the proposed construction did not meet the State Building Code, the permits were not issued. Fire Inspector Dymek and the Engineer are working on forms and procedures for the enforcement of the State Building Code.