REPORT OF PUBLIC WORKS
December 20, 2004
TO: BOARD OF TRUSTEES
FROM: Ed Quick, Working Supervisor
PERIOD: November 2004
REPORT BY DEPARTMENT:
1. PUBLIC WORKS
a. Street System: We finished all the paving on Klinewoods and Hanshaw
Roads. The Tompkins County Highway Dept. brought their shoulder
machine in to put gravel in.
b. Storm Water System: We have been keeping the catch basins cleaned of
leaves.
c. Water System: No Report
d. Sewer System: No Report
e. Solid Waste: We had 21 UFPO’s ~ DSNY. There is a copy of one on the
back of this report so everyone can see what they look like.
i. Equipment: DPW Fuel Consumption for the month:
Gas = 164.60 Diesel = 1253.30
f. Buildings and Grounds: We have been cleaning up the yard that has
accumulated stuff over the summer, such as a huge dirt pile, old melted
pipe, etc.
g. Personnel: No report
h. Safety: I’m waiting to hear from our new Insurance Company so I can set
up a Safety Meeting.