Re: Monthly Report- August 2012
During the month of August the crew worked on White Park Rd, starting the
sidewalk. We intend on completing this by the end of September.
Also we dedicated a crew to start and proceed with the office addition.
We have been able to keep up with all the regularly scheduled maintenance, garbage,
and brush pickup. We also finished the road stripping without any OT.
We also had 2 water main breaks that were repaired, 1 at 319 Highland Rd, and the
other was a transmission main on Pleasant grove Rd.
Sincerely; Jeffrey Frisbie ASPW
REPORT OF PUBLIC WORKS
Thursday, September 06, 2012
TO: BOARD OF TRUSTEES
FROM: Jeffrey Frisbie; Asst. Superintendent of Public Works
PERIOD: August 2012
REPORT BY DEPARTMENT:
1. PUBLIC WORKS
a. Street System: We are working on the sidewalk on White Park Rd. We
intend on finishing the sidewalk in September.
b. Storm Water System: We have been continuously cleaning catch basins
and monitoring our creeks to keep them clear of debris...
c. Water System: We had 2 breaks that were repaired.
d. Sewer System: We have plans on continuing flushing...
e. Buildings and Grounds: We continue to clean the yard as time allows.
f. Personnel: Nothing to report…