Monday, Thursday, September 06, 2012
To: The Honorable Mayor Supron
Members of the Board of Trustees
Village of Cayuga Heights
Re: Monthly Report- August 2012
During the month of August the crew worked on White Park Rd, starting the
sidewalk. We intend on completing this by the end of September.
Also we dedicated a crew to start and proceed with the office addition.
We have been able to keep up with all the regularly scheduled maintenance, garbage,
and brush pickup. We also finished the road stripping without any OT.
We also had 2 water main breaks that were repaired, 1 at 319 Highland Rd, and the
other was a transmission main on Pleasant grove Rd.
Sincerely; Jeffrey Frisbie ASPW