Friday, October 05, 2012
To: The Honorable Mayor Supron
Members of the Board of Trustees
Village of Cayuga Heights
Re: Monthly Report- September 2012
During the month of September the crew worked on White Park Rd, completing the
sidewalk.
Also we dedicated a crew proceed with the office addition.
We have been able to keep up with all the regularly scheduled maintenance, garbage,
and brush pickup.
We also have prepared all the equipment for the upcoming Leaf collection, and
salting of the roads.
In addition, we are in the process of planning and scheduling he water main
replacement project on Forrest Dr.
Sincerely; Jeffrey Frisbie ASPW
REPORT OF PUBLIC WORKS
Friday, October 05, 2012
TO: BOARD OF TRUSTEES
FROM: Jeffrey Frisbie; Asst. Superintendent of Public Works
PERIOD: September 2012
REPORT BY DEPARTMENT:
1. PUBLIC WORKS
a. Street System: We have completed the sidewalk on White Park Rd.
b. Storm Water System: We have been continuously cleaning catch basins
and monitoring our creeks to keep them clear of debris...
c. Water System: We are in the planning and scheduling process for the
Forrest Dr. project.
d. Sewer System: We have plans on continuing flushing...
e. Buildings and Grounds: We continue to clean the yard as time allows.
f. Personnel: Nothing to report…
g. Safety: Nothing to Report…