Re: Monthly Report- October 2011
During the month of October, we have completed all scheduled capital projects, we
also was able to start various other small projects that we needed to address throughout
the village… in addition to that our Leaf crew has been collecting leafs on the regular
scheduled days, and our regular scheduled duties have been on schedule.
We had 1 water main break that occurred at 1010 tripphammer rd. that was
repaired…
Winter deicing salt has been ordered and on site for winter conditions…
Pleasant Gr. Road Bus Shelter is approximately 98 percent completed, with the only
work left is the bus shelter pad to be installed…
Kendall Crosswalk is completed…
Sincerely;
Jeffrey Frisbie
Asst Supervisor DPW