Mayor Gilmore called the meeting to order at 12:05 PM, explaining that the special
meeting was called for Site Plan Approval of the Chemung Canal Trust Company bank
building. Mayor Gilmore also stated that due to the excused absence of Clerk Manning,
Attorney Elena Flash would be the minute taker for this meeting.
There were two agenda items:
1. The demolition permit was distributed to the Board for information purposes. The
Mayor reported that the work is underway. Supt. Cross reported that initial site
investigation has been done, but can not be completed until removal of the slab
which will be completed after all debris is removed. Preliminary testing indicated
no issues. Time for completion of removal of the slab is approximately one more
week.
Trustee Bors asked whether the gas station had footer drains in response to public
comment about drainage. Supt. Cross indicated that determination will be made
when the removal is complete. Supt. Cross further explained that runoff would be
handled by a stormwater management plan.
2. Final Site Plan for Chemung Canal Trust Company, Cayuga Heights branch.
Architect John Snyder offered a presentation regarding a change to the plan to
include stone around the building. (Refer to Sheet A200 attached to Trustee
packet.) Roofing remains as previously proposed. The architect showed material
samples for roofing and stone – color choices to be finalized to coordinate with
other buildings in the area, including Marcham Hall. The Board discussed the
length of life of the building and maintenance.
Supt. Cross and John Snyder explained the new plan regarding site lighting (see
L104 attached to Trustee packet), including low lighting along signage, entry and
walkway, two pole fixtures identified to be 12’high and low uplight for flag pole.
Safety and winter hours concerns will be addressed with walkway lighting.
2
Supt. Cross reviewed the resolution. Chief Boyce discussed the safety and traffic
concerns. No Left Turn will be permitted at exit onto Pleasant Grove Road. Joe
Perry expressed concern about this decision as not necessary and inconvenient.
Chief Boyce responded that public safety concerns regarding increased traffic are
throughout the day. The Mayor also responded that safety is the primary concern.
Atty. Flash commented that the location of this sign is not on the Chemung site and
the Village can require this as a public safety issue.
Mayor Gilmore also commented about consideration of adding a bike path along
Pleasant Grove Road if funding can be identified, other than municipal funds.
Trustee Bors commented that traffic overall around Community Corners must
continually be evaluated. The Board and the applicant engaged in extensive
discussion of safety issues through the Community Corners area considering speed,
parking, and pedestrians.
The Mayor added that the Planning Board wants to add hours for construction
consistent with the demolition permit. Those hours will be added to the resolution
as item 7.
Supt. Cross clarified that the Mayor and the Village Engineer will stamp and sign
approved drawings and will develop a system for approval going forward.
Motion by Trustee Bors
Seconded by Trustee Donner
Trustees Antil, Bors. Collyer, Donner, and Riesman voted YES
Move to pass Resolution 6355 accepting and adopting the Site Plan for the new
Chemung Canal Bank Building at 909 Hanshaw Road as follows:
RESOLUTION 6355 TO APPROVE SITE PLAN FOR NEW CHEMUNG CANAL
BANK BUILDING AT 909 HANSHAW ROAD
Whereas, Corners Community Center, Inc., as owner, and Chemung Canal Trust
Company, as tenant/developer (together referred to as the “Applicants”), have made an
application to the Village of Cayuga Heights Planning Board for review of a site plan
related to a new building to be constructed at 909 Hanshaw Road, which application
includes drawings LD100, L100-L103, L104, L200, A200-L201 entitled, “Chemung Bank
Building, Community Corners” prepared by John Snyder Architects, dated 5/29/08
(collectively the “Site Plan), and
Whereas, the Zoning Officer has determined that this project is subject to Site Plan Review
according to Village of Cayuga Heights Article IX, Section III.A.1 and has referred the
application to the Village of Cayuga Heights Planning Board for said review, and
Whereas, the Planning Board conducted a public hearing on 4/21/08 to receive comments
on potential impacts of this project, which public hearing was duly advertised in the Ithaca
Journal on 4/11/08, and for which a notice was mailed to all contiguous property owners
on or before 4/14/08,
3
Whereas, the Planning Board has determined that this project is a Type II action in
accordance with 6NYCRR617.5.c.7, and therefore no further review under SEQRA is
required, and
Whereas, the Planning Board has determined that this project is not subject to the
notification requirements set forth in General Municipal Law Sections 239-m and -n, and
Whereas, the Planning Board has carefully considered the Site Plan and all of those factors
set forth in Village of Cayuga Heights Zoning Ordinance Article IX and Local Law 2
Section III.A.1, and
Now, Therefore, the Village of Cayuga Heights Planning Board hereby approves the Site
Plan, subject to the following conditions, which conditions must be met prior to the
issuance of the zoning permits (including the building permit and certificate of occupancy)
as set forth below:
1. Installation of a sign located at the Pleasant Grove Road exit driveway from the
Corners Community Center to read “NO LEFT TURN”, as approved by the Zoning
Officer prior to issuance of a certificate of occupancy.
2. Submittal of final engineering design of a Stormwater Management Plan, including
erosion and sedimentation control, for approval by the Village Engineer prior to
issuance of a building permit.
3. Submittal of a plan to specify the location of routes for construction equipment and
deliveries, for approval by the Village Engineer prior to issuance of a building
permit.
4. Upon completion of demolition, the owner shall provide a final written report by an
environmental consultant acceptable to the Village Engineer showing either that no
environmental contamination existed at the site or that any identified contamination
has been remediated in full compliance with the rules and regulations of the NYS
DEC. This report shall be satisfactory to the Village Engineer in all respects prior
to the issuance of a building permit.
5. All on-building and free standing signs shall conform with the sign provisions of
the Village Zoning Ordinance and will be approved by the Zoning Officer prior to
the issuance of a building permit. Any variation from the zoning ordinance must be
approved by the Zoning Board of Appeals of the Village.
6. All building and grounds exterior lighting must be indicated by type, candle power
and hours of operation and approved by the Zoning Officer, prior to installation.
7. Building construction and delivery of materials to and from the site will be limited
to the hours of 7 am to 7 pm, Monday through Saturday.
Provided all matters brought forth in this resolution, and all those matters previously
discussed and agreed upon by both parties such as design and material improvements to
the structure, are adhered to, The Planning Board authorizes the Zoning Officer to issue a
Zoning Permit pursuant to the above conditions.
Motion by Trustee Antil
Seconded by Trustee Bors
Adjourn the meeting of the Planning Board at 1:49 P.M.
Trustees Antil, Bors. Collyer, Donner, and Riesman voted YES